This work investigates the potential for improved accuracy of a cost-estimating method called weighted reference class forecasting (WRCF) with respect to the traditional reference class forecasting (RCF) method. WRCF is a modification of the RCF method, which uses historical project cost data to produce project cost estimate uplifts. WRCF uses work package-level cost deviations to overcome a limitation of RCF: the unavailability of reference data. However, WRCF has not been validated, raising concerns about the method’s reliability. This case study uses real project data from a utility company in simulated project portfolios and cross-validation to assess the validity of WRCF. The study contributes to the robustness of RCF in practice by providing empirical evidence on the performance of WRCF. Results indicate that WRCF produces more conservative cost estimates than the traditional RCF. In addition, WRCF cost estimates have a higher level of certainty than expected, potentially leading to inflated cost estimates beyond what is intended. This study emphasises the importance of practitioners selecting appropriate WRCF percentiles to avoid excessive conservatism in cost estimates and overallocation of resources. Further research is needed to assess WRCF’s validity across diverse industries and regions, providing insights for practitioners in estimating project cost uplifts.
Article navigation
1 September 2025
Research Article|
April 11 2025
Empirical comparison of weighted and non-weighted reference class forecasting
David Zani
;
Institute of Construction and Infrastructure Management
, ETH Zurich, Zurich, Switzerland
Corresponding author David Zani (zani@ibi.baug.ethz.ch)
Search for other works by this author on:
Bryan T. Adey
Bryan T. Adey
Institute of Construction and Infrastructure Management
, ETH Zurich, Zurich, Switzerland
Search for other works by this author on:
Corresponding author David Zani (zani@ibi.baug.ethz.ch)
Publisher: Emerald Publishing
Received:
June 07 2024
Accepted:
March 12 2025
Online ISSN: 2053-0250
Print ISSN: 2053-0242
© 2025 Emerald Publishing Limited
2025
Emerald Publishing Limited
Licensed re-use rights only
Infrastructure Asset Management (2025) 12 (3): 147–158.
Article history
Received:
June 07 2024
Accepted:
March 12 2025
Citation
Zani D, Adey BT (2025), "Empirical comparison of weighted and non-weighted reference class forecasting". Infrastructure Asset Management, Vol. 12 No. 3 pp. 147–158, doi: https://doi.org/10.1680/jinam.24.00024
Download citation file:
New and popular articles
Suggested Reading
Digital twin adoption, cost accounting, and sustainability in GCC infrastructure systems
Infrastructure Asset Management (November,2025)
Adaptive capabilities for road agencies in emerging economies
Infrastructure Asset Management (June,2018)
Modularisation and offsite in engineering construction: an early decision-support tool
Proceedings of the Institution of Civil Engineers - Civil Engineering (August,2019)
Crossrail project: the execution strategy for delivering London’s Elizabeth line
Proceedings of the Institution of Civil Engineers - Civil Engineering (May,2017)
Procurement and technological innovations of India’s new dedicated freight railways
Proceedings of the Institution of Civil Engineers - Civil Engineering (May,2021)
Related Chapters
Infrastructure digital technology requires systems-thinking
Doing it Differently: Systems for rethinking infrastructure
ROLLER COMPACTED CONCRETE: A NEW WAY IN ALGERIAN DAM CONSTRUCTION
Role of Concrete In Sustainable Development: Proceedings of the International Symposium dedicated to Professor Surendra Shah, Northwestern University, USA held on 3–4 September 2003 at the University of Dundee, Scotland, UK
Cost: A Measure of Project Success
Measures of Sustainable Construction Projects Performance
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.