Skip to Main Content
Purpose

Often, public procurement is perceived to be too slow. One prominent factor that impedes procurement time is the so-called “red tape” problem. Red tape represents formal or informal constraints to an organisation’s freedom, i.e. rules and regulation but also influence on key stakeholders. These constraints can lead to procedural delay. This study aims to assess the effectiveness of counter-measures to red tape and their effect on public procurement speed and time.

Design/methodology/approach

This research is imbedded in the case of the German defence industry. Here, several legal and regulatory measures have been taken to reduce procurement time. Using time stamps from the public procurement system of roughly 40,000 procurement procedures in an ex ante /ex post comparison analysis, this study is able to assess different counter-measures and their effectiveness.

Findings

In this case, the overall duration of public procurement decreased by 36.6% over seven years. Findings show that this reduction in duration is correlated with the reduction of red tape as several measures have been taken to reduce regulatory burden. Furthermore, chi-square testing shows dependency between time and red tape.

Social implications

While it is not new that superfluous rules and regulations require critical assessment in public procurement, this study is able to demonstrate the effectiveness of top-down laws and directives which aim to reduce procurement durations. Beyond that, the study calls for the introduction of standardised speed metrics to better monitor performance−time relations in public procurement.

Originality/value

Previous research examined red tape predominantly from a perceptive point of view. In contrast, this study leverages empirical time stamps obtained from an actual procurement system.

When the COVID-19 pandemic struck in early 2020, public institutions across the globe scrambled to procure protective equipment, ventilators and vaccines, only to find themselves entangled in layers of bureaucratic procedure that slowed urgent action (Bundesrechnungshof, 2024; OECD, 2020). A similar dynamic emerged in the wake of the Russian invasion of Ukraine in 2022, where European defence ministries urgently sought to accelerate the procurement of defence material but were frequently hindered by rigid regulatory frameworks and internal compliance rules (Kortukova et al., 2023; Schoeni et al., 2023). These cases highlight a central dilemma in public procurement: the urgent need for speed and responsiveness during crises often clashes with the regulatory safeguards designed to ensure accountability, transparency and fairness (Haase, 2019). Even if unforeseen events like a pandemic or a severe national security threat allow for emergency procedures in public procurement, these striking examples point to the general problem that public procurement is perceived as acting in a system of several goal conflicts with the outcome of being tightly regulated and slow (Tátrai and Nyikos, 2013).

This tension has reignited a longstanding debate in public administration and procurement research regarding the role of red tape, commonly defined as excessive or burdensome regulation that impedes organisational performance (Bozeman, 1993; George et al., 2021). While prior studies have acknowledged the performance implications of red tape, empirical investigations have predominantly relied on perceptual data, measuring stakeholders’ subjective views on procurement time, rather than analysing objective procedural durations (Coursey and Pandey, 2007; Welch and Pandey, 2006). There are only few works that use actual procurement data (e.g. Čudanov et al., 2018; He et al., 2023). The content of research addressing the temporal dimension of procurement (i.e. how long it takes to fulfil demand) often focuses on the comparison of the duration of different procedures (Bagnasco, 2022; Čudanov et al., 2018). He et al. (2023, p. 11), for instance, analysed the time duration of different public procurement procedures and found that “simpler versions of auctions and negotiations, i.e. the open and negotiated procedures, are better at saving time than their more complicated counterparts, i.e. the restricted procedure and competitive dialogue”. Similarly, Čudanov et al. (2018) compared the duration of different public procurement procedure types and found that the procedure type explains around 23% of the duration variability. Vice versa, 77% of the variability is not explained by the procedure type. This points to another finding in the literature that “organisational factors, notably bureaucracy in administrating and coordinating different stages of more complicated award processes […], may better account for slow decision making in public procurement” (He et al., 2023, p. 11). Overall, existing research neglects the regulatory context of procedures and focuses on comparing single procedures, while it is acknowledged that there are significant influential factors like bureaucracy and red tape.

Understanding and explaining procurement duration and speed is also of analytical relevance. For instance, Migliaccio et al. (2010) found that longer procurement durations may positively influence supplier delivery times following contract award. However, the same study reported no significant effect of faster or slower procurement on costs incurred during the execution phase. In a related vein, Prier et al. (2021) criticised existing measures of public procurement speed within the European Union, arguing that they are often biased due to a lack of contextual information, the masking of critical underlying variations or the structural omission of key influencing variables. Consequently, the research gap extends beyond the relationship between red tape and procedural duration to include both the performance implications of procurement speed and the development of more robust, context-sensitive speed metrics.

This article addresses these gaps by empirically analysing how varying levels of red tape affect public procurement duration and speed. Using a large-scale secondary data set of more than 42,000 public procurement procedures conducted in Germany between 2018 and 2024, this study investigates whether and how regulatory intensity correlates with procedural efficiency. Red tape intensity is operationalised through discrete policy phases, including the implementation of a procurement acceleration law and a subsequent directive to reduce internal rules, both aimed at enhancing supply responsiveness in the context of emerging geopolitical threats.

The central research question is thus:

RQ1.

To what extent do reductions in red tape contribute to shorter procurement durations and higher procedural speed in public procurement?

Methodologically, this study applies both descriptive and inferential statistical analyses to actual tender data, capturing time stamps and performance metrics across multiple procurement procedures and regulatory phases. The findings reveal a statistically significant, albeit modest, association between lower red tape levels and faster procurement processes, measured both in terms of average duration and relative speed (bids or volume per day). These results contribute not only to the literature on red tape and procurement performance but also provide actionable insights for policymakers navigating the trade-off between regulation and responsiveness in times of crisis.

The remainder of this article is as follows: In the next section, the theoretical background on red tape as well as extant research on time and speed in public procurement is presented. That section also explains and depicts the study’s analytical framework cumulating in the formulation of a hypothesis. This is followed by a methodology section that introduces the case setting, sampling procedure and a holistic description of the sample. Next, the findings section provides insights into the proper analysis of procedural time stamps. The findings are discussed and subsequently interpreted leading to several implications. The article ends with a brief conclusion that also highlights limitations and opportunities for future research.

Public procurement operates at the intersection of competing goals: efficiency, transparency, accountability, and increasingly, responsiveness to shifting political priorities (Schapper et al., 2006). In times of crisis or geopolitical urgency, governments reprioritise speed over procedural rigour to ensure rapid delivery of critical goods and services (Harland et al., 2021). This recalibration of objectives has direct consequences for procurement timelines. However, this shift towards speed raises important questions. While faster procurement may be desirable in situations of urgent need, particularly in health or defence sectors, acceleration can also entail risks. Shortened timelines may compromise due diligence, reduce competition or limit opportunities for oversight; thus, creating trade-offs between speed and quality, accountability or long-term effectiveness (Haase, 2019; Prier et al., 2021). In the defence domain especially, the complexity, sensitivity and risk associated with procurement activities demand a careful balance between urgency and control. A failure to address this trade-off appropriately bears the risk of severe administrative inefficiencies.

In this light, red tape has long been a central concept in public administration, generally referring to excessive, overly rigid or burdensome regulations and formalities that hinder organisational performance (Bozeman, 1993). The origins of the term date back to the 16th century, when European bureaucracies used literal red ribbons to bind administrative documents (Dickson, 2014). This symbolic gesture that still survives in some modern administrations, such as in Spain. At its core, red tape represents regulatory complexity that impedes timely and efficient action. This may manifest as redundant documentation requirements, prolonged approval chains or rigid compliance rules that limit managerial discretion.

Early research identified red tape as a symptom of institutional inertia, often emerging from well-intentioned accountability mechanisms that eventually become counterproductive (Bretschneider, 1990). Subsequent scholarship has expanded the concept to explore its effects on public service delivery, innovation, performance and organisational behaviour (George et al., 2021; Scott and Pandey, 2005). A key distinction has also been made between internally perceived red tape (as seen through the eyes of bureaucrats) and objectively observable regulatory burdens. In both cases, however, red tape is increasingly linked to negative outcomes, higher costs, longer processing times, lower innovation capacity and diminished responsiveness (Bozeman, 2012).

The present study defines the red tape concept in relation to excessive bureaucratic regulation within state institutions. This manifests itself in the form of internal regulations, processes and bureaucratic obstacles aimed at regulating institutional activities. A concrete example is the often-lengthy approval procedure for projects or decisions in state authorities. While the intention is to ensure transparency and accountability, bureaucratic red tape can often lead to delays and tie up resources. Moreover, the extensive reporting and documentation required by government agencies can also be examples of red tape. While this is intended to create transparency, the high administrative burden can significantly impair efficiency. Red tape therefore represents an unnecessary organisational burden (Cooke et al., 2019), as it limits the performance of both private and public organisations (Jovanović et al., 2022).

Within public procurement, red tape plays an especially critical role. Procurement processes are heavily formalised, often involving multiple stages of planning, budgeting, tendering, contracting and oversight. These steps are embedded in legal and administrative frameworks designed to promote fairness, transparency and the efficient use of public funds. Yet empirical research shows that these same rules can result in significant procedural complexity and rigidity (Davis and Stazyk, 2014; Jovanović et al., 2022). In some instances, the procurement function itself becomes a key driver of red tape, with internal procedures, documentation requirements and formal reviews extending timelines beyond what is necessary for effective control.

Supplier-side barriers to public procurement are well-documented in the “barriers” literature. Small and medium-sized enterprises (SMEs) often face disproportionate burdens when engaging with public tendering processes, including excessive documentation, resource-intensive qualification procedures and a perceived bias towards larger suppliers (Loader, 2007, 2010, 2015). For example, extensive prequalification requirements, such as high insurance thresholds, lengthy track record demands and overly complex specifications, can deter SMEs from bidding or render them uncompetitive (Hoekman and Taş, 2022; Loader, 2015). Furthermore, collaborative procurement strategies, supplier rationalisation and the bundling of contracts to achieve scale economies have been shown to marginalise smaller suppliers by increasing both the volume and complexity of contracts (Loader, 2007). Even where SMEs are willing to engage, the procedural demands and lack of feedback often lead to frustration and disengagement (Loader, 2015), preventing lean and efficient business practices (Loader, 2010).

Procurement red tape is typically operationalised through individual perceptions of procedural restrictiveness. Survey data capture how managers or stakeholders assess the rules governing procurement activities (Coursey and Pandey, 2007; Scott and Pandey, 2005). While useful, these perception-based measures limit analytical precision, particularly when studying time-dependent outcomes. Moreover, some scholars have highlighted that procurement red tape can lead not only to inefficiency, but also to resource waste and corruption risks, as complex procedures may obscure transparency or create bottlenecks that are selectively bypassed (El Benni et al., 2022; Guriev, 2004). One important subdimension is budgeting red tape. This refers to regulations that constrain financial flexibility. Budgetary red tape has been shown to inhibit timely spending or reallocation, even in urgent contexts (Coursey and Pandey, 2007), and thus may further interact with procurement time.

In general, several specific consequences of red tape in procurement settings have been documented in the literature:

  • Cost inflation. Time-consuming regulatory procedures increase transaction costs on both the government and supplier side (El Benni et al., 2022).

  • Reduced competition. SMEs, in particular, may be discouraged from participating due to the complexity of compliance, thus lowering market diversity (Welch and Pandey, 2006).

  • Inefficiency. Excessive administrative demands may require more personnel and time, creating inefficiencies and delays (Bozeman, 1993).

  • Delays. Lengthy processes, especially during the pre-award phase, have been identified as a key symptom of procurement red tape (Coursey and Pandey, 2007; Jovanović et al., 2022).

The dimension of time in public procurement has historically received less empirical attention than cost or quality. Yet procurement performance is closely linked to time, especially when policy priorities demand accelerated delivery. Delays in major public projects. Examples such as the Berlin Brandenburg Airport [originally planned for 5 years, completed in 14 (Kersting and Neuerer, 2020)] or Stuttgart 21 [delayed by at least 7 years (Menzel, 2023; Ministerium für Verkehr Baden-Württemberg, 2023)] illustrate how time overruns affect not just efficiency, but also political credibility and public trust. Delays can also have a significant impact on other types of projects, such as the development of the Boeing 787. The development time for the plane had already been delayed by three years, but the aircraft delivered now appear to be experiencing repeated problems. Production has been repeatedly halted and delivered aircraft have been withdrawn (The New York Times, 2013; Paul, 2018).

Other research disciplines have a more profound conceptual understanding of time than public procurement. In operational management, for instance, the concept of the “right time” is foundational. The 4-R principle (Grochla, 1973, 1992) emphasises the availability of the right product, in the right quantity and quality, at the right time and place. Procurement planning integrates multiple time-based indicators, including requirements determination, budgeting time, awarding time, delivery time and contract execution periods (Holoubek, 2009; Thommen et al., 2020). However, real-world dynamics, such as uncertainty, risk, market volatility, often hinder strict optimisation of time. Differently phrased, theoretical optimisation of time seems possible, but active management of time is far more complicated.

Nonetheless, the performance management literature tries to conceptualise time. With respect to Holoubek (2009), Kortendieck and Stepanek (2019), Kroeber-Riel (1966), Lödding (2016), Tempelmeier (1983) and Thommen et al. (2020), numerous different procurement durations are measured such as:

  • Requirements determination time. Duration of the determination of the optimal type of goods, order quantity and quality of the goods of the required quantity, procurement quantity (total) and order quantity (per call-off).

  • Budgeting time. Duration of the budgeting process for a project.

  • Awarding time. Duration of the awarding procedure.

  • Delivery time. Duration until the physical distribution of the goods to be procured from the time the order is placed.

  • Contract duration. Duration of the contract, which depends on the supplier’s characteristics or material requirements. Contracts for individual requirements or framework agreements with a longer term are created here.

  • Order time. Duration of the decision to place an order until it is placed.

  • Administration time. Duration for creating the replenishment order.

  • Transport time. Delivery time from the supplier until they arrive at the customer.

  • Procurement time. Duration of the period between placing the order and delivery of the goods; it occurs as soon as goods are required that are not kept in stock.

  • Replenishment time/demand coverage time. Is the sum of the lead time of the supplier’s production, the procurement time, the delivery time and the administration time.

  • Procurement lead time. Includes several time spans, such as information or material lead times. These are sometimes decisive for basic procurement decisions, such as a make-or-buy analysis.

  • Goods acceptance time. Time between the arrival of the goods at the ordering party and their availability for production.

A related concept often discussed in the literature is procurement cycle time, defined as the total time elapsed from the initiation of the sourcing process to the final delivery and payment for goods or services (Olupot, 2023). It includes multiple stages, such as needs assessment, tendering, contract award and contract execution. Procurement cycle time functions as a comprehensive process-level indicator that spans both pre- and post-award phases (Olupot, 2023). While useful as a diagnostic metric, it is not easily decomposable or attributable to specific actors or procedural steps, as it is heavily shaped by exogenous factors such as institutional pressures, legal reviews or contractor behaviour (Olupot, 2023; Yeo and Ning, 2006). For this reason, the present study does not address the entire procurement cycle. Rather, focusing on a specific section of the procurement process allows for an in-depth analysis of two analytically tractable time dimensions: duration and speed. In doing so, the study aims to complement the extent research on procurement time by providing more granular evidence on where and how time is consumed or accelerated in public procurement procedures.

Furthermore, recent literature distinguishes between duration and speed as two analytically separate dimensions of performance. Duration refers to the absolute length of time that elapses between two defined points in a process, for example, the number of days between the initiation of a tender and the awarding of a contract. In contrast, speed is a relational metric that captures the amount of output or activity achieved within a given time span, such as the volume of procurement handled per day or the number of bids processed over a specific period. This distinction is important because increasing speed is not synonymous with simply reducing duration. A procurement process could be shorter in time but still inefficient in output, whereas an increase in speed implies both time compression and a proportional increase in performance (Vinton, 1992). Studies such as Prier et al. (2021) have introduced this distinction in the context of decision-making processes, particularly in examining how quickly decisions are made under different governance structures. However, despite its relevance, the application of this distinction to public procurement remains underdeveloped. Most procurement research continues to focus on absolute time measures without linking them to output or efficiency metrics, leaving a gap in understanding how procurement systems perform under time pressure. In this study, procurement speed is operationalised as a relational performance metric, calculated by dividing a defined output variable by elapsed time. This approach contrasts with simple duration measures, which reflect the total time between two events but do not account for the level of activity completed within that period. In the context of public procurement, typical performance outputs include the procurement volume (i.e. the total monetary value of procured goods and services) and the number of tenders processed. Accordingly, this study uses two distinct speed metrics:

  1. procurement volume per time unit; and

  2. tenders processed per time unit.

These indicators reflect not only how long procedures take, but how intensively procurement systems operate within a given time frame.

This distinction is especially important, as faster procurement, understood as higher procurement process speed, has tangible benefits beyond administrative efficiency. From an end-user perspective, accelerated procurement processes enable quicker access to critical goods, services or infrastructure, which is especially vital in sectors relying on responsive operations (OECD, 2020). In emergency contexts, delays in procurement can translate into severe social costs, including unmet medical needs or compromised public safety (Harland et al., 2021; Vecchi et al., 2020). From an institutional perspective, faster procurement also supports improved resource utilisation by aligning procurement timelines more closely with planning, budgeting and implementation cycles (Flynn and Davis, 2017). This reduces idle time, avoids stockouts and prevents costly last-minute interventions or contract amendments (Rutkowski et al., 2022). Moreover, compressed timelines may reduce administrative overhead and monitoring costs, freeing up organisational capacity for strategic functions (McCue and Prier, 2008; Prier and McCue, 2009).

Altogether, while there is an existing and growing body of literature linking red tape to organisational performance, few studies have examined its relationship with objective procurement timelines. To the best of the author’s knowledge, the existing research relies on subjective perceptions of time, typically gathered through surveys, rather than on actual procedural data. This study seeks to fill that gap by providing a rare empirical insight into the temporal dynamics of red tape, using an extensive data set of public procurement procedures to analyse how regulatory intensity correlates with procurement duration and speed.

First, delays of several kinds are a key symptom of procurement red tape (Coursey and Pandey, 2007; Jovanović et al., 2022). Hence, red tape and public procurement duration should have significant statistical relation to each other:

H1.

Red tape and public procurement duration are interdependent.

Second, as outlined above, there is a conceptual distinction between procurement duration and procedural speed (e.g. Prier et al., 2021). Consequently, delays attributed to red tape (Coursey and Pandey, 2007; Jovanović et al., 2022) are expected to affect not only the duration but also the speed of public procurement processes. Speed is contemplated as a relational metric, reflecting the volume of output or activity achieved within a defined time span. This study uses two distinct speed indicators: one based on procurement volume and the other on the number of tenders completed over time. It is assumed that red tape is significantly associated with both speed metrics, reflecting its potential to constrain procedural throughput:

H2a.

Red tape and public procurement speed, measured in procurement volume per time unit, is interdependent.

H2b.

Red tape and public procurement speed, measured in number of tenders processed per time unit, is interdependent.

This research investigates the relation between red tape and time in public procurement. For this purpose, the methodology is based on a secondary data analysis. First, methodological procedures, data source and the case study setting are presented. Thereafter, the operationalisation of red tape is explained, a research hypothesis is phrased and activities to test this hypothesis are explained.

The use of secondary data remains relatively uncommon and methodologically underutilised in public procurement and supply chain research (Busse, 2010). Nevertheless, secondary data analysis can offer substantial advantages, particularly in terms of scale, objectivity and unobtrusiveness. In the context of digital transformation and datafication of public services, data sets capturing actual organisational behaviour (e.g. system-generated time stamps) are increasingly accessible and valuable (Calantone and Vickery, 2010). Still, such data often originate from operational systems rather than academic research designs, making it essential to consider potential biases and cross-validate internal consistency and contextual accuracy.

Unlike many prior studies that rely on perceptual data collected via surveys (e.g. asking stakeholders about their views on procurement duration), this study leverages a rich secondary data set comprising time stamp records from a major public procurement organisation in Germany. The organisation was selected not only for reasons of data accessibility but also due to its methodological relevance. As one of Germany’s largest and most visible public buyers, both in terms of procurement volume and staff, it plays a central role in executing large-scale, often complex procurement procedures. In public and political discourse, the organisation has frequently been labelled as “too slow”, “overly bureaucratic” and “ineffective” (Der Spiegel, 2023), making it a particularly salient case for examining the relationship between red tape and procurement performance.

From a theoretical standpoint, the case offers a meaningful opportunity to study procurement under conditions of high regulatory density and asset specificity. The organisation’s portfolio spans from routine items such as office supplies to complex, defence-related procurement of ships, aircraft and other strategic assets. Many of these items are tailored to unique technical specifications, supplied by limited vendors, and subject to additional layers of security and compliance regulations. These characteristics are consistent with what transaction cost theory would define as high asset specificity. This is an important factor known to increase coordination complexity and, by extension, procurement duration. Thus, despite limitations inherent to single-case research, the case selection is justified not merely by data access but also by its analytical fit: the organisation operates in a highly formalised environment with strong procedural recording practices, while simultaneously facing political pressure to improve performance. The case thus serves as a “critical case” for exploring the broader research question of how changes in red tape affect procurement efficiency.

Moreover, Germany presents a relevant national context for this study. As a mature, rules-based procurement system operating under EU directives and national regulations, Germany offers a setting where regulatory change is transparent and formally codified. The timing of the study coincides with two significant regulatory interventions: a new procurement acceleration law and a directive to reduce internal rules. This allows for an empirical comparison of procurement time and speed under varying levels of red tape.

Arguably, the higher the level of bureaucracy in a system, the greater the complexity of process execution within that system. Consequently, this should be accompanied by longer process durations. This is reflected by the extant literature’s view on red tape, as earlier presented in the background section. For the purpose of the present study, it is necessary to additionally operationalise the intensity of red tape.

The quantity and quality as well as their usage and implementation are of relevance in this context. In the case organisation, a recent analysis counted the presence of over 7,900 different rules, instructions, laws and directives. However, most of these are technical (e.g. quality descriptions of production procedures or materials). Thus, merely counting the quantity of rules is not sufficient to operationalise red tape, as for example an additional rule might optimise usage and implementation of existing red tape and thus, potentially even help to reduce the red tape problem. Then again, measuring the qualitative intensity of red tape also bears risks, as the number of rules and their interdependencies exceeds the feasibility of a proper assessment. Hence, it is necessary to search for an alternative way to operationalise red tape.

In the present case, a proxy for the red tape intensity is provided by overarching changes in the regulatory framework. On 1 July 2022 a so-called “procurement acceleration law” (PAcL) was implemented that sets new and eased regulatory rules for the case organisation. On 25 April 2023, this was even intensified by a Secretary of State-Directive (SoS-D) in which the case organisation was provided with even more decision-making freedom by further reducing internal rules and regulation. Therefore, the proxy for red tape is marked by the dates of these strategic acceleration initiatives. This allows to differentiate levels of red tape intensities according to time phases in which the regulatory initiatives have been either enacted or not (see Table 1).

Table 1.

Operationalisation of different red tape intensities over time

PhasesTimeframePhase contentOperationalisationfor red tape in the case
Pre-COVID19Before 30 June 2020Initial state of highly regulated public procurement; legal rules and internal directives dominate the execution of public procurement in the organisationHighest level of red tape in the sample
COVID191 July 2020 to 30 June 2022Extraordinary timeframe with loosening of public procurement regulations (in particular direct procurement of marginal value) but on the other hand major additional rules for executing work, shut-downs etcExtraordinary phase of red tape, reduced on the one hand, increased on the other
PAcL1 July 2022 to 24 April 2023New law for acceleration of public procurement (for defence sector) with numerous and different approaches, e.g. loosened use of lots, freedom in the choice of procedure etcMedium level of red tape
SoS-D25 April 2023 to 31 December 2024New directive of the state secretary to accelerate public procurement also by reducing internal rules and instructions that go beyond legal regulationLowest level of red tape
Source(s): Authors’ own creation

This study uses data already starting before the COVID-19 pandemic, since this phase is expected to have the highest level of red tape compared to recent phases with the use of PAcL and SoS-D. The most recent phase of SoS-D is reasoned as the one with the lowest level of red tape. Having this in mind, the analysis of procedural time stamps allows to calculate the overall (mean) duration of procurement procedures. Compared with the phases, this allows to evaluate and test the already existing proposition that red tape causes or relates to public procurement time.

The data set used in this study was directly exported from the internal IT system of the case organisation, a major German public procurement body. The system records every formal procurement procedure initiated within the organisation and automatically logs procedural metadata, including multiple time stamps (e.g. initiation date, tender opening, deadline, contract award); procedural types (e.g. open, restricted, negotiated); estimated and actual procurement volumes; and the number of applicants and bids. The raw export covered a total of 42,070 procurement procedures conducted between January 2018 and December 2024. Data extraction was performed by in-house IT personnel via a secured export interface, ensuring data completeness and alignment with internal reporting structures.

Following extraction, the data set was screened for completeness, plausibility and consistency. In the first step, duplicate entries and procedures with missing key time stamps were removed. Next, implausible values (e.g. negative durations, durations exceeding three years or missing procurement types) were flagged and cross-validated against secondary internal reports. Extremely long procedures (i.e. above the 99.5th percentile) were subjected to additional manual inspection and flagged as outliers where appropriate. After this initial cleaning process, all variables were reformatted to ensure comparability and usability in the analysis (e.g. standardising date formats, harmonising procurement procedure codes).

The data set is subject to right-censoring, as longer-running procedures, especially those initiated in later years like 2024, are underrepresented due to the cut-off date of 31 December 2024. To correct this, an adjustment factor was applied. This factor was derived from the annual change in mean total duration of procurement procedures, calculated by comparing cohorts with increasing time since initiation. All cohorts were then adjusted to a standardised observation window of six years using a proportional uplift approach.

The cleaned data set was then used to calculate key time-based metrics. Procurement duration was computed as the number of days between the initiation of the procurement process and the formal end of procedure (e.g. contract award). The measurement is similar to other duration measurement approaches in procurement using specific process steps as time stamps (e.g. Migliaccio et al., 2010: duration between request for proposals and due date; e.g. Prier et al., 2021: duration between receiving offers and award notice announcement). Procurement speed was operationalised in two ways, using two performance measures in relation to duration:

  1. bids received per duration; and

  2. net procurement volume per duration.

These metrics were subsequently aggregated across the four regulatory phases (Pre-COVID, COVID, PAcL, SoS-D) to allow comparative analysis under varying levels of red tape. Descriptive and inferential statistical analyses, including chi-square tests and Cramér’s V, were conducted using SPSS to examine the relationship between red tape intensity and procurement performance outcomes.

Each year covered in the data has almost equal share with around 6,462–6,849. In 2018 and 2024, the number of retrieved data points are slightly lower but still big enough to be included in the analysis (4,776 / 4,423) (see Figure 1). Relating the data to the distinct phases, Pre-COVID-19 represents 14,749 data sets, COVID 13,251, post-COVID altogether 14,070 with PAcL including 5,423 and SoS-D 8,647 projects.

Figure 1.
A pie chart displays data from 2018 to 2024, showing numerical values and percentages for each year.The pie chart illustrates numerical data from the years 2018 to 2024, with each segment representing a different year. Each section is labeled with the year, alongside the corresponding numerical value and the percentage it represents of the total. The data shows the following numerical values: 2018 has four thousand seven hundred seventy-six with eleven percent; 2019 features six thousand five hundred six at fifteen percent; 2020 includes six thousand eight hundred forty-nine at sixteen percent; 2021 displays six thousand five hundred sixty-six at sixteen percent; 2022 shows six thousand four hundred sixty-two at fifteen percent; 2023 has six thousand four hundred eighty-eight at fifteen percent; and 2024 contains four thousand four hundred twenty-three at eleven percent. The chart's segments range from darker to lighter shades, emphasizing the differences in data values. There are no overlapping or missing segments, with a clear distribution across the circle.

Sample overview

Source: Authors’ own creation

Figure 1.
A pie chart displays data from 2018 to 2024, showing numerical values and percentages for each year.The pie chart illustrates numerical data from the years 2018 to 2024, with each segment representing a different year. Each section is labeled with the year, alongside the corresponding numerical value and the percentage it represents of the total. The data shows the following numerical values: 2018 has four thousand seven hundred seventy-six with eleven percent; 2019 features six thousand five hundred six at fifteen percent; 2020 includes six thousand eight hundred forty-nine at sixteen percent; 2021 displays six thousand five hundred sixty-six at sixteen percent; 2022 shows six thousand four hundred sixty-two at fifteen percent; 2023 has six thousand four hundred eighty-eight at fifteen percent; and 2024 contains four thousand four hundred twenty-three at eleven percent. The chart's segments range from darker to lighter shades, emphasizing the differences in data values. There are no overlapping or missing segments, with a clear distribution across the circle.

Sample overview

Source: Authors’ own creation

Close modal

Annually, the case organisation spends a substantial volume on procuring goods and services. The overall analysed procurement volume for the given time-frame is over €41.4bn as depicted in Figure 2. The annually mean procurement volume is €5.6bn. Generally, the budget of the considered procurement organisation increased over time. The increase is in part steep, as the procurement organisation received extraordinary funding to address urgent demand. The relatively small figure in 2024 is explained by the fact that this analysis took place at end of 2024, where high budget projects started in 2024 are not yet finished.

Figure 2.
A bar graph illustrating procurement volume in billion euros from 2018 to 2024, showing fluctuating values across the years.The image presents a bar graph titled "Procurement volume [billion EUR]," depicting the procurement volume in billions of euros for the years 2018 through 2024. The horizontal axis represents the years while the vertical axis measures the procurement volume in billion euros. Each year is marked along the bottom of the graph, with corresponding bar heights indicating the procurement volume: 3.63 billion in 2018, 7.31 billion in 2019, 6.91 billion in 2020, 4.45 billion in 2021, 8.83 billion in 2022, 8.09 billion in 2023, and 2.26 billion in 2024. Each bar is solid and presented in the same width with numerical values displayed at the midpoint of each bar to indicate their precise procurement volumes.

Procurement volume per year

Source: Authors’ own creation

Figure 2.
A bar graph illustrating procurement volume in billion euros from 2018 to 2024, showing fluctuating values across the years.The image presents a bar graph titled "Procurement volume [billion EUR]," depicting the procurement volume in billions of euros for the years 2018 through 2024. The horizontal axis represents the years while the vertical axis measures the procurement volume in billion euros. Each year is marked along the bottom of the graph, with corresponding bar heights indicating the procurement volume: 3.63 billion in 2018, 7.31 billion in 2019, 6.91 billion in 2020, 4.45 billion in 2021, 8.83 billion in 2022, 8.09 billion in 2023, and 2.26 billion in 2024. Each bar is solid and presented in the same width with numerical values displayed at the midpoint of each bar to indicate their precise procurement volumes.

Procurement volume per year

Source: Authors’ own creation

Close modal

Across the sample, a reduction in the duration of public procurement procedures can be observed. In 2018, the mean duration time per procurement procedure was 197.0 days, while by 2023 it had decreased to 152.8 days. This is a reduction of over 22.4%. In 2024, the mean duration further decreases to 124.8 days, representing a 36.6% reduction compared to 2018. A relatively consistent downward trend in duration over the years is depicted in Figure 3.

Figure 3.
Line graph displaying the mean duration in days from 2018 to 2024, with notable values indicated for each year.The mean duration in days is shown to decline steadily over time. In 2018, it was 197.0 days, dropping to 170.6 days in 2019, then slightly increasing to 180.3 days in 2020 and 181.3 days in 2021. The trend declines again to 157.9 days in 2022, 152.8 days in 2023, and reaches 124.8 days in 2024, indicating a clear downward pattern in mean duration across the years.

Average duration time per year

Source: Authors’ own creation

Figure 3.
Line graph displaying the mean duration in days from 2018 to 2024, with notable values indicated for each year.The mean duration in days is shown to decline steadily over time. In 2018, it was 197.0 days, dropping to 170.6 days in 2019, then slightly increasing to 180.3 days in 2020 and 181.3 days in 2021. The trend declines again to 157.9 days in 2022, 152.8 days in 2023, and reaches 124.8 days in 2024, indicating a clear downward pattern in mean duration across the years.

Average duration time per year

Source: Authors’ own creation

Close modal

Additionally, duration is analysed in relation to red tape phases. The descriptive findings indicate that duration decreased progressively from phase to phase. The mean time savings are substantial, declining from 180.9 days in the first phase (pre-COVID-19) to 136.1 days in the final phase (a reduction of over 24.8 percentage points). This finding is noteworthy in itself, given the immense reduction in duration. Furthermore, it suggests a clear trend: phases characterised by lower levels of red tape tend to have shorter public procurement durations (see Figure 4). This supports further investigations into potential causal relationships driving the observed decline in procurement duration.

Figure 4.
A line chart presents the mean duration in days across different pandemic-related phases.The mean duration in days decreases across the four stages. Before C O V I D 19, it stands at 180.9 days, slightly decreasing to 177.5 days during C O V I D 19, further falling to 155.3 days in the P A C L phase, and finally reducing to 136.1 days in the S o S D phase. The data demonstrate a consistent reduction in mean duration from pre-pandemic to later phases.

Average duration time per red tape phase

Source: Authors’ own creation

Figure 4.
A line chart presents the mean duration in days across different pandemic-related phases.The mean duration in days decreases across the four stages. Before C O V I D 19, it stands at 180.9 days, slightly decreasing to 177.5 days during C O V I D 19, further falling to 155.3 days in the P A C L phase, and finally reducing to 136.1 days in the S o S D phase. The data demonstrate a consistent reduction in mean duration from pre-pandemic to later phases.

Average duration time per red tape phase

Source: Authors’ own creation

Close modal

To provide a more fine-grained perspective of the duration reduction in the examined case, different procurement procedures types are analysed (see  Appendix 1). Figure 5 depicts changes in the mean duration of each procurement procedure type. The range of reduction spans from −10.4% to −59.6%. All procedures exhibit shorter duration durations, with the sole exception being “negotiated procedure with call for competition”, which showed an increase of +18.25%. The greatest reductions were observed in the “public tender” (below EU threshold) and the negotiating procedures with or without tender publication.

Figure 5.
A bar chart displays percentage changes in duration reduction across various tender procedures between 2018 and 2024.The chart shows duration reduction in percent for different procurement methods from 2018 to 2024. Restricted tender decreased by 48.3 percent, open procedure by 21.1 percent, public tender by 59.6 percent, and price inquiry by 10.4 percent. Negotiated procedures with tender publication declined by 36.1 percent and without tender publication by 41.0 percent. The negotiated procedure with a call for competition increased by 18.2 percent, while the same without a call for competition decreased by 25.7 percent.

Duration reduction per public procurement procedure

Source: Authors’ own creation

Figure 5.
A bar chart displays percentage changes in duration reduction across various tender procedures between 2018 and 2024.The chart shows duration reduction in percent for different procurement methods from 2018 to 2024. Restricted tender decreased by 48.3 percent, open procedure by 21.1 percent, public tender by 59.6 percent, and price inquiry by 10.4 percent. Negotiated procedures with tender publication declined by 36.1 percent and without tender publication by 41.0 percent. The negotiated procedure with a call for competition increased by 18.2 percent, while the same without a call for competition decreased by 25.7 percent.

Duration reduction per public procurement procedure

Source: Authors’ own creation

Close modal

Next, this research investigates the speed of public procurement, defined as relationship between time and a performance metric. This helps to assess acceleration in procurement processes. Two different approaches are used to investigate public procurement speed:

  1. mean bids per mean duration; and

  2. mean procurement volume per mean duration time.

First, the mean number of bids, sorted by red tape phases, shows only slight variation. The overall mean is 2.17, ranging from a high of 2.29 in 2018 to a low of 2.11 in 2024. Figure 6 shows this relatively stable trend, with a slight decrease from 2.22 to 2.11 bids per procedure. This could suggest a marginal decline in competitive intensity.

Figure 6.
A line chart presents the mean number of bids per procedure across different pandemic-related phases.The mean number of bids per procedure remains relatively stable over time. Before C O V I D 19, it was 2.22 bids, slightly decreasing to 2.17 during C O V I D 19, then to 2.11 in both the P A C L and S o S D phases. The data indicate a minor decline in the mean number of bids, suggesting a consistent but slightly reduced level of competition across all phases.

Mean bids per red tape phases

Source: Authors’ own creation

Figure 6.
A line chart presents the mean number of bids per procedure across different pandemic-related phases.The mean number of bids per procedure remains relatively stable over time. Before C O V I D 19, it was 2.22 bids, slightly decreasing to 2.17 during C O V I D 19, then to 2.11 in both the P A C L and S o S D phases. The data indicate a minor decline in the mean number of bids, suggesting a consistent but slightly reduced level of competition across all phases.

Mean bids per red tape phases

Source: Authors’ own creation

Close modal

Using this data for evaluation public procurement speed, the metric “bids per day” is used to assess acceleration. Results show that in the most recent phase (SoS-D), with the lowest level of red tape, the highest speed is achieved. Overall, speed increases steadily across the phases, from 0.0123 to 0.0155 (see Figure 7).

Figure 7.
A bar chart presents the mean number of bids per mean duration measured in bids per day across different pandemic-related phases.The chart shows a gradual increase in mean bids per day over four phases. Before C O V I D 19, the mean was 0.0123 bids per day, followed by 0.0122 during C O V I D 19. It then rose to 0.0136 during the P A C L phase and reached 0.0155 in the S o S D phase. The results suggest a steady improvement in bidding activity relative to time across successive phases.

Speed assessment − bids per day

Source: Authors’ own creation

Figure 7.
A bar chart presents the mean number of bids per mean duration measured in bids per day across different pandemic-related phases.The chart shows a gradual increase in mean bids per day over four phases. Before C O V I D 19, the mean was 0.0123 bids per day, followed by 0.0122 during C O V I D 19. It then rose to 0.0136 during the P A C L phase and reached 0.0155 in the S o S D phase. The results suggest a steady improvement in bidding activity relative to time across successive phases.

Speed assessment − bids per day

Source: Authors’ own creation

Close modal

Second, speed is assessed using net procurement volume. Descriptive data indicate that the mean value ranges from 1.10 PAcL before the pandemic to 0.84 during the COVID19 phase. Although the volume declined during the pandemic, it rebounded afterward. This suggests that analyses of public procurement trends should treat the COVID-19 period as a potential outlier. Generally, the data indicate stable procurement volume when comparing the pre-COVID-19 with PAcL (post-COVID19) phases. The slight decline in the SoS-D phase is likely due to incomplete project data for that period, especially for high-volume contracts (see Figure 8).

Figure 8.
A line chart displays changes in mean procurement volume in million E U R across four phases.The mean procurement volume begins at 1.07 million E U R before C O V I D 19, dropping to 0.84 million E U R during C O V I D 19. It increases again to 1.10 million E U R during the P A C L phase before declining slightly to 1.00 million E U R in the S o S D phase. The trend indicates an initial decline during the pandemic followed by a partial recovery in later stages.

Mean procurement volume per tender

Source: Authors’ own creation

Figure 8.
A line chart displays changes in mean procurement volume in million E U R across four phases.The mean procurement volume begins at 1.07 million E U R before C O V I D 19, dropping to 0.84 million E U R during C O V I D 19. It increases again to 1.10 million E U R during the P A C L phase before declining slightly to 1.00 million E U R in the S o S D phase. The trend indicates an initial decline during the pandemic followed by a partial recovery in later stages.

Mean procurement volume per tender

Source: Authors’ own creation

Close modal

Using volume as a performance criterion, its ratio to time indicates an increase in procurement speed from pre-COVID19 to post-COVID19 phases. Only the COVID-19 phase shows a notably lower volume per day ratio. This would imply an acceleration of 24% acceleration in procurement volume processed per procedure day (see Figure 9).

Figure 9.
A bar chart presents the mean procurement volume per mean duration time measured as volume per day across four categories.The chart shows variations in mean procurement volume per mean duration time for four categories. Category 1 records a volume of 5,922.27 per day, Category 2 decreases to 4,714.76 per day, Category 3 increases to 7,095.93 per day, and Category 4 reaches the highest value of 7,332.50 per day. The data indicate an overall upward trend after an initial decrease, showing improved efficiency in procurement volume relative to time.

Speed assessment − volume per day

Source: Authors’ own creation

Figure 9.
A bar chart presents the mean procurement volume per mean duration time measured as volume per day across four categories.The chart shows variations in mean procurement volume per mean duration time for four categories. Category 1 records a volume of 5,922.27 per day, Category 2 decreases to 4,714.76 per day, Category 3 increases to 7,095.93 per day, and Category 4 reaches the highest value of 7,332.50 per day. The data indicate an overall upward trend after an initial decrease, showing improved efficiency in procurement volume relative to time.

Speed assessment − volume per day

Source: Authors’ own creation

Close modal

Finally, multivariate statistics is used to evaluate the relation between red tape and time. First, correlation analysis investigates how the variables relate to each other (see  Appendix 2). Duration, tender volume (0.067**), number of bidders (−0.040**) and number of applicants (−0.038**) are significantly correlated, though the coefficients are small.

To analyse the relation between duration and red tape intensity levels, a chi-square test is used. The chi-square test determines whether there is a significant association between two variables. It compares observed and expected frequencies and thereby assesses if the differences between these frequencies are due to chance or statistically significant interdependencies. If the chi-square test is significant, the null-hypothesis of independency must be refused, what in turn indicates a dependency. Cramér′s V is then used to measure the strength of the association. The same procedure is used for speed by volume and speed by number of bids.

For the calculation SPSS software was used. To meet the prerequisite of the chi-square test, an expected cell count of at least five continuous variables were grouped into meaningful categories:

  • Project duration in days was aggregated into monthly intervals, with all durations exceeding three years combined into one single category.

  • Speed in volume per day was grouped into increments of €10,000 per day, with all values above €100,000 forming the top category.

  • Speed in bids per day was divided into seven categories: ≤0.01; 0.01–0.02; 0.02–0.03; 0.03–0.04; 0.04–0.05; 0.05–0.1; and >0.1 bids per day.

Each of these categorical variables was then tested against the bureaucracy proxy using the chi-square test to assess potential associations. The analysis revealed a highly significant chi-square result for procedural duration (Table 2), with a Cramér’s V of 0.200, indicating a weak association between duration and red tape (Table 3). In other words, there is a statistically weak dependency between red tape and the duration of public procurement procedures.

Table 2.

Chi-square test results

Statistical parametersValueDfApproximate significance(two-sided)
Pearson chi square1,677.77437< 0.001
Likelihood ratio1,972.09637< 0.001
Linear by linear association195.9751< 0.001
N of valid cases42,070
Note(s):

0 cells (0.0%) have expected count less than 5. The minimum expected count is 9.36

Source(s): Authors’ own creation
Table 3.

Symmetric measures and Cramér’s V results

Statistical parametersValueApproximate significance
Nominal by nominal
Phi0.200< 0.001
Cramér’s V0.200< 0.001
N of valid cases42,070
Source(s): Authors’ own creation

For procurement speed by volume, the chi-square test was significant, with a Cramér’s V of 0.025 ( Appendix 3), while speed by number of bids yielded a highly significant chi-square test with a Cramér’s V of 0.070 ( Appendix 4). These results suggest that the relationship between red tape and procurement speed, both in terms of procurement volume and number of bids, is statistically significant but weak.

Red tape in public procurement refers to the excessive or rigid compliance requirements that public officials and suppliers must address to complete a procurement process. Often, red tape is only analysed for procurement procedures, but there are numerous additional rules before and after the pure tendering process. These rules are intended to ensure transparency, fairness and accountability, but their sheer complexity can lead to significant delays in decision-making (Coursey and Pandey, 2007; Jovanović et al., 2022). As a result, projects that might have been completed faster in the private sector often face prolonged delays in the public sector due to the need to follow strict procedural guidelines. This is what also the case organisation faces, as the published reports with multi-year delays for some of their most prominent procurement objects (e.g. Bundesministerium der Verteidigung, 2023).

This study contributes to the literature by empirically capturing how changes in the regulatory environment translate into measurable shifts in procurement durations. This is based on red tape operationalised by multiple timeframes with different settings of rules and regulations. Unlike prior studies that often rely on subjective perceptions to assess red tape (Coursey and Pandey, 2007; Scott and Pandey, 2005), our approach offers an objective measurement based on process data from the case organisation.

This approach offers the opportunity to analyse longitudinal changes due to the addressed red tape mitigation actions. Due to recent crises and risks in supply security for public organisations, new rules were issued in a top-down approach that aimed to combat the red tape problem. These approaches, including a new law (PAcL) or secretary of state directive (SoS-D) did not only change the regulatory frame, but they also addressed risk aversion and use of exemption rules in public procurement. Nevertheless, red tape is, in part, a safeguard against accusations of corruption, nepotism or mismanagement. The more rules and procedures in place, the safer procurement officials may feel from these accusations. However, this emphasis on safeguarding can create delays. The top-down approach was a major signal to the organisation to become less risk averse and backed the use of exemption rules. The analysis provides empirical evidence that policy interventions, such as the SoS-D directive, can lead to a measurable reduction in procedural risk aversion within public procurement. This highlights that red tape is not merely a function of regulation quantity, but also of organisational interpretation and leadership framing, adding a behavioural dimension to the debate.

In light of previous reports and research in the field, this study underpins the reasoning that red tape is causing delays with empirical evidence. This is in contrast to prevalent practices. For instance, The World Bank Benchmarking Report measures time in public procurement, but, instead of referring to procedural time, it examines the waiting time of suppliers to receive payment (World Bank, 2017). Similar to Hoekman and Taş (2022), who use regulation quality as a proxy for procurement system effectiveness, this study also applies a regulatory phase-based proxy to assess time-related performance outcomes. Moreover, the European Union examined the administrative capacity in the EU with regard to public procurement and also analysed time or time-consumptive issues like training of personnel (European Union, 2022, 2023). As such, this research generally adds a new empirically substantiated perspective to existing approaches.

Moreover, analysing procurement time is not new to academic research, as a number of studies contemplated transition factors of more efficient procurement systems (e.g. Anjali Kumar et al., 2015). Time is, by and large, a variable that is interpreted as inefficiency. Vice versa, the reduction of procurement time in the public sector is an indirect goal of almost every reform (Thai, 2017). Empirical studies show duration times of 286 days in the mean (Anjali Kumar et al., 2015). Anjali Kumar et al.’s (2015) research indicated that different procedures and procurement methods lead to far reaching different times (434 days to 209 days, Anjali Kumar et al., 2015). The presented duration time of the case sample is below that duration time. But the mean duration time lies with 197 days in 2018 still in the lower range of Anjali Kumar et al. (2015). It seems as if there is even a longer global trend of management efforts that resulted in time reduction of public procurement procedures. Effectively, duration time is decreasing, while procurement speed is increasing. It is of interest if this is only a limited or a lasting trend and if the findings can be reproduced in other (country) settings.

This research contributes to the public procurement literature by proposing a more standardised way to evaluate duration or speed times, as most studies and research works measure time differently. Wang et al. (2020) measure the time between publication of a tender to the award of contract. Flynn (2018) measures the time between deadline of receipt of offers and award of contract. In contrast, Hult et al. (2002) investigate in a survey the total time between initialising and ending of a procurement procedure. This research investigates a data set that in its findings of this article follows the total time approach, similar to Hult et al. (2002), but data would also allow to measure partial times. If research on the topic would follow a more standardised way referring to time stamps, duration and speed, then overarching, even meta-analysis studies would be possible.

This could enhance existing benchmarks about the time consumption in public procurement. For example, Flynn (2018) mentions that 120 days is a satisfactory timespan for the duration time of public procurement (receipt of offers to award of contracts). Comparing our results with this benchmark, the mean total duration time in our case is in the last phase (SoS-D) with 136.1 days is close to that threshold. Findings indicate that the case organisation is on a good path towards increased efficiency, but findings also highlight the need for a more differentiated view on best practices, taking the diversity of project types and public procurement procedure types into account. It would also help to have appropriate measurement indicators and instruments for duration or speed in public procurement. As of now, research is quite heterogeneous. For example, Arun Kumar et al. (2005) investigate and measure the difference between real and goal/estimated duration time. This research contributes to the instruments for evaluating public procurement time by proposing speed metrics. Processed bids per day or processed procurement volume per day are metrics that can be used for cross-organisational or cross-country assessment of public procurement time.

Referring the research back to red tape, it is plausible, within the limitations of the operationalisation and measurement of red tape in this study, that procurement red tape reduces time performance. However, there are numerous other effects discussed in the red tape research streams, that are also worth investigating. First of all, budgeting red tape, i.e. hindering rules in the public budgeting process, can also cause inefficiencies (Coursey and Pandey, 2007). This would call for a more fine-grained analysis and even a better merger of red tape theory with performance measurement and management in public procurement.

In addition, Haase describes a central dilemma in public procurement: the urgent need for speed and responsiveness during crises often clashes with the regulatory safeguards designed to ensure accountability, transparency and fairness (Haase, 2019). While the potentially unintended effects of reducing regulatory controls lie beyond the scope of this paper, they raise an important question: should public organisations aim for the right timing in procurement, rather than simply the shortest or fastest procedures?

Despite these additional considerations, the present research supports the observation that red tape contributes to procurement delays. The data set, spanning the period from 2018 to 2024, provides a robust empirical foundation, enabling a rigorous examination of the dependency hypothesis. As such, this study offers a meaningful contribution by empirically testing the assumed relationship between bureaucratic intensity and procurement duration using a large and representative sample. Moreover, it introduces novel benchmarking tools for assessing time efficiency in public procurement processes.

The methodology of this paper contains two original aspects. First, the relation between red tape and time in public procurement is not evaluated by perceptions of involved people but by means of an empirical secondary analysis based on actual procurement durations. This was grounded on a public procurement software systems’ data output on 42,070 procurement procedures including the respective time stamps. This is a promising avenue for future research. Furthermore, time is a variable that allows comparison, benchmarking and meta-analysis not only between different public procurement organisations but also between different regulatory contexts. Second, this research distinguishes between the simple duration of a public procurement procedure and the speed of it. Hence, this work introduces speed metrics (bids per duration time; volume per duration time) and proposes an approach to evaluate public procurement procedures in relation to its main drivers. The findings showed an increase in speed and interdependency between red tape and public procurement duration. Beyond that, this work can be seen as a methodological proposition that speed metrics must be developed to really assess and evaluate how fast public procurement actually is.

Overall, the perception and gut feeling that red tape is causing delays in public procurement procedures is supported by empirical evidence based on a substantial secondary data set. In general, public procurement managers shall work on reducing redundant or superfluous rules and regulations or internal instructions. Additionally, public procurement managers are tasked to monitor and evaluate time and speed of their procedures.

Then again, managerial effort shall be taken in a differentiated way. Extraordinary demand in a new-buy-situation will typically cause longer procedures than standardised, market-common demand in a re-buy situation. Different measures must be taken. The data set revealed that in the last phase, internal instructions had also a major impact and loosening documentation requirements was one of the key drivers to increase speed and reduce time duration. The case organisation simply allowed to use the documentation form with the lowest administrative duration for a higher number of procurement procedures. This decreased times tremendously. Consequently, the transfer of time-efficient work flows to public procurement procedures is recommended.

The findings indicate that red tape and public procurement duration are interrelated phenomena: lower levels of red tape correspond to faster procurement procedures. That dependency is also backed by the highly significant chi-square-test. This complements findings by Hoekman and Taş (2024), who demonstrate a trade-off between procedural discretion and outcomes such as contract prices and small and medium-sized enterprise contract awards, reinforcing the importance of regulatory design in shaping performance. The finding also corresponds to the perception of involved people, media and society at large. Nevertheless, this is one of the few studies that had access to an actual large-scale data set of procedures including their respective time stamps. Thus, this study is able to provide empirical evidence on the relationship between red tape and public procurement time. This finding not only calls for but also justifies further studies to get more fine-grained insights.

While this study offers empirical insights into the relationship between red tape and procurement efficiency, its conclusions are shaped by several contextual and methodological constraints that merit reflection. The study is based on secondary data from a single, albeit major, German public procurement organisation. While this provides in-depth insight into a highly formalised procurement system, the findings may not be directly transferable to other national or institutional contexts with different regulatory cultures, administrative capacities or procurement volumes. The single-case design limits the ability to make cross-organisational comparisons or to draw conclusions about broader systemic patterns across the EU or globally. Moreover, the operationalisation of red tape is based on four discrete regulatory phases. This presents both a strength and a limitation. On the one hand, it allows for a structured comparison of procurement performance over time. On the other, it simplifies a complex phenomenon. Regulatory change rarely translates instantly into procedural practice, and procurement processes that span multiple phases may blur the intended contrast between high- and low-red-tape periods. Although care was taken to detect and control for such outliers, some level of misclassification remains possible and may have attenuated observed effects. Methodologically, the study relies on descriptive and bivariate statistical approaches, which are effective for detecting patterns but limited in isolating causal mechanisms. Key influences such as project complexity, market competition or organisational risk aversion were not systematically modelled. This limits the explanatory power of the findings and highlights the need for future research to incorporate multivariate methods and richer sets of explanatory variables.

Taken together, these limitations suggest several opportunities for future research. Expanding the empirical scope to include multiple procurement organisations across different countries or administrative levels would allow for cross-case comparison and strengthen the robustness of findings. Furthermore, a more nuanced operationalisation of red tape, perhaps through hybrid indicators combining document analysis, survey input and regulatory burden metrics, could improve construct validity. Finally, incorporating multivariate statistical techniques and interaction terms would help uncover the contingent conditions under which red tape most strongly affects procurement performance.

Bagnasco
,
A.M.
(
2022
), “
Public procurement between emergency and transparency: where We are
”,
Eurasia Business and Economics Society Conference
,
Springer Nature
,
Switzerland
.
Bozeman
,
B.
(
1993
), “
A theory of government “red tape
”,
Journal of Public Administration Research and Theory: J-PART
, Vol.
3
No.
3
, pp.
273
-
303
, available at: Link to A theory of government “red tapewww.jstor.org/stable/1181785
Bozeman
,
B.
(
2012
), “
Multidimensional red tape: a theory coda
”,
International Public Management Journal
, Vol.
15
No.
3
, pp.
245
-
265
, doi: .
Bretschneider
,
S.
(
1990
), “
Management information systems in public and private organizations: an empirical test
”,
Public Administration Review
, Vol.
50
No.
5
, p.
536
, doi: .
Bundesministerium der Verteidigung
(
2023
),
17. Bericht des Bundesministeriums der Verteidigung zu Rüstungsangelegenheiten: Teil 1
.
Bundesrechnungshof
(
2024
), “
Bericht nach § 88 Absatz 2 BHO an den Haushaltsausschuss des deutschen bundestages über die Prüfung der beschaffung und verteilung von schutzmasken durch das bundesministerium für Gesundheit
”.
Busse
,
C.
(
2010
), “
A procedure for secondary data analysis: innovation by logistics service providers
”,
Journal of Supply Chain Management
, Vol.
46
No.
4
, pp.
44
-
58
.
Calantone
,
R.J.
and
Vickery
,
S.K.
(
2010
), “
Introduction to the special topic forum: using archival and secondary data sources in supply chain management research
”,
Journal of Supply Chain Management
, Vol.
46
No.
4
, pp.
3
-
11
, doi: .
Cooke
,
D.K.
,
Brant
,
K.K.
and
Woods
,
J.M.
(
2019
), “
The role of public service motivation in employee work engagement: a test of the job demands-resources model
”,
International Journal of Public Administration
, Vol.
42
No.
9
, pp.
765
-
775
, doi: .
Coursey
,
D.H.
and
Pandey
,
S.K.
(
2007
), “
Content domain, measurement, and validity of the red tape concept
”,
The American Review of Public Administration
, Vol.
37
No.
3
, pp.
342
-
361
, doi: .
Čudanov
,
M.
,
Jovanović
,
P.
and
Jaško
,
O.
(
2018
), “
Influence of the public procurement procedure type on the duration of public procurement
”,
Lex localis - Journal of Local Self-Government
, Vol.
16
No.
2
, pp.
361
-
378
, doi: .
Davis
,
R.S.
and
Stazyk
,
E.C.
(
2014
), “
Making ends meet: how reinvention reforms complement public service motivation
”,
Public Administration
, Vol.
92
No.
4
, pp.
919
-
936
, doi: .
Der Spiegel
(
2023
), “
Mammutbehörde in Koblenz: pistorius tauscht Spitze des Bundeswehr-Beschaffungsamtes aus
”,
DER SPIEGEL
,
available at:
Link to Mammutbehörde in Koblenz: pistorius tauscht Spitze des Bundeswehr-Beschaffungsamtes ausLink to the cited article.
Dickson
,
D.
(
2014
),
The People’s Government: An Introduction to Democracy
,
Cambridge University Press
,
Cambridge
, doi: .
El Benni
,
N.
,
Ritzel
,
C.
,
Heitkämper
,
K.
,
Umstätter
,
C.
,
Zorn
,
A.
and
Mack
,
G.
(
2022
), “
The cost of farmers’ administrative burdens due to cross-compliance obligations
”,
Journal of Environmental Planning and Management
, Vol.
65
No.
5
, pp.
930
-
952
, doi: .
European Union
(
2022
), (Ed.). “
Annual burden survey 2021: the European Union’s efforts to simplify legislation
”,
available at:
Link to Annual burden survey 2021: the European Union’s efforts to simplify legislationLink to a PDF of the cited article.
European Union
(
2023
), (Ed.). “
The European Union’s action to simplify legislation: annual burden survey 2022
”,
available at:
Link to The European Union’s action to simplify legislation: annual burden survey 2022Link to a PDF of the cited article.
Flynn
,
A.
(
2018
), “
Measuring procurement performance in Europe
”,
Journal of Public Procurement
, Vol.
18
No.
1
, pp.
2
-
13
, doi: .
Flynn
,
A.
and
Davis
,
P.
(
2017
), “
Explaining sme participation and success in public procurement using a capability-based model of tendering
”,
Journal of Public Procurement
, Vol.
17
No.
3
, pp.
337
-
372
, doi: .
George
,
B.
,
Pandey
,
S.K.
,
Steijn
,
B.
,
Decramer
,
A.
and
Audenaert
,
M.
(
2021
), “
Red tape, organizational performance, and employee outcomes: meta‐analysis, meta‐regression, and research agenda
”,
Public Administration Review
, Vol.
81
No.
4
, pp.
638
-
651
, doi: .
Grochla
,
E.
(
1973
),
Grundlagen Der Materialwirtschaft: Das Materialwirtschaftliche Optimum Im Betrieb
, ( (2nd ed.) ),
Springer Gabler
,
Wiesbaden
,
available at:
https://ebookcentral.proquest.com/lib/kxp/detail.action?docID=6711262
Grochla
,
E.
(
1992
),
Grundlagen Der Materialwirtschaft: Das Materialwirtschaftliche Optimum im Betrieb
, (
3., gründlich durchges. Aufl., unveränd. Nachdr
).
Gabler-Lehrbuch.Gabler
.
Guriev
,
S.
(
2004
), “
Red tape and corruption
”,
Journal of Development Economics
, Vol.
73
No.
2
, pp.
489
-
504
, doi: .
Haase
,
T.W.
(
2019
), “Uncertainty in crisis management”, In
A.
Farazmand
(Ed.),
Springer eBook Collection. Global Encyclopedia of Public Administration, Public Policy, and Governance
,
Springer
, pp.
1
-
5
, doi: .
Harland
,
C.M.
,
Knight
,
L.
,
Patrucco
,
A.S.
,
Lynch
,
J.
,
Telgen
,
J.
,
Peters
,
E.
,
Tátrai
,
T.
and
Ferk
,
P.
(
2021
), “
Practitioners’ learning about healthcare supply chain management in the COVID-19 pandemic: a public procurement perspective
”,
International Journal of Operations and Production Management
, Vol.
41
No.
13
, pp.
178
-
189
, doi: .
He
,
C.
,
Milne
,
A.
and
Ataullah
,
A.
(
2023
), “
What explains delays in public procurement decisions?
”,
Economic Modelling
, Vol.
121
, p.
106201
, doi: .
Hoekman
,
B.
and
Taş
,
B.K.O.
(
2022
), “
Procurement policy and SME participation in public purchasing
”,
Small Business Economics
, Vol.
58
No.
1
, pp.
383
-
402
, doi: .
Hoekman
,
B.
and
Taş
,
B.K.O.
(
2024
), “
Discretion and public procurement outcomes in Europe
”,
European Journal of Political Economy
, Vol.
82
, p.
102525
, doi: .
Holoubek
,
M.
(
2009
), “
Vergaberecht 2009
”,
SpringerLink Bücher. Springer
, doi: .
Hult
,
G.M.
,
Ferrell
,
O.
and
Hurley
,
R.F.
(
2002
), “
Global organizational learning effects on cycle time performance
”,
Journal of Business Research
, Vol.
55
No.
5
, pp.
377
-
387
, doi: .
Jovanović
,
P.
,
Ivanović
,
T.
,
Maričić
,
M.
and
Ivančević
,
S.
(
2022
), “
Public procurement employees’ perception on legal changes, perceived red tape and job stress: evidence from Serbia
”,
Engineering Economics
, Vol.
33
No.
5
, pp.
507
-
520
, doi: .
Kersting
,
S.
and
Neuerer
,
D.
(
2020
), “
BER: Warum der Pannen-Flughafen erst jetzt eröffnet wird
”,
Handelsblatt
,
available at:
Link to BER: Warum der Pannen-Flughafen erst jetzt eröffnet wirdLink to the cited article.
Kortendieck
,
G.
, and
Stepanek
,
P.
(
2019
), “Controlling in der deutschsprachigen Sozialwirtschaft: Eine Einführung”,
Springer eBooks Education and Social Work
,
Springer VS
,
Wiesbaden
, doi: .
Kortukova
,
T.
,
Kolosovskyi
,
Y.
,
Korolchuk
,
O.L.
,
Shchokin
,
R.
and
Volkov
,
A.S.
(
2023
), “
Peculiarities of the legal regulation of temporary protection in the European Union in the context of the aggressive war of the Russian Federation against Ukraine
”,
International Journal for the Semiotics of Law - Revue Internationale de Sémiotique Juridique
, Vol.
36
No.
2
, pp.
667
-
678
, doi: .
Kroeber-Riel
,
W.
(
1966
), “
Beschaffung und Lagerung: Betriebswirtschaftliche Grundfragen der Materialwirtschaft
”,
Springer Gabler. in Springer Fachmedien Wiesbaden GmbH
,
available at:
Link to Beschaffung und Lagerung: Betriebswirtschaftliche Grundfragen der MaterialwirtschaftLink to the cited article.
Kumar
,
A.
,
Nair
,
A.
and
Piecha
,
J.
(
2015
), “
Measuring efficiency in international public procurement
”,
Journal of Public Procurement
, Vol.
15
No.
3
, pp.
365
-
389
, doi: .
Kumar
,
A.
,
Ozdamar
,
L.
and
Ng
,
C.P.
(
2005
), “
Procurement performance measurement system in the health care industry
”,
International Journal of Health Care Quality Assurance
, Vol.
18
No.
2
, pp.
152
-
166
, doi: .
Loader
,
K.
(
2007
), “
The challenge of competitive procurement: value for money versus small business support
”,
Public Money and Management
, Vol.
27
No.
5
, pp.
307
-
314
, doi: .
Loader
,
K.
(
2010
), “
Is local authority procurement ‘lean’? An exploration to determine if ‘lean’ can provide a useful explanation of practice
”,
Journal of Purchasing and Supply Management
, Vol.
16
No.
1
, pp.
41
-
50
, doi: .
Loader
,
K.
(
2015
), “
SME suppliers and the challenge of public procurement: evidence revealed by a UK government online feedback facility
”,
Journal of Purchasing and Supply Management
, Vol.
21
No.
2
, pp.
103
-
112
, doi: .
Lödding
,
H.
(
2016
),
Verfahren Der Fertigungssteuerung: Grundlagen, Beschreibung, Konfiguration
, ( (3. Aufl. 2016) ).
Springer Vieweg
,
Heidelberg
,
available at:
http://nbn-resolving.org/urn:nbn:de:bsz:31-epflicht-1607838
McCue
,
C.
and
Prier
,
E.
(
2008
), “
Using agency theory to model cooperative public purchasing
”,
Journal of Public Procurement
, Vol.
8
No.
1
, pp.
1
-
35
, doi: .
Menzel
,
B.
(
2023
), “
Stuttgart 21 verzögert sich weiter – und wird noch teurer
”,
Merkur
,
available at:
Link to Stuttgart 21 verzögert sich weiter – und wird noch teurerLink to the cited article.
Migliaccio
,
G.C.
,
Bogus
,
S.M.
and
Chen
,
A.
(
2010
), “
Effect of duration of design–build procurement on performance of transportation projects
”,
Transportation Research Record: Journal of the Transportation Research Board
, Vol.
2151
No.
1
, pp.
67
-
73
, doi: .
Ministerium für Verkehr Baden-Württemberg
(
2023
), “
Stuttgart 21
”,
available at:
Link to Stuttgart 21Link to the cited article.
Olupot
,
P.S.
(
2023
), “
Institutional pressures and procurement cycle time in Uganda’s Central government procuring and disposing entities: the mediating role of opportunistic behavior
”,
Journal of Public Procurement
, Vol.
23
Nos
3-4
, pp.
344
-
364
, doi: .
Paul
,
S.
(
2018
), “
Crisis in Boeing 787 Dreamliner: an investigation from project management control perspective
”,
International Journal of Human Resource Studies
, Vol.
8
No.
4
, p.
242
, doi: .
Prier
,
E.
and
McCue
,
C.P.
(
2009
), “
The implications of a muddled definition of public procurement
”,
Journal of Public Procurement
, Vol.
9
Nos
3-4
, pp.
326
-
370
, doi: .
Prier
,
E.
,
McCue
,
C.P.
and
Csáki
,
C.
(
2021
), “
Evaluating decision speed as a measure of public procurement performance in the European single market
”,
International Journal of Public Administration
, Vol.
44
No.
13
, pp.
1065
-
1075
, available at: Link to Evaluating decision speed as a measure of public procurement performance in the European single markethttps://ideas.repec.org/a/taf/lpadxx/v44y2021i13p1065-1075.html
Rutkowski
,
C.J.
,
Eboch
,
K.
,
Carr
,
A.
and
Greer
,
B.M.
(
2022
), “
Strategic procurement collaboration for the common good: private and public procurement relationship duringa pandemic
”,
Journal of Public Procurement
, Vol.
22
No.
1
, pp.
43
-
63
, doi: .
Schapper
,
P.R.
,
Veiga Malta
,
J.N.
and
Gilbert
,
D.L.
(
2006
), “
An analytical framework for the management and reform of public procurement
”,
Journal of Public Procurement
, Vol.
6
Nos
1-2
, pp.
1
-
26
, doi: .
Schoeni
,
D.
,
Butler
,
L.
and
Trybus
,
M.
(
2023
), “
A special issue on the emerging impact of the Russian invasion of Ukraine on defence procurement in Europe
”, doi: .
Scott
,
P.G.
and
Pandey
,
S.K.
(
2005
), “
Red tape and public service motivation
”,
Review of Public Personnel Administration
, Vol.
25
No.
2
, pp.
155
-
180
, doi: .
Tátrai
,
T.
, and
Nyikos
,
G.
(
2013
), “The uses and abuses of public procurement in Hungary”,
Charting a Course in Public Procurement Innovation and Knowledge Sharing/
, edited by
Gian Luigi
Albano
,
Keith F.
Snider
and
Khi V.
Thai
.
PrAcademics Press
,
Boca Raton
, pp.
29
-
54
,
available at:
Link to The uses and abuses of public procurement in HungaryLink to a PDF of the cited article.
Tempelmeier
,
H.
(
1983
), “Lieferzeit-Orientierte Lagerungs- und Auslieferungsplanung”,
Physica-Schriften Zur Betriebswirtschaft Ser: v
,
6
.
Physica-Verlag
,
Heidelberg
,
available at:
Link to Lieferzeit-Orientierte Lagerungs- und AuslieferungsplanungLink to the cited article.
Thai
,
K.V.
(
2017
), “International handbook of public procurement/Khi V. Thai ”, ( (1st) ).
Public Administration and Public Policy
,
Routledge
,
London
.
The New York Times
(
2013
), “
A rocky path for the 787 Dreamliner
”,
The New York Times
,
available at:
Link to A rocky path for the 787 DreamlinerLink to the cited article.
Thommen
,
J.
,
P.
,
Achleitner
,
A.
,
K.
,
Gilbert
,
D.U.
,
Hachmeister
,
D.
,
Jarchow
,
S.
and
Kaiser
,
G.
(
2020
), “
Lehrbuch. Springer gabler
”,
Allgemeine Betriebswirtschaftslehre (9., Vollständig Überarbeitete Auflage)
, doi: .
Vecchi
,
V.
,
Cusumano
,
N.
and
Boyer
,
E.J.
(
2020
), “
Medical supply acquisition in Italy and the United States in the era of COVID-19: the case for strategic procurement and public–private partnerships
”,
The American Review of Public Administration
, Vol.
50
Nos
6-7
, pp.
642
-
649
, doi: .
Vinton
,
D.E.
(
1992
), “
A new look at time, speed, and the manager
”,
Academy of Management Perspectives
, Vol.
6
No.
4
, pp.
7
-
16
, doi: .
Wang
,
Q.
,
Zhang
,
R.
and
Liu
,
J.
(
2020
), “
Price/time/intellectual efficiency of procurement: uncovering the related factors in Chinese public authorities
”,
Journal of Purchasing and Supply Management
, Vol.
26
No.
3
, p.
100622
, doi: .
Welch
,
E.W.
and
Pandey
,
S.K.
(
2006
), “
E-Government and bureaucracy: toward a better understanding of intranet implementation and its effect on red tape
”,
Journal of Public Administration Research and Theory
, Vol.
17
No.
3
, pp.
379
-
404
, doi: .
World Bank
(
2017
),
Benchmarking Public Procurement: Assessing Public Procurement Regulatory Systems in 180 Economies
,
International Bank for Reconstruction and Development
,
Washington DC
.
Yeo
,
K.T.
and
Ning
,
J.H.
(
2006
), “
Managing uncertainty in major equipment procurement in engineering projects
”,
European Journal of Operational Research
, Vol.
171
No.
1
, pp.
123
-
134
, doi: .
Table A1.

Procurement procedures

Procurement procedureGerman termDefinitionLegal basis and context
Restricted tenderBeschränkte AusschreibungA national procedure where a limited number of suppliers are directly invited to submit bids without a prior public noticeBelow EU thresholds, under VOB/A (construction) and UVgO (supplies/services)
Restricted tender with a call for competitionBeschränkte Ausschreibung mit TeilnahmewettbewerbA two-step national procedure where a public call precedes supplier selection; selected suppliers are then invited to bidBelow EU thresholds, UVgO/VOB/A
Restricted procedureNichtoffenes VerfahrenA formal EU-regulated two-stage procedure. Any supplier may apply, but only qualified candidates are invited to submit full tendersAbove EU thresholds, under GWB and VgV, per Directive 2014 / 24/EU, Art. 28
Open procedureOffenes VerfahrenA fully public procedure where all interested suppliers may submit a tenderAbove EU thresholds, under GWB/VgV, Directive 2014 / 24/EU, Art. 27
Public tenderÖffentliche AusschreibungA national equivalent of the open procedure; open to all suppliers via public noticeBelow EU thresholds, under VOB/A or UVgO
Price inquiryPreisanfrageAn informal, simplified procurement method for very low-value contracts where pricing is requested from a few suppliersBelow EU thresholds, allowed under UVgO §14 and VOB/A §3a
Negotiated procedure with tender publicationVerhandlungsverfahren mit VergabebekanntmachungA procedure where a public notice is published and selected participants negotiate the terms after initial offersAbove EU thresholds, under GWB/VgV, Directive 2014 / 24/EU, Art. 29
Negotiated procedure without tender publicationVerhandlungsverfahren ohne VergabebekanntmachungA direct negotiated process without a prior call, used only in exceptional cases (e.g. extreme urgency)Above EU thresholds, only under strict exceptions, Directive 2014 / 24/EU, Art. 32
Negotiated procedure with a call for competitionVerhandlungsvergabe mit TeilnahmewettbewerbA simplified negotiated process initiated with a public call, followed by negotiation with selected biddersBelow EU thresholds, under UVgO §12 (1) Nr. 2
Negotiated procedure without a call for competitionVerhandlungsvergabe ohne TeilnahmewettbewerbA simplified, direct award process without prior publication, typically for low-value or urgent needsBelow EU thresholds, under UVgO §8 (4) and VOB/A §3a (3)
Source(s): Authors’ own creation
Table A2.

Correlation matrix

Pearson correlations (n = 39,702)Total durationVolumeNo. of biddersNo. of applicants
Total duration10.067**−0.40**−0.38**
Volume1−0.013**−0.009
Number of bidders10.68**
Number of applicants1

Note(s): **Correlation is significant at the 0.01 level (two-tailed)

*correlation is significant at the 0.05 level (two-tailed)

Source(s): Authors’ own creation
Table A3.

Chi square for speed by volume

Statistical parametersValueDfApproximate significance (two-sided)
Pearson chi square26.341100.003
Likelihood ratio28.315100.002
Linear by linear association1.32410.250
No of valid cases42.070
Note(s):

0 cells (0.0%) have expected count less than 5. The minimum expected count is 10.03

Source(s): Authors’ own creation
Table A4.

Symmetric measures and Cramér’s V results for speed by volume

Statistical parametersValueApproximate significance
Nominal by nominal
Phi0.0250.003
Cramér’s V0.0250.003
No of valid cases42.070
Source(s): Authors’ own creation
Table A5.

Chi square for speed by tenders

Statistical parametersValueDfApproximate significance(two-sided)
Pearson chi square206.7306< 0.001
Likelihood ratio255.9256< 0.001
Linear by linear association147.4271< 0.001
No of valid cases42.070
Note(s):

0 cells (0.0%) have expected count less than 5. The minimum expected count is 6.02

Source(s): Authors’ own creation
Table A6.

Symmetric measures and Cramér’s V results for speed by tenders

Statistical parametersValueApproximate significance
Nominal by nominal
Phi0.070< 0.001
Cramér’s V0.070< 0.001
N of valid cases42.070
Source(s): Authors’ own creation
Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence maybe seen at Link to the terms of the CC BY 4.0 licenceLink to the terms of the CC BY 4.0 licence.

or Create an Account

Close Modal
Close Modal