The ability to recover costs in an extension of time claim can be greatly enhanced if a contractor produces and issues with tender documents a critical path network that clearly shows the floats of all non-critical activities. By merely supplying a computer-generated Gantt chart that may well show the floats in the form of bar extensions, a contractor may not be able to prove adequately which, and to what extent, other activities are affected by a client-originated variation, resulting in an extension of time. This article shows that costs can be recovered over and above the normal site establishment and labour costs associated with an extension of time. At the same time, the client will be able to see to what extent the variation has affected the original completion date.
Article navigation
May 2010
Review Article|
May 01 2010
Briefing: Extension of time claims Available to Purchase
Albert Lester
Albert Lester
Project Manager
London
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
February 16 2009
Accepted:
July 13 2009
Online ISSN: 1751-4312
Print ISSN: 1751-4304
© 2010 Thomas Telford Ltd
2010
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (2010) 163 (2): 47–49.
Article history
Received:
February 16 2009
Accepted:
July 13 2009
Citation
Lester A (2010), "Briefing: Extension of time claims". Proceedings of the Institution of Civil Engineers - Management, Procurement and Law, Vol. 163 No. 2 pp. 47–49, doi: https://doi.org/10.1680/mpal.2010.163.2.47
Download citation file:
Suggested Reading
Managing a programme under the NEC3 ECC contract
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (August,2010)
Briefing: Participation, consensus and adjudication in designing the A3 Hindhead tunnel, UK
Proceedings of the Institution of Civil Engineers - Engineering Sustainability (April,2013)
Simulation of scheduling logic using dynamic functions
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (June,2013)
Workington: a case study in coordination and communication
Proceedings of the Institution of Civil Engineers - Municipal Engineer (September,2015)
Major sporting events—planning for legacy
Proceedings of the Institution of Civil Engineers - Municipal Engineer (December,2007)
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.
