A typical preliminary cost estimation for a building construction project in Indonesia may take weeks and have an error rate varying from around −13 to +27%. The research objectives of this study were thus to determine the factors that influence cost estimation in Indonesia and to develop a support vector regression model to improve the accuracy and reduce the work hours for preliminary cost estimation. The literature review identified 14 factors that have the most influence on cost estimation in Indonesia. Data collection was carried out to gather information randomly on 104 building cases in Indonesia deemed to contain valid information for the proposed model. The model with a radial basis function kernel was established after data trimming, analysis and normalisation. The proposed model was then evaluated and implemented using fivefold cross-validation and yielded an average accuracy of 96% for preliminary cost estimation of building construction projects. The model’s average accuracy was 87%, it was efficient and resulted in significant time savings.
Article navigation
12 February 2019
Research Article|
January 24 2019
Improving preliminary cost estimation in Indonesia using support vector regression
Jieh-Haur Chen
;
Institute of Construction Engineering and Management, National Central University, Taoyuan, Taiwan
(corresponding author: jhchen@ncu.edu.tw)
Search for other works by this author on:
Yu-Min Su;
Yu-Min Su
Assistant Professor
Department of Civil Engineering, National Kaohsiung University of Science and Technology, Kaohsiung, Taiwan
Search for other works by this author on:
Diana Wahyu Hayati;
Diana Wahyu Hayati
Doctoral student
Institute of Construction Engineering and Management, National Central University, Taoyuan, Taiwan
Search for other works by this author on:
Indradi Wijatmiko;
Indradi Wijatmiko
Lecturer
Department of Civil Engineering, University of Brawijaya, Malang, Indonesia
Search for other works by this author on:
Ragil Purnamasari
Ragil Purnamasari
Graduate student
Department of Civil Engineering, University of Brawijaya, Malang, Indonesia
Search for other works by this author on:
(corresponding author: jhchen@ncu.edu.tw)
Publisher: Emerald Publishing
Received:
August 30 2018
Accepted:
December 31 2018
Online ISSN: 1751-4312
Print ISSN: 1751-4304
ICE Publishing: All rights reserved
2019
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (2019) 172 (1): 25–33.
Article history
Received:
August 30 2018
Accepted:
December 31 2018
Citation
Chen J, Su Y, Hayati DW, Wijatmiko I, Purnamasari R (2019), "Improving preliminary cost estimation in Indonesia using support vector regression". Proceedings of the Institution of Civil Engineers - Management, Procurement and Law, Vol. 172 No. 1 pp. 25–33, doi: https://doi.org/10.1680/jmapl.18.00040
Download citation file:
New and popular articles
Suggested Reading
National culture and perceptions of success and failure in projects
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (August,2014)
Knowledge based decision support system for appraisement of sustainable partner under fuzzy cum non-fuzzy information
Kybernetes (January,2018)
A simulation model for generating alternative scenarios
Proceedings of the Institution of Civil Engineers - Urban Design and Planning (September,2008)
Novel passive treatment for mine water discharges
Proceedings of the Institution of Civil Engineers - Water Management (December,2008)
Constant rate of displacement test on ultra-soft soil
Proceedings of the Institution of Civil Engineers - Geotechnical Engineering (June,2008)
Related Chapters
The Role of Operations in a Mega Project
Crossrail Project: Infrastructure Design and Construction
Case studies
Programme Management in Construction
Civil engineering projects
Civil Engineering Procedure
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.