M. J. Gelderd, BSc, MIQA, 1991. "18. The development of quality management techniques for independent pre-commissioning design appraisal, inspection and test", Civil engineering in the nuclear industry: Proceedings of the conference organized by the Institution of Civil Engineers and held in Windermere on 20–22 March 1991, R Dexter-Smith
Download citation file:
The Independent Inspection Agency for the Primary Containment Structure lor Sizewell ‘B’ Nuclear Power Station was appointed in 1987. To manage and control its activities the Agency was required to establish and implement quality management systems that conformed to the requirements of BS 5882: 1980.
SYNOPSIS
INTRODUCTION
IIA FOR PRIMARY CONTAINMENT
SPECIFICATION FOR WORK TO BE UNDERTAKEN BY THE IIA
QUALITY ASSURANCE PROGRAMME
COMMUNICATIONS
COMPARISONS BETWEEN US AUTHORIZED NUCLEAR INSPECTION AGENCIES AND THE IIA FOR SIZEWELL ‘B’ PRIMARY CONTAINMENT STRUCTURE
CONCLUSION