Purpose

The purpose of this paper is to deal with the problem of integration of production and maintenance policies. In this context, the authors consider production systems made of parallel machines producing a single product over a finite horizon made of equal periods for which a forecasted demand is known. The authors investigate the impact of switching production in case of failure of any given machine.

Design/methodology/approach

A mathematical model is first developed to find an optimal production plan which minimizes the average total storage, shortage and production costs. Then, using this optimal production plan and taking into account the influence of the production rate on the degradation of each machine, optimal preventive maintenance (PM) policies are proposed for the situations with and without switching.

Findings

Optimal production rates are determined for each production period and for each machine. Optimal PM periods are also computed for each machine.

Practical implications

Usually, in manufacturing systems, the production rate of a machine influences its failure rate. In case a machine fails, it takes a random time to repair it during which production is lost. The paper attempts to propose a switching policy (SP) according to which the lost production is compensated by all the other machines. The effects of the SP coupled with the PM strategy are shown through a numerical example.

Originality/value

Contrarily to previous works, the authors consider more realistic settings with a non-negligible random time for repairing failed machines. In order to compensate the lost production during the repair of a failed machine, a SP is proposed to transfer the load uniformly to all the other machines. As a result, those machines will produce at a higher production rate and will consequently have their failure rate increased. It will therefore be essential to determine an optimal PM schedule knowing that durations of these activities are not negligible. It is shown that the simultaneous implementation of periodic PM and load transfer in case of failure is the most economical integrated strategy.

Licensed re-use rights only
You do not currently have access to this content.
Don't already have an account? Register

Purchased this content as a guest? Enter your email address to restore access.

Please enter valid email address.
Email address must be 94 characters or fewer.
Pay-Per-View Access
$41.00
Rental

or Create an Account

Close Modal
Close Modal

Gift article access

As a benefit of your subscription, you can share temporary access to restricted articles.

Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.

Please sign in to your personal account to gift article access.

Register

Gift article access

As a benefit of your subscription, you can share temporary access to restricted articles.

Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.

Gift articles remaining: --

Gift article access

Each link will stop working after 30 days or 10 uses. You may create up to 10 links in a 30 day period.

Gift articles remaining: --

Gift article access

As a benefit of your subscription, you can share temporary access to restricted articles.

Each link will stop working after 30 days or 10 uses.

You have reached the limit of 10 links within a 30 day period.