Purpose

This research evaluates the current state of 5D building information modelling (BIM) in cost estimation and management within the architecture, engineering and construction/FM industry. It identifies key areas of interest, synthesizes industry needs and highlights research gaps by analysing a large corpus of academic articles.

Design/methodology/approach

A quantitative approach using latent Dirichlet allocation (LDA) analysed articles from Scopus and Web of Science. The methodology involved querying these databases for relevant articles on 5D BIM and cost estimation, applying LDA to identify and analyse emerging themes and synthesizing the findings for a comprehensive overview of the research landscape.

Findings

The LDA analysis reveals themes in 5D BIM for cost estimation and management, including integration with cost tools, implementation challenges and practical case studies. It also highlights technological advancements, software innovations and educational needs for effective BIM adoption. Research gaps are noted in standardization, interoperability and the long-term impacts of 5D BIM on project lifecycle costs.

Research limitations/implications

This study’s reliance on abstracts may miss key terms in full texts, though full-text analysis could introduce noise. Despite this, the findings offer valuable insights into trends and opportunities in 5D BIM research, guiding future studies and highlighting underexplored areas.

Originality/value

This study provides novel insights by using LDA to analyse a large volume of 5D BIM research articles systematically. Unlike traditional reviews, LDA enables the objective identification of latent themes across over a thousand abstracts, reducing bias and ensuring scalability. By integrating natural language processing with domain-specific expertise, the study reveals critical issues in the construction industry by identifying research gaps.

Several articles have been published discussing recent trends and research themes in building information modelling (BIM), along with their implications (Biswas et al., 2024). BIM uses digital tools and technologies to support business processes that generate shared digital representations of built assets through the design, construction and operation phases. BIM enables the production and management of information and improves communication across the entire construction life cycle (Eastman et al., 2011; Sacks et al.,2018). To achieve its full potential, BIM extends beyond geometric representation in a 3D environment (Charef et al., 2018). The third dimension (3D) provides graphical and non-graphical information within a digital model of a construction project. The fourth dimension (4D) integrates scheduling data to visualize and control project development during the construction phase. The fifth dimension (5D) manages and links cost information to the 3D model and project schedule. Nowadays, there is an increasing interest in domains linked to the geometric world of construction (3D BIM). This study focuses on BIM-based cost management (5D BIM).

The implementation of 5D BIM significantly enhances the management of design change (Harrison and Thurnell, 2015), improves the exchange of information among stakeholders and reduces errors and delays (Grilo and Jardim-Goncalves, 2010; Sattineni and Macdonald, 2014). It also facilitates the inclusion of relevant data for monitoring and managing project costs (Mesároš et al., 2019).

Before the advent of 5D BIM, cost management relied on traditional methods based on manual processes. Estimators calculated costs based on their experience and knowledge, starting from project drawings and specifications (Fazeli et al., 2021), performing quantity take-offs (QTOs) manually from 2D drawings. This process was time-consuming and error-prone.

Furthermore, cost scenario analysis using spreadsheets was challenging and inefficient. Any project changes require recalculating estimates from scratch, often resulting in outdated figures. This approach often led to delays and increased the risk of cost overruns. The accuracy of cost estimates heavily depended on the estimator’s expertise, frequently leading to inconsistencies, inconsistencies and human error (Fazeli et al., 2021; Elghaish et al.,2020).

In response to these limitations, the concept of “5D CAD” emerged in the early 2000s, extending traditional CAD models by incorporating time and cost dimensions (O’Brien, 2000). These systems enabled the simulation of construction sequences alongside cost implications, offering visual and quantitative support to decision-making. By associating components with unit costs and scheduling data, 5D CAD anticipated many of the functions now embedded within BIM platforms (Popov et al., 2010; Smith, 2014). Although less interoperable than current solutions, 5D CAD laid the foundation for integrated design-to-cost workflows that define contemporary digital construction practices.

The methodological principles introduced by 5D CAD, such as linking quantities to the cost elements of the construction process, remain central to current 5D BIM approaches. As such, the transition from 5D CAD to 5D BIM reflects a broader shift from standalone design applications to semantically rich, interoperable environments supporting lifecycle cost management (Lu et al., 2016). Recognising this evolution helps to contextualize 5D BIM as the result of progressive technological integration, rather than a completely new paradigm.

The concept of 5D BIM was formally introduced in 2010 (Charef et al., 2018; Popov et al.,2010). Since then, numerous studies have examined its potential benefits and implementation challenges (Stanley and Thurnell, 2014), as well as its adoption in real-world construction projects (Stanley and Thurnell, 2014; Lu et al., 2016). 5D BIM is now widely regarded as a promising solution to enhance the efficiency and reliability of cost management processes throughout the project lifecycle (Lu et al., 2016; Smith, 2014).

On the other hand, doubts remain regarding the actual performance improvements brought by 5D BIM adoption (Wahab and Wang, 2022). Key challenges include software security, investment in staff training and software purchase and software accessibility standards (Mesároš et al., 2019). Another major constraint is the level of information need (Sattineni and Macdonald, 2014; Aibinu and Venkatesh, 2014).

This paper aims to examine and evaluate recent literature related to cost management in BIM. This study identifies current practices and potential research gaps to guide future research investigations in the construction sector. Literature was sourced from two major scientific databases: Scopus and Web of Science.

The main purpose of this document is to answer the two questions that follow:

Q1.

What are the current applications and research related to the cost domain in BIM?

Q2.

What are the emerging issues in the published literature related to the cost domain in BIM, and what are the “grey areas” of current research?

The analysis shows that some areas remain underexplored. This research contributes to existing knowledge by synthesizing the critical needs of the BIM sector in the field of cost estimation and cost management. It also highlights current research gaps through a statistical meta-analysis of the literature. To achieve this, due to the increased number of articles, a statistical meta-analysis of literature was conducted using latent Dirichlet allocation (LDA). This method enables objective identification of latent themes across over a thousand abstracts while reducing bias and ensuring scalability.

This paper is structured as follows. Section “Method of Research” illustrates the research design method used in this paper. The first step is to give an overview of the method used: the statistical meta-analysis used to evaluate the published literature. Thereafter, the section “Results and Findings” presents the findings of the quantitative analysis conducted. Subsequently, the section “Discussion” discusses the findings by quantitative results while presenting critical issues in current research. In the final section, “Conclusion and Future Work”, the limitations of this study, the implications for future research and the contributions made in this article are outlined.

This study aims to synthesize the pressing issues related to the dimension of the cost linked to the BIM world in the architecture, engineering and construction (AEC) industry, to support BIM implementation and consolidate existing domain knowledge, thus identifying future research directions. To address these objectives, a quantitative statistical analysis of a large data set of published literature was conducted using LDA to illuminate the established 5D BIM knowledge domain. This analysis allows a complete view for validation purposes. Unlike traditional reviews, LDA enables the objective identification of latent themes across more than a thousand abstracts, reducing bias and ensuring scalability. By integrating natural language processing with domain-specific expertise, the study uncovers critical themes such as cost data management, interoperability challenges and technological integration. Furthermore, the findings address significant research gaps, offering practical pathways for the application of 5D BIM in cost estimation and project lifecycle management. This innovative use of LDA not only advances meta-analytical approaches in BIM research but also aligns academic insights with industry needs, making it a valuable contribution to the field.

The use of multiple data sources to study the same phenomenon allows researchers to detect critical issues and consistent relationships between variables. All research methods have inherent strengths and limitations; therefore, quantitative analysis allows for a broader and more objective exploration of data patterns.

The methodology used consists of a three-step process, aligned with the structure illustrated in Figure 1, and described in the following sections:

Figure 1.
A flowchart illustrating a three-step process: data collection, data analysis of topics, and results, detailing tasks involved in each step.The flowchart is structured into three sequential steps showing the progression of a research process. Step one, titled data collection, includes task boxes for defining the scope, searching keywords, and selecting databases such as Scopus and W o S. Step two, titled data analysis of topics, contains tasks for data preparation, applying latent Dirichlet allocation, and identifying topics. Step three, labelled results, involves topic labelling and identifying topic relations. Arrows connect each step to indicate workflow direction from data gathering through analysis to interpretation. The design uses clearly separated boxes for each task, arranged from left to right, highlighting a structured and logical approach to topic-based research analysis.

Workflow of the methodology adopted

Source: Created by author

Figure 1.
A flowchart illustrating a three-step process: data collection, data analysis of topics, and results, detailing tasks involved in each step.The flowchart is structured into three sequential steps showing the progression of a research process. Step one, titled data collection, includes task boxes for defining the scope, searching keywords, and selecting databases such as Scopus and W o S. Step two, titled data analysis of topics, contains tasks for data preparation, applying latent Dirichlet allocation, and identifying topics. Step three, labelled results, involves topic labelling and identifying topic relations. Arrows connect each step to indicate workflow direction from data gathering through analysis to interpretation. The design uses clearly separated boxes for each task, arranged from left to right, highlighting a structured and logical approach to topic-based research analysis.

Workflow of the methodology adopted

Source: Created by author

Close modal
  1. data collection;

  2. data analysis and topic identification; and

  3. topic labelling and validation.

Statistical meta-analysis consists of data collection (Step 1) and data analysis (Step 2). The entire data set collected was analysed using the LDA method. Step 3 presents topic labelling and topic relations.

Data collection began with the collection of abstracts from academic journals and conference articles using two databases: Scopus and Web of Science (WoS). Scopus contains over 27,500 peer-reviewed journals, 11.6 million conference papers, and over 90 million records (Scopus, 2023). The WoS database covers over 12,000 peer-reviewed journals and more than 160,000 conference proceedings (Clarivate, 2023).

The initial query aimed to identify current research on 5D BIM. A predefined set of keywords, operators and nesting combinations was applied to both databases (Table 1). Starting from articles published since 2013, a total of 1,865 abstracts were collected in June 2024. A comparative review showed a balanced distribution of articles between the two databases.

Table 1.

Overview of data extracted from research studies in Scopus and Web of Science (WoS)

KeywordsNumber ofarticles ScopusNumber ofarticles WoS
“5D BIM” OR “5D Building Information Modeling” OR “5D Building Information Modelling” OR “5D Building Information Model”10952
“Cost estimation” AND “5D BIM” OR “5D Building Information Modeling” OR “5D Building Information Modelling” OR “5D Building Information Model”2720
“Cost estimation” AND “BIM” OR “Building Information Modeling” OR “Building Information Modelling” OR “Building Information Model”244177
IFC OR “industry foundation class” OR “industry foundation classes” AND “5D BIM” OR “5D Building Information Modeling” OR “5D Building Information Modelling” OR “5D Building Information Model”62
IFC OR “industry foundation class” OR “industry foundation classes” AND “cost”333232
IFC OR “industry foundation class” OR “industry foundation classes” AND “qto” OR “quantity take off” OR “quantity-take-off”1412
“BIM” OR “Building Information Modeling” OR “Building Information Modelling” OR “Building Information Model” AND “qto” OR “quantity take off” OR “quantity-take-off”12373
ifcowl4870
“cost” AND “BIM” OR “Building Information Modeling” OR “Building Information Modelling” OR “Building Information Model” AND IFC OR “industry foundation class” OR “industry foundation classes”198120
“cost” AND “ifcOWL”23
TOTAL per database1,104761
TOTAL1,865
TOTAL without abstract3
TOTAL without duplicate and abstract1,284
Source(s): Created by author

The collected data were stored in text files and contained the following information: authors, titles, year, type of publication, abstracts and keywords. Since the analysis is based on abstracts, any entries without one were excluded. In total, three text files were removed from the database. In addition, 507 duplicate articles were eliminated. The final cleaned data set comprised 1,281 unique abstracts used for the analysis.

Considering the large volume of extracted articles, a statistical meta-method was selected to identify the dominant knowledge domains in the BIM cost area.

Several statistical meta methods currently exist, such as the term frequency–inverse document frequency scheme (Salton and McGill, 1986), latent semantic indexing (Deerwester et al., 1990) and probabilistic latent semantic analysis (Hofmann, 1999) and LDA (Blei et al., 2001).

LDA was chosen for its ability to model the co-occurrence of words across large corpora, allowing efficient extraction of underlying topics. Compared to other methods, LDA is less prone to overfitting and enables an objective evaluation of extensive textual data (Blei et al., 2001). While bibliometric analyses often rely on subjective selection criteria, LDA reduces such bias by using unsupervised learning techniques. LDA is a topic modelling technique developed in the fields of natural language processing, machine learning and computer science to retrieve and query bodies of large data (Blei et al., 2001). It defines “corpus” as a collection of “M” documents, “document” as a sequence of “N” words and “word” as the basic unit of the data (Blei et al., 2001). It uses documents as representations of themes, where each topic comprises a collection of keywords represented in a certain proportion. LDA provides an automated procedure for sorting the contents of a corpus of text data into a set of meaningful “topics”. The algorithm automatically groups terms into a meaningful set of topics with minimal human intervention.

The analysis was implemented using Python 3.10, a widely used object-oriented programming language. Python was selected due to several advantages:

  • It provided quick development and test activities as Python can be executed directly without the need to compile an executable format – the script was executed using Jupyter Notebook to optimize the execution of the algorithm of analysis (Project Jupyter, 2023) or using Visual Studio Code, installing the available extensions to execute the code;

  • It offers several dedicated packages for the development of natural language processing [e.g. the Natural Language Toolkit package (Bird et al., 2008)], and topic modelling applications [e.g. the Gensim package (Rehurek and Sojka, 2010)]; and

  • It allows easy reading and code transparency for dissemination, verification and re-use in future research.

Data preparation.

Before applying the LDA, the data set was pre-processed to improve the reliability of topic extraction. These steps included:

  • tokenizing abstracts into a “bag of words”;

  • converting all letters to lowercase;

  • removing all stop words (e.g. “so”, “and” and “or”) using the English stop word dictionary provided by the Natural Language Toolkit (NLTK) package for Python;

  • eliminating all forms of punctuation;

  • excluding words with fewer than three characters due to their irrelevant significance in the text; and

  • removing numerical characters and overly common domain-specific terms that appeared across all topics.

A personalised set of words was defined by the authors and removed from the corpus following a series of iterations of the algorithm on the available data [1]. This has led to the elimination of even terms that are predominant transversally on all topics and therefore do not characterize them.

After pre-processing, a stemming algorithm technique (Hotho et al., 2005) was applied to consolidate words with the same roots [2]. The identification of n-grams was included to identify possible correlations because LDA does not evaluate the sequencing of words in texts analysed. An n-gram is an aggregation of single words processed during the tokenization of a set of words, where n identifies the number of words considered in the aggregation. For example, the bi-gram “cost-estimation” reflects the joint significance of both terms. Based on findings in previous research (Yalcinkaya and Singh, 2015), the inclusion of bi-grams improved topic coherence. The use of three grams in this research did not provide significant improvements to the data analysis.

Latent Dirichlet allocation.

After that, the cleaned data were applied to the vector representation process, in which each document was represented as a set of words occurring across the corpus. A unique ID was assigned to each word, thereby creating a “dictionary”. Consequently, documents were represented as numerical arrays, where each number corresponded to a specific word. The algorithm then counted the frequency of each word in each document and linked it to its corresponding ID. As a result, each document was encoded as a sparse vector, suitable for input into the LDA transformation model.

LDA requires a predefined number of topics as input data. The algorithm’s performance was evaluated through a quality assessment procedure, which determined the optimal number of topics based on thematic clarity and model output quality. This assessment relied on the UCI coherence score, a quantitative metric that measures how well the identified topics represent the underlying corpus (Röder et al., 2015). To this end, the LDA model was tested using four configurations: 5, 10, 15 and 20 topics. The coherence score remained high (approximately 0.63) for both the 5- and 10-topic models but dropped to around 0.60 for 15 and 20 topics. Based on the comparative results, the authors selected the five-topic model as the most effective solution, noting that the 10-topic model contained significant thematic overlap between topics.

Topics identification.

Once the LDA model was finalized, each document was associated with a probability distribution across topics. Based on this distribution, a dominant topic was assigned to each document, effectively clustering them into thematic groups. It is important to note that emerging topics may not include all existing research areas, as the model tends to highlight only the most prevalent themes based on their statistical relevance and frequency within the data set. Topics with fewer occurrences, corresponding to underrepresented areas in the literature, may fall below the detection threshold and thus be omitted. These represent so-called “grey areas” or emerging fields in the academic discourse. For instance, in Topic 0, the frequency of the top 10 keywords ranged between 1.0% and 4.5%, while any keyword appearing in less than 1.0% of documents was excluded by the algorithm.

To ensure robustness and consistency, the topic modelling process was iterated ten times for each configuration (i.e. 5, 10, 15 and 20 topics). This approach aimed to verify the stability of the most significant keywords and confirm their dominance relative to other terms. Given the probabilistic nature of the method, the keywords identified may vary slightly across runs. Therefore, a consistency score was calculated for each output. Ultimately, the version with the highest consistency score (closest to 1) was selected for the final analysis.

Step 3 comprised topic labelling and the identification of thematic relationships. Three authors and three external experts in the field independently interpreted the LDA results and proposed topic labels. Subsequently, they convened to discuss and consolidate their interpretations, ensuring consistency and alignment. In this phase, the first author collected the results of the LDA analysis in an Excel spreadsheet. This file was then distributed to the other two authors and three external experts, including a representative from a construction company and two professional engineers. Each participant independently reviewed the data and proposed labels for each data cluster.

The individual assessments were then collected and compared. A collaborative meeting was held to discuss discrepancies and refine the topic definitions. This process ensured a comprehensive and multidisciplinary evaluation, enhancing both the robustness and validity of the identified topics while minimizing individual bias.

The final set of topics resulting from this procedure is presented in the section “Results of the Statistical Analysis”.

The results are based on the quantitative analysis, which presented topics related to 5D BIM research identified in existing literature. The synthesis of quantitative results offers an interpretative framework for understanding key arguments to inform future 5D BIM research (Creswell and Creswell, 2017). The main research areas have been clearly identified, and the outcome of the Quantitative analysis [3] is presented in Table 2. This table shows, in percentage terms, the frequency of keywords identified across the Topic clusters through the statistical process. These keywords, derived from the iterative LDA procedure, were considered optimal for representing the primary research domains in the field.

Table 2.

Quantitative analysis results

TopicK0K1K2K3K4K5K6K7K8K9
Topic 0%0.0050.0050.0050.0040.0040.0030.0030.0030.0030.003
keyconstructdatacostprocessestimprojectusemethodsystemwork
Topic 1%0.0140.0100.0090.0080.0070.0060.0040.0040.0040.003
keycostconstructestimdataprojectcost_estimmethodprocessmanagsystem
Topic 2%0.0090.0090.0090.0070.0050.0050.0040.0040.0030.003
keyprojectcostconstructdatamanagprocessestimmethoduseindustri
Topic 3%0.0080.0060.0050.0040.0040.0030.0030.0030.0030.002
keyconstructcostprojectprocesssystemuseenergidatamanagindustri
Topic 4%0.0060.0050.0040.0040.0040.0030.0020.0020.0020.002
keyconstructcostprojectdatasystemprocesssemantuseontologmanag
Source(s): Created by author

The research identified 5 different macro areas, Topic 0-1-2-3-4 (Table 2), in which to divide the current research. Table 3 summarizes the main research areas divided by the Topic clusters identified through the analysis performed according to the methodology described in the section “Method of Research”. The five topics identified are:

Table 3.

Main topics analysis

TopicTopic labelNo. of paper%
0Technology and methods for cost data21917.06
1Cost estimation data management and methods33426.01
2Project cost data processes, methods and management36228.19
3Energy design and use cost management21016.36
4Cost data ontology15912.38
Source(s): Created by author
  1. technology and methods for cost data;

  2. cost estimation management methods;

  3. cost and estimation data management;

  4. energy design and use costs management; and

  5. cost data ontology.

Each topic is listed with the corresponding number of articles and percentage of total articles analysed (1,284 abstracts). The key topics of the 5D BIM dimension, underlying the idea of better and more efficient cost management and estimation (Elghaish et al., 2020), appear in each topic, and this confirms what is initially defined by the search keys.

The analysis has identified five key topics illustrating the different applications of 5D BIM in research. These topics highlight the significance and advancements BIM brings to the construction industry in the field of cost.

Topic 0: technology and methods for cost data.

This topic emphasizes leveraging technological advancements and methodological approaches for effective cost data management in construction projects. BIM and automation enhance data accuracy and project efficiency.

Topic 1: cost estimation data management and methods.

Efficient cost estimation and data management are crucial for successful project planning and execution. This section examines how BIM-enabled strategies and methodologies ensure accurate cost estimation from the early design phases, facilitating precise financial forecasting and better resource allocation throughout the project.

Topic 2: project cost data processes, methods and management.

Streamlined cost management processes are critical for keeping projects on schedule and within budget. This section explores how BIM enhances the management and optimization of cost data throughout the entire project lifecycle, from initial planning to execution, improving overall project outcomes by integrating efficient cost control methods.

Topic 3: energy design and use cost management.

Managing costs related to energy-efficient design and usage is vital for sustainable construction. BIM helps optimize energy performance, evaluate lifecycle costs and reduce operational expenses.

Topic 4: cost data ontology.

Cost data ontology is a structured approach that categorizes and correlates cost information, enhancing interoperability and data integration. This section discusses the development and application of cost data ontologies in BIM.

Overall, the trend of research results for the five topics identified, in Figure 2, provides a comprehensive overview of 5D BIM trends and shows an increasing interest in this field in recent years. Current trends indicate that this sector will continue to play a significant role in construction management. The observed decline in 2024 is attributable to the analysis only considering publications from the first half of the year. By projecting a uniform distribution of publications for the entire year and thus doubling the number of articles identified in the first half of 2024, using dashed lines in Figure 2, it is possible to observe how the year-end estimate confirms the growth and interest in the topics analysed for all five identified subjects.

Figure 2.
A line graph shows publication trends from 2013 to 2024 across five cost-related research topics in construction and energy design.The line graph presents the number of publications for five research topics across the years 2013 to 2024. The horizontal axis is labelled year of publication and spans from 2013 to 2024. The vertical axis is labelled number of publications and ranges from 0 to 60 in intervals of 10. Each of the five lines represents a specific topic: technology and methods for cost data, cost estimation data management and methods, project cost data processes methods and management, energy design and use cost management, and cost data ontology. The lines follow yearly publication counts with some showing gradual increases, others remaining relatively stable or fluctuating. Dotted line segments beyond 2023 suggest projected values for future research outputs. A legend on the right matches each topic with its corresponding line style and shade, allowing for clear distinction between research areas.

Temporal evolution of publications across identified topics (2013–2024)

Source: Created by author

Figure 2.
A line graph shows publication trends from 2013 to 2024 across five cost-related research topics in construction and energy design.The line graph presents the number of publications for five research topics across the years 2013 to 2024. The horizontal axis is labelled year of publication and spans from 2013 to 2024. The vertical axis is labelled number of publications and ranges from 0 to 60 in intervals of 10. Each of the five lines represents a specific topic: technology and methods for cost data, cost estimation data management and methods, project cost data processes methods and management, energy design and use cost management, and cost data ontology. The lines follow yearly publication counts with some showing gradual increases, others remaining relatively stable or fluctuating. Dotted line segments beyond 2023 suggest projected values for future research outputs. A legend on the right matches each topic with its corresponding line style and shade, allowing for clear distinction between research areas.

Temporal evolution of publications across identified topics (2013–2024)

Source: Created by author

Close modal

In addition, Figure 3 shows the total number of 5D BIM publications since 2013 in each Topic.

Figure 3.
A bar chart compares the total number of publications across five topics, with Topic 2 having the highest count at 362.The bar chart displays the total number of publications for five distinct topics, labelled Topic 0 through Topic 4. The horizontal axis represents the topic labels, while the vertical axis shows publication counts ranging from 0 to 400. Topic 2 has the highest number of publications at 362, followed by Topic 1 with 334, Topic 0 with 219, Topic 3 with 210, and Topic 4 with 159. Each bar extends vertically to represent the exact value, and the numerical count is clearly shown at the top of each bar for easy reference.

Total number of publications per identified topic (2013–2024)

Source: Created by author

Figure 3.
A bar chart compares the total number of publications across five topics, with Topic 2 having the highest count at 362.The bar chart displays the total number of publications for five distinct topics, labelled Topic 0 through Topic 4. The horizontal axis represents the topic labels, while the vertical axis shows publication counts ranging from 0 to 400. Topic 2 has the highest number of publications at 362, followed by Topic 1 with 334, Topic 0 with 219, Topic 3 with 210, and Topic 4 with 159. Each bar extends vertically to represent the exact value, and the numerical count is clearly shown at the top of each bar for easy reference.

Total number of publications per identified topic (2013–2024)

Source: Created by author

Close modal

The analysis of topics has shown that 5D BIM is currently being used across various research fields. These topics delve into strategies, tools and challenges related to managing cost data from the initial design stages. The importance of organising and managing costs in project networks is therefore crucial.

The five topics identified by the statistical analysis are described and analysed below.

The first topic, “Technology and Methods for Cost Data”, emphasizes the role of technological advancements and methodologies, particularly BIM, in shaping cost data management. The integration of tools like BIM and automation of QTO has been acknowledged in both research and industry for their potential benefits (Rouhanizadeh et al., 2021; Gohil et al.,2022; Valinejadshoubi et al., ,2024). However, despite this recognition, the economic advantages of BIM are often seen as intangible and unclear, posing a barrier to its widespread adoption (Barlish and Sullivan, 2012; Jin et al.,2017; Zhang et al., ,2018; Cezar et al., ,2023; Jafary et al., ,2024). Consequently, these perceived economic benefits are frequently regarded as a significant barrier to the widespread adoption of BIM, as indicated by the research conducted by Papadonikolaki and Aibinu (2017) and Tan et al. (2019).

Furthermore, accurate cost feedback is essential for early design decision-making, but it is challenging for cost estimators to provide precise estimates when the project is evolving and incomplete (Sepasgozar et al., 2022). The adoption of 5D BIM technologies aims to address this issue by reducing manual workloads and enhancing precision and timeliness (Mesároš et al., 2019; Forgues et al.,2012). Traditional cost estimation methods, which often involve outdated workflows and non-digital processes, are prone to errors and inefficiencies (Agostinelli et al., 2019). This makes cost estimates less reliable, yet there is growing interest in BIM as a solution to these challenges, driven by the realization that traditional standards no longer align with BIM-based systems (Banihashemi et al., 2022). BIM offers a structured approach to aligning cost and quantity data, facilitating a seamless workflow and improving project document updates. By addressing cost and delay issues, BIM’s automated monitoring capabilities are vital in the AEC sector (ElQasaby et al., 2023).

The 5D BIM methodology enables more efficient information exchange, reduces errors and offers a clear budget and construction progress to stakeholders (Grilo and Jardim-Goncalves, 2010; Sattineni and Macdonald, 2014; Mesároš et al., ,2019). In addition, it provides faster cost feedback, leading to improved customer satisfaction (Pasquire et al., 2011). The 5D model’s ability to directly associate unit costs with specific quantities enhances safety and optimizes cost management throughout the project (Abdel-Hamid and Abdelhaleem, 2023). A study by Abdel-Hamid and Abdelhaleem (2023) demonstrated that the gap between planned and actual costs decreased from 12% to 5% with 5D BIM (Abdel-Hamid and Abdelhaleem, 2023).

Various BIM-based software applications facilitate the integration of BIM into cost estimation (Abanda et al., 2017; Toan et al., 2023). These tools, such as Autodesk Revit (Autodesk, 2023), offer fundamental modelling capabilities and essential features for calculating user costs associated with building components. In addition, there are specialized cost-measurement software solutions like CostX (Exactal, 2023), Vico Estimator (Trimble, 2023) and Innovaya Visual Estimating (Innovaya, 2023).

However, interoperability issues persist, particularly between 3D, 4D and 5D modelling, preventing full realization of BIM’s potential (Moshtaghian and Noorzai, 2023; Ramaji et al., 2018; Yoon and Pishdad-Bozorgi, 2022). There are still several doubts about the actual improvement given by the application of 5D BIM methodology (Wahab and Wang, 2022; Moses et al.,2020). It is worth noting that the extent of 5D BIM implementation varies among different countries (Mesároš et al., 2019).

From this need emerged numerous studies have developed automated systems to improve cost estimation accuracy through tools like quantity extraction and open standards such as Industry Foundation Classes (IFC) (Fazeli et al., 2021; Rouhanizadeh et al., 2021; Le et al., ,2021; Liu et al., ,2014; Alzraiee, 2022; Ma et al., ,2013; Gökçe et al., ,2013). These systems promise quicker, more accurate processes for cost management (Yao et al., 2020; Sherafat et al.,2022; Han et al., ,2017). Agostinelli et al. (2019) proposed a framework for cost planning that automatically updates quantities as models change (Agostinelli et al., 2019). Other studies, like those by Le et al. (2021) and Akanbi and Zhang (2017), focus on BIM-database integration for more precise cost estimation (Le et al., 2021; Akanbi and Zhang, 2017). Stransky and Dlask (2018) focused on a semi-automatic process to identify and link work items between BIM models and cost estimating software (Stransky and Dlask, 2018).

While several software solutions exist for 5D BIM (Mesároš et al., 2019; Smetanková et al., 2018; Vigneault et al., ,2020), issues remain. Using various software necessitates additional effort to synchronize all data about cost, schedule and quantities (Suarez et al., 2020). The need for manual inputs to complete cost estimation processes is a significant weakness in the automation of construction cost estimation. Several studies introduced NLP techniques to address this gap, automating the alignment of BIM elements with cost items (Akanbi et al., 2019; Akanbi and Zhang, 2020; Nabavi et al., ,2023; Shahinmoghadam et al., ,2024; Yin et al.,  2023).

Similarly, integrating BIM with virtual reality (VR) offers a way to automatically compute costs when project changes occur (Wang and Tung, 2023; Lee et al.,2022).

Data management and cost estimation methods are crucial for the success of construction projects in the AEC sector. The process of construction cost estimation is inherently labour-intensive and requires accurate data collection, management and analysis of materials, labour and costs (Lee et al., 2022; Ma and Liu, 2014; Herdyana and Suroso, 2023). Accurate cost estimation is essential for budgeting and tendering in construction projects, involving direct costs like materials, labour and professional services (Samphaongoen, 2010; Olatunji et al., 2010).

Cost estimation is a dynamic and knowledge-intensive process, comprising two components: quantities of design elements (e.g. concrete columns) and process quantities related to construction tasks (e.g. labour hours for concrete casting) (Marzouk et al., 2018). Engineers typically rely on design plans, specifications and available cost data to calculate material quantities and assign unit costs, often based on their judgment (Xu et al., 2015a, 2015b). BIM tools, particularly 5D BIM, help automate these calculations, reducing manual work and improving data accuracy (Elghaish et al., 2020; Alsamarraie and Ghazali, 2023).

The integration of BIM with QTO functionality offers a higher degree of precision in cost estimation, directly linking extracted quantities with cost databases (Azhar, 2011; Bryde et al., 2013). This process reduces the time engineers spend on manual quantity measurement (Choi et al., 2015). The most common method involves associating digital object codes with price items from cost databases (Pavan et al., 2017). In addition, BIM-based clash detection has been shown to lead to significant cost savings by refining processes and improving detection accuracy (Chahrour, 2021).

Despite these advantages, research on BIM adoption in QTO remains fragmented (Mesároš et al., 2019; Alzraiee, 2022; Zhao and Wang, 2014), with significant gaps in functionality. Traditional BIM models often lack essential information for QTO, and the calculations may not align with prescribed rules in standard methods of measurement, compromising the accuracy of cost estimation (Han et al., 2017; Liu et al., 2021; Yang et al., ,2022). Furthermore, engineers must still manually verify work items and assign costs, a process complicated by low-level development (LOD) of BIM models [Sattineni and Macdonald, 2014; Aibinu and Venkatesh, 2014; International Organization for Standardization (ISO), 2023, Issues like differences in layer dimensions for elements such as architectural walls, or overlapping structural elements in low LOD models, hinder cost estimation accuracy (Khosakitchalert et al., 2018; Lee et al., 2015).

While the potential of BIM to enhance cost control is widely acknowledged, the exploration of its full capabilities is ongoing. Several studies are investigating how BIM can improve cost estimation accuracy, surpassing traditional manual methods (Haider et al., 2020; Clark, 2019; Matejka and Vitasek, 2018). Research by Zhao and Wang (2014) and Khaleel and Naimi (2022) has shown that BIM technologies like Revit can significantly improve the accuracy of cost estimates compared to manual methods (Zhao and Wang, 2014; Khaleel and Naimi, 2022; Shen and Issa, 2010).

In construction projects, cost, schedule and quality targets are critical parameters for determining project success (Silva and Warnakulasooriya, 2017; Hui et al.,2023; Abdel-Hamid and Abdelhaleem, 2023). Assessing economic viability at an early stage is essential for informed decision-making and project realization (Bender and Stoy, 2021; Nsimbe and Di, 2024). However, managing project cost data goes beyond initial cost estimation and encompasses the entire project lifecycle (Wan Abdul Basir et al., 2023; Inzerillo et al., 2024). Effective management of cost data is crucial for accurate planning, monitoring and control throughout the project (Chen, 2023).

Managing cost data requires robust processes, methods and strategies to ensure accurate tracking and control. Achieving this goal demands more than just estimating costs; it involves comprehensive data management practices. One of the primary challenges is ensuring efficient data exchange, not only within the cost domain but also across different domains and disciplines. Efforts in the architecture, engineering, construction and owner industry have focused on improving data interoperability across various software systems. BIM serves as a strong foundation for collaborative data management, supporting efficient monitoring and control of processes like design, planning, cost control, construction and maintenance (Ruano-Ruiz et al., 2022).

While modern methodologies offer real-time data accessibility and integration, traditional construction project management approaches are often linear and fragmented, hindering seamless data exchange and resulting in project delays and budget overruns (Chen et al., 2021). The use of diverse BIM software tools by different stakeholders can also lead to inconsistencies, data gaps and reduced operational efficiency (Ren et al., 2022; Leicht et al., 2020; Keerthana and Gunarani, 2019).

To address these challenges, buildingSMART has introduced IFC, a standardized schema to enhance data interoperability across different software applications. This schema helps ensure data consistency, improving collaboration within the industry (Cheng and Wu, 2013).

The integration of cost models within BIM is an evolving field. New standards, such as ISO 16739 (IFC4), have introduced additional entities and properties to expand BIM’s capabilities [International Organization for Standardization (ISO), 2018]. While the representation of process-based cost information through IFC4 objects shows promise, further development is needed to fully realize this potential (Isatto, 2021). IFC data structures hold significant potential for improving information integration and interoperability, providing a standardized platform for various BIM software, reducing complexity and lowering project costs (Ramaji and Memari, 2015).

Sustainable practices, particularly energy efficiency, have gained significant attention in the construction industry. Managing energy-related costs in construction projects is crucial for maximizing energy-efficient building components, evaluating life-cycle costs and reducing long-term operating expenses. Effectively managing energy design and use costs is vital for constructing environmentally friendly and cost-effective buildings.

Recent research highlights key themes and challenges in energy design and use cost management, particularly the use of 5D BIM models. These models provide comprehensive insights into all costs associated with building projects, enabling better decision-making regarding energy-efficient components (Pučko et al., 2020; Wasim et al., 2023).

In addition, the analysis of building envelope shape, especially for amorphous buildings, using IFC has improved the reliability of design proposals and cost prediction by incorporating building performance at the initial design stage (Choi and Lee, 2023; Choi and Lee, 2023).

Interoperability between BIM and building energy models has also been a key focus, especially regarding the structured data for material properties, which enhances the efficiency of the mapping process (Turkyilmaz, 2013; Porsani et al., 2021; Ahn et al., ,2014; Santos et al., ,2017). However, despite the existence of dedicated databases, the lack of a common property set for building materials complicates the mapping process, hindering the integration of energy performance data with cost estimation models (Fenz et al., 2021).

A significant challenge in economic analysis is obtaining cost data based on energy performance, particularly in the early design phases. This often results in postponing quantitative economic analyses until later stages, when making changes becomes more costly and difficult (Rafati Sokhangoo et al., 2019).

The management of energy design and use costs is a dynamic and evolving field, with significant potential to improve sustainability and cost-effectiveness. BIM and IFC technologies are crucial in addressing the complexities of energy-efficient building design and management, yet challenges remain in fully integrating energy performance data with cost analysis tools.

The construction industry is increasingly adopting ontologies and semantic technologies to improve the management and utilization of cost data. This theme explores the development and implementation of cost data ontologies, which provide a standardized, structured representation of cost-related information. These ontologies facilitate seamless data exchange and interoperability among stakeholders, contributing to the evolution of more efficient and interconnected cost data management systems.

The integration of ontologies with BIM has become a significant trend, enhancing the organization and use of cost-related data (Santos et al., 2017; Xu et al., 2013). Cost data ontologies enable a structured representation of information, standardizing data exchange across stakeholders (Abanda et al., 2017; Choi and Lee, 2023).

Notably, the integration of BIM with ontological inference has shown promise in improving cost estimation and work item classification, with BIM automating the search for suitable work items, such as in tiling methods. Ontologies also play a key role in standardizing measurement methodologies, such as the new rules of measurement (NRM), which improves the precision of cost estimation during the tendering phase (Ma et al., 2013). Lee et al. (2014) introduced an ontological approach to automate work item selection, enhancing consistency and reducing subjectivity, thereby supporting BIM-centric construction management practices (Lee et al., 2014). Abanda et al. (2017) further explored the automation of cost estimation using BIM and an ontology based on NRM (Abanda et al., 2017).

However, a critical need remains for ontology-based platforms that can quickly create BIM applications with reasoning support, addressing challenges in cost estimation and overall interoperability. The combination of BIM and ontological technologies has demonstrated potential in automating cost management, compliance checking and green building evaluation (Narlawar et al., 2019). Jia et al. (2022) proposed an approach to automatically generate finite element models from BIM using OpenBIM and IFC to streamline cost management processes (Jia et al., 2022). Guo et al. (2020) introduced a technique for automatically generating SPARQL queries to facilitate data extraction (Guo et al., 2020).

In the AEC/FM industry, ontologies like ifcOWL are widely used to improve data exchange and cost estimation through enhanced interoperability (Gökçe et al., 2013; Ren et al.,2021; Vakaj et al., ,2020; Pauwels and Terkaj, 2016; Terkaj and Šojić, 2015; Beetz et al., ,2009). This ontological approach enables more accurate evaluations of design alternatives, further optimizing the cost estimation process (Xu et al., 2013). Xu et al. (2016) and Liu et al. (2016) proposed semantic web-based ontologies for cost item generation and QTO from BIM models, respectively (Xu et al., 2016; Liu et al.,2016). Lawrence et al. (2014) proposed an approach to cost estimation by mapping the BIM objects to cost information (Lawrence et al., 2014). Abanda et al. (2015) introduced an ontology-based approach utilizing the UK standard method of measurement for cost estimation (Abanda et al., 2015). Ma et al. (2016) developed a methodology that uses ontology to formalize specifications for construction cost estimation in China (Ma et al., 2016). In addition, Abanda et al. (2016) and Abanda et al. (2014) developed an ontology based on NRM to enhance QTO and cost estimation processes during the tendering phase of construction projects (Abanda et al., 2016; Abanda et al., 2014). Fürstenberg et al. (2021) investigated the use of semantic web technology to facilitate BIM-based automated cost estimation linked to an IFC property set (Fürstenberg et al., 2021).

Despite these advancements, the challenges in the construction sector remain substantial. The successful integration of BIM and ontological approaches requires deep knowledge of cost estimation processes and the extension of pricing data (Biolek et al., 2019).

As technology continues to evolve, the construction industry must adapt to improve cost estimation efficiency and accuracy, paving the way for better decision-making and streamlined processes. By integrating BIM, ontologies and advanced reasoning support tools, the future of construction cost management holds great promise, ultimately reducing errors and enhancing cost efficiency (Xiao et al., 2022).

In the field of construction cost management, many advances have been made, particularly with the integration of technologies such as 5D BIM. However, several research gaps and challenges remain, which prevent the full implementation of these technologies in the cost estimation, management and decision-making processes. Summarized general research gaps for all the topics:

  • Technology and methods for cost data: Despite advancements in BIM and automation tools, the integration and interoperability between BIM models and cost estimation software remain key challenges. Manual data input continues to hinder seamless alignment, preventing the full realization of BIM's potential in cost management (Inzerillo et al., 2024; Chen, 2023).

  • Cost estimation data management and methods:BIM models often lack the necessary granularity for accurate QTO and manual verification of cost items remains common, leading to inconsistencies and errors that limit BIM’s ability to streamline and automate cost estimation [International Organization for Standardization (ISO), 2018; Ahn et al., 2014].

  • Project cost data processes, methods and management:BIM and IFC provide a strong foundation for cost data management, but further advancements are needed to fully integrate process-based cost information. Current integration between BIM and cost estimation tools is fragmented, requiring more sophisticated methods for handling cost data across different software systems (Wan Abdul Basir et al., 2023; Ren et al., 2022).

  • Energy design and use costs management: The lack of standardized property sets for material data and the late-stage consideration of energy performance cost data hinder the integration of energy-efficient design and cost optimization within BIM, particularly during early design phases [International Organization for Standardization (ISO), 2018; Porsani et al., 2021].

  • Cost data ontology: Despite progress, challenges remain in extending pricing data and integrating ontology-based platforms with BIM. A standardized ontology that encompasses all aspects of cost data, including pricing and material properties, is still lacking and requires further development (ElQasaby et al., 2023; Fenz et al., 2021).

Table 4 presents a comprehensive overview of the main research gaps, challenges and future directions, specifically focusing on the five identified topics within BIM in the construction sector. These topics represent a balanced spectrum of research opportunities, ranging from areas with substantial existing literature to those still underexplored. By highlighting these gaps, the table aims to guide future research efforts and facilitate a clearer understanding of where innovation and further investigation are most needed.

Table 4.

Research gaps, challenges and future directions in 5D BIM

TopicResearch gapsChallengesFuture directions
0. Technology and methods for cost dataIntegration and interoperability between BIM models and cost estimation tools remain significant barriers. The alignment between BIM elements and cost items is not fully realizedFragmentation of BIM systems and cost estimation tools requires manual intervention. Lack of standardized methods for full automationDevelopment of standardized protocols for integrating BIM models with cost estimation tools. Creation of unified systems to reduce manual data input
1. Cost estimation data management and methodsBIM models often lack sufficient detail to support accurate cost estimation. Manual verification of cost items is still requiredInconsistency in data provided by BIM models and reliance on manual verification lead to inaccuraciesEnhancing the granularity of BIM models and automating data verification. Development of sophisticated tools to ensure data consistency
2. Project cost data processes, methods and managementNeed for cost models that integrate process-based information. Interoperability across different software systems is still insufficientFragmented data management systems hinder data sharing across different software platforms. Lack of comprehensive cost models in BIMDevelopment of advanced cost models that integrate process-based information and ensure smooth interoperability between software systems
3. Energy design and use costs managementLack of standardized property sets for material data. Energy-related costs are considered too late in the design processDifficulty in integrating energy performance data. Delays in considering energy costs during the early design stagesDevelopment of standardized property sets for materials and improved integration of energy data in BIM models Incorporating energy costs earlier in the design process
4. Cost data ontologyLack of standardized ontologies covering all aspects of cost data. Incomplete integration of ontologies into existing construction workflowsIncomplete ontologies for cost data hinder automation of cost estimation. Existing platforms need improvement to support real-time reasoningDevelopment of comprehensive ontologies that cover all aspects of cost data. Creation of ontology-based platforms to automate cost estimation and enhance interoperability
Source(s): Created by author

The primary significance of this article lies in its quantitative analysis of the current state of the art in 5D BIM. This analysis has enabled researchers to focus on critical industry needs while simultaneously contextualizing ongoing 5D BIM research within the framework of industry experience. Moreover, it serves the essential function of directing future research endeavours. In this context, LDA was used to analyse a large corpus of published literature, offering several methodological and practical advantages. From a methodological perspective, LDA enables the objective identification of latent themes in large-scale literature data sets, reducing human bias typically associated with manual thematic coding. It supports scalability and reproducibility, which are essential in growing research fields such as 5D BIM. Practically, LDA-based topic clustering can inform academic curricula by highlighting underexplored areas, guide funding priorities by identifying research gaps and support industry stakeholders in tracking the evolution of cost-related BIM research.

However, LDA also presents certain limitations. Firstly, it relies on the statistical co-occurrence of words and does not account for deeper semantic meaning or contextual nuances. Secondly, the granularity of topic interpretation is influenced by parameter tuning and subjective labelling, which, despite expert validation, may affect consistency across studies. Thirdly, the analysis is based solely on abstracts, which may exclude important terms present in the full text.

Despite these limitations, the integration of LDA into systematic literature reviews represents a robust and efficient approach that bridges theory and practice. It contributes to the body of knowledge by offering a replicable methodology for mapping complex research domains and has the potential to influence both academic research directions and applied innovation in the AEC sector.

In this review, five topics related to 5D BIM were presented and analysed starting from the data of the LDA analysis:

  1. technology and methods for cost data;

  2. cost estimation data management and methods;

  3. project cost data processes, methods and management;

  4. energy design and use costs management; and

  5. cost data ontology.

From this analysis, it has emerged that the management of cost data in the construction field is undergoing a transformation due to the integration of BIM, ontologies and advanced technologies. This evolution improves cost estimation accuracy, data exchange and interoperability, leading to more efficient and sustainable construction practices. However, key barriers persist. These include interoperability challenges between cost estimation tools and BIM platforms, the lack of standardized property sets for building material data and the need for manual data inputs in cost estimation workflows. Overcoming these issues is essential to fully unlock the potential of 5D BIM in promoting cost-effective and sustainable construction.

Overall, this article establishes an objective and empirical foundation for analysing the state of research in the 5D BIM domain. The research areas and themes identified highlight current trends and future opportunities that can benefit both industry and academia. The findings help current BIM researchers position their work within a broader thematic framework and assist emerging scholars in identifying relevant directions for future inquiry.

The gaps identified in this study can be addressed by practitioners and researchers who may use this work as a roadmap. By leveraging the detailed analysis of existing challenges, future research can focus on overcoming barriers in interoperability, automation and standardization, accelerating the adoption of advanced 5D BIM methodologies.

This article significantly contributes to the field by outlining the current research landscape in 5D BIM and suggesting pathways for future exploration. However, it has limitations, notably the exclusive reliance on abstracts, which may omit nuanced content present in full-text articles. While full text analysis could provide additional depth, it may introduce noise. Despite this, the study examined a substantial number of abstracts, identifying trends, albeit not exhaustively. To address gaps, keywords related to interoperability, cost and other dimensions were closely examined. The statistical method employed possible variation due to randomness in document clustering. To mitigate bias, the labelling phase involved six independent reviewers, leading to convergent and validated results.

In conclusion, this study used LDA as the primary analytical method. However, other statistical approaches could be explored in future research to validate or complement these findings. As a potential extension, this methodology could be applied to other BIM dimensions, such as 4D BIM, to evaluate cross-dimensional relationships and thematic consistency.

[1.]

Delete list used in the algorithm: [‘abstract: ‘, ‘ab ‘, “.\n”, ‘elsevier’, ‘bridg’, ‘queri’, ‘algorithm’, ‘network’, ‘function’, ‘propos’, ‘oper’, ‘cell’, ‘develop’, ‘approach’, ‘stage’, ‘check’, ‘applic’, ‘evac’, ‘qualiti’, ‘compon’, ‘layout’, ‘ation’, ‘patient’, ‘waste’, ‘commun’, ‘gener’, ‘image’, ‘social’, ‘rural’, ‘review’, ‘predict’, ‘china’, ‘firm’, ‘relev’, ‘repres’, ‘build’, ‘building’, ‘inform’, ‘model’, ‘also’, ‘paper’, ‘research’, ‘mine’, ‘need’, ‘needs’, ‘finding’, ‘findings’, ‘purpose’, ‘result’, ‘results’, ‘present’, ‘presents’, ‘provide’, ‘provides’, ‘include’, ‘includes’, ‘require’, ‘requires’, ‘improve’, ‘life’, ‘base’, ‘current’, ‘output’, ‘outputs’, ‘switch’, ‘path’, ‘increase’, ‘decrease’, ‘cover’, ‘covers’, ‘differ’, ‘differs’, ‘high’, ‘year’, ‘years’, ‘feature’, ‘features’, ‘extract’, ‘compare’, ‘compares’, ‘show’, ‘shows’, ‘sign’, ‘signs’, ‘dose’, ‘do’, ‘breack’, ‘breacks’, ‘perceive’, ‘perceives’, ‘potential’, ‘mg/kg’, ‘initial’, ‘print’, ‘cool’, ‘breast’, ‘studies’, ‘study’, ‘use’, ‘uses’, ‘ment’, ‘used’, ‘useful’, ‘integrat’, ‘plan’, ‘structur’, ‘detect’, ‘quantiti’, ‘technology’, ‘industri’, ‘decision’, ‘tradit’, ‘reliabl’, ‘ent’, ‘evaluation’]

[2.]

The stemming dictionary used in the code: Link to snowball tartarus algorithmsLink to the homepage

[3.]

The results report the frequency (expressed in % terms), of the keywords derived from the quantitative analysis of the corpus of the main topics.

Keywords&Frequency (K) keywords and relative frequency (%) in the main topics.

Topics: Topic 0: Technology and methods for cost data; Topic 1: Cost estimation data management and methods; Topic 2: Project cost data processes, methods and management; Topic 3: Energy design and use costs management; Topic 4: Cost data ontology.

Abanda
,
F.H.
,
Kamsu-Foguem
,
B.
and
Tah
,
J.
(
2015
), “
Towards an intelligent ontology construction cost estimation system: using BIM and new rules of measurement techniques
”,
World Academy of Science, Engineering and Technology, International Journal of Computer, Electrical, Automation, Control and Information Engineering
.
Abanda
,
F.H.
,
Kamsu-Foguem
,
B.
and
Tah
,
J.H.M.
(
2017
), “
BIM – new rules of measurement ontology for construction cost estimation
”,
Engineering Science and Technology, an International Journal
, Vol.
20
No.
2
, pp.
443
-
459
, doi: .
Abanda
,
F.H.
,
Nkeng
,
G.E.
,
Tah
,
J.H.M.
,
Ohandja
,
E.N.F.
and
Manjia
,
M.B.
(
2014
), “
Embodied energy and CO analyses of mud-brick and cement-block houses
”,
AIMS Energy
, Vol.
2
No.
1
, pp.
18
-
40
.
Abanda
,
F.H.
,
Manjia
,
M.B.
,
Nkeng
,
G.E.
,
Pettang
,
C.
and
Tah
,
J.H.M.
(
2016
), “
Building information modelling in Cameroon: Overcoming existing challenges
”,
Civil and Environmental Engineering: Concepts, Methodologies, Tools, and Applications
, Vol.
1
, pp.
145
-
172
.
Abdel-Hamid
,
M.
and
Abdelhaleem
,
H.M.
(
2023
), “
Project cost control using five dimensions building information modelling
”,
International Journal of Construction Management
, Vol.
23
No.
3
, pp.
405
-
409
, doi: .
Agostinelli
,
S.
,
Cinquepalmi
,
F.
and
Ruperto
,
F.
(
2019
), “
5D BIM: tools and methods for digital project construction management
”,
WIT Transactions on the Built Environment
, Vol.
192
, pp.
205
-
215
, doi: .
Ahn
,
K.U.
,
Kim
,
Y.J.
,
Park
,
C.S.
,
Kim
,
I.
and
Lee
,
K.
(
2014
), “
BIM interface for full vs. semi-automated building energy simulation
”,
Energy and Buildings
, Vol.
68
No.
PART B
, pp.
671
-
678
, doi: .
Aibinu
,
A.
and
Venkatesh
,
S.
(
2014
), “
Status of BIM adoption and the BIM experience of cost consultants in Australia
”,
Journal of Professional Issues in Engineering Education and Practice
, Vol.
140
No.
3
.
Akanbi
,
T.
and
Zhang
,
J.
(
2017
), “
Automated wood construction cost estimation
”,
Congress on Computing in Civil Engineering, Proceedings
, pp.
141
-
148
, doi: .
Akanbi
,
T.
and
Zhang
,
J.
(
2020
), “
Automated design information extraction from construction specifications to support wood construction cost estimation
”,
Construction Research Congress 2020: Project Management and Controls, Materials, and Contracts – Selected Papers from the Construction Research Congress 2020
, pp.
658
-
666
, doi: .
Akanbi
,
T.
,
Zhang
,
J.
, and
Lee
,
Y.C.
(
2019
), “
Automated item matching and pricing (IMP) for wood building elements to support BIM-Based wood construction cost estimation
”,
Computing in Civil Engineering 2019: Visualization, Information Modeling, and Simulation – Selected Papers from the ASCE International Conference on Computing in Civil Engineering 2019
, pp.
402
-
409
, doi: .
Alsamarraie
,
M.M.
and
Ghazali
,
F.
(
2023
), “
Cost-benefit analysis of using BIM compared to traditional methods in Iraq’s public construction projects
”,
ASEAN Engineering Journal
, Vol.
13
No.
2
, pp.
107
-
114
, doi: .
Alzraiee
,
H.
(
2022
), “
Cost estimate system using structured query language in BIM
”,
International Journal of Construction Management
, Vol.
22
No.
14
, pp.
2731
-
2743
, doi: .
Autodesk
(
2023
), “
Autodesk Revit software
”,
available at:
Link to Autodesk Revit softwareLink to the cited article (
accessed
27 October 2023).
Azhar
,
S.
(
2011
), “
Building information modeling (BIM): trends, benefits, risks, and challenges for the AEC industry
”,
Leadership and Management in Engineering
, Vol.
11
No.
3
, pp.
241
-
252
.
Banihashemi
,
S.
,
Khalili
,
S.
,
Sheikhkhoshkar
,
M.
and
Fazeli
,
A.
(
2022
), “
Machine learning-integrated 5D BIM informatics: building materials costs data classification and prototype development
”,
Innovative Infrastructure Solutions
, Vol.
7
No.
3
, doi: .
Barlish
,
K.
and
Sullivan
,
K.
(
2012
), “
How to measure the benefits of BIM – A case study approach
”,
Automation in Construction
, Vol.
24
, pp.
149
-
159
, doi: .
Beetz
,
J.
,
Van Leeuwen
,
J.
and
Vries
,
B.D.
(
2009
), “
IfcOWL: a case of transforming EXPRESS schemas into ontologies
”,
Artificial Intelligence for Engineering Design, Analysis and Manufacturing
, Vol.
23
No.
1
, pp.
89
-
101
.
Bender
,
S.
and
Stoy
,
C.
(
2021
), “
Process gaps of Model-Based construction cost estimation from selected constellation of actors
”,
ERES
, available at: Link to Process gaps of Model-Based construction cost estimation from selected constellation of actorsLink to the cited article (
accessed
26 October 2023).
Biolek
,
V.
,
Hanak
,
T.
and
Hanak
,
M.
(
2019
), “
Proposed interconnecting database for BIM models and construction-economic systems in the Czech Republic
”,
IOP Conference Series: Materials Science and Engineering
, Vol.
471
No.
11
, doi: .
Bird
,
S.
,
Klein
,
E.
and
Loper
,
E.
(
2008
), “
Natural language processing in python
”, p.
479,
doi: .
Biswas
,
H.K.
,
Sim
,
T.Y.
and
Lau
,
S.L.
(
2024
), “
Impact of building information modelling and advanced technologies in the AEC industry: a contemporary review and future directions
”,
Journal of Building Engineering
, Vol.
82
, p.
108165
, doi: .
Blei
,
D.
,
Ng
,
A.
and
Jordan
,
M.I.
(
2001
), “
Latent dirichlet allocation
”,
Journal of Machine Learning Research
, Vol.
1
No.
2
, doi: .
Bryde
,
D.
,
Broquetas
,
M.
and
Volm
,
J.M.
(
2013
), “
The project benefits of building information modelling (BIM)
”,
International Journal of Project Management
, Vol.
31
No.
7
, pp.
971
-
980
.
Cezar
,
J.A.
,
Kamarazaly
,
M.A.
,
King
,
L.S.
and
Mbachu
,
J.
(
2023
), “
Benefits of the potential implementation of augmented reality to the construction profession
”,
Malaysian Construction Research Journal
, Vol.
18
No.
1
, pp.
220
-
234
.
Chahrour
,
R.
, et al (
2021
), “
Cost-benefit analysis of BIM-enabled design clash detection and resolution
”,
Construction Management and Economics
, Vol.
39
No.
1
, pp.
55
-
72
, doi: .
Charef
,
R.
,
Alaka
,
H.
and
Emmitt
,
S.
(
2018
), “
Beyond the third dimension of BIM: a systematic review of literature and assessment of professional views
”,
Journal of Building Engineering
, Vol.
19
, pp.
242
-
257
, doi: .
Chen
,
P.
,
Shi
,
C.
and
Ren
,
X.
(
2021
), “
A whole process cost control strategy of construction engineering based on BIM
”,
Proceedings – 2021 6th International Conference on Smart Grid and Electrical Automation, ICSGEA 2021
, pp.
555
-
559
, doi: .
Chen
,
S.
, et al (
2023
), “
Potential features of building information modelling for application of project management knowledge areas as advances modeling tools
”,
Advances in Engineering Software
, Vol.
176
, p.
103372
, doi: .
Cheng
,
Y.M.
and
Wu
,
I.C.
(
2013
), “
Parametric BIM objects exchange and sharing between heterogeneous BIM systems
”,
ISARC 2013 - 30th International Symposium on Automation and Robotics in Construction and Mining, Held in Conjunction with the 23rd World Mining Congress
, pp.
329
-
336
, doi: .
Choi
,
J.
and
Lee
,
S.
(
2023
), “
A suggestion of the alternatives evaluation method through IFC-Based building energy performance analysis
”,
Sustainability
, Vol.
15
No.
3
, p.
1797
, doi: .
Choi
,
J.
,
Kim
,
H.
and
Kim
,
I.
(
2015
), “
Open BIM-based quantity take-off system for schematic estimation of building frame in early design stage
”,
Journal of Computational Design and Engineering
, Vol.
2
No.
1
, pp.
16
-
25
, doi: .
Clarivate
(
2023
), “
Web of science platform
”, available at: Link to Web of science platformLink to the cited article (
accessed
29 October 2023).
Clark
,
M.T.
(
2019
), “
A framework for BIM model-based construction cost estimation
”.
Creswell
,
J.W.
and
Creswell
,
J.D.
(
2017
),
Research Design: qualitative, Quantitative, and Mixed Methods Approaches
, (5 ed.)
SAGE publications
,
Los Angeles
.
Deerwester
,
S.
,
Dumais
,
S.T.
,
Furnas
,
G.W.
,
Landauer
,
T.K.
and
Harshman
,
R.
(
1990
), “
Indexing by latent semantic analysis
”, doi: .
Eastman
,
C.
,
Teicholz
,
P.
,
Sacks
,
R.
and
Liston
,
K.
(
2011
),
BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors
,
John Wiley and Sons, Inc
,
NJ
.
Elghaish
,
F.
,
Abrishami
,
S.
,
Hosseini
,
M.R.
and
Abu-Samra
,
S.
(
2020
), “
Revolutionising cost structure for integrated project delivery: a BIM-based solution
”,
Engineering, Construction and Architectural Management
, Vol.
28
No.
4
, pp.
1214
-
1240
.
ElQasaby
,
A.R.
,
Alqahtani
,
F.K.
and
Alheyf
,
M.
(
2023
), “
Automated schedule and cost control using 3D sensing technologies
”,
Applied Sciences (Switzerland)
, Vol.
13
No.
2
, doi: .
Exactal
(
2023
), “
iTWO costX - BIM and 2D construction estimating software
”,
available at:
Link to iTWO costX - BIM and 2D construction estimating softwareLink to the cited article (
accessed
27 October 2023).
Fazeli
,
A.
,
Dashti
,
M.S.
,
Jalaei
,
F.
and
Khanzadi
,
M.
(
2021
), “
An integrated BIM-based approach for cost estimation in construction projects
”,
Engineering, Construction and Architectural Management
, Vol.
28
No.
9
, pp.
2828
-
2854
, doi: .
Fenz
,
S.
,
Bergmayr
,
J.
,
Plattner
,
N.
,
Chávez-Feria
,
S.
,
Poveda-Villalón
,
M.
and
Giannakis
,
G.
(
2021
), “
Integration of building material databases for IFC-based building performance analysis
”,
Proceedings of the 38th International Symposium on Automation and Robotics in Construction (ISARC)
, Vol.
2021-November
, pp.
182
-
189,
doi: .
Forgues
,
D.
,
Iordanova
,
I.
,
Valdivesio
,
F.
and
Staub-French
,
S.
(
2012
), “
Rethinking the cost estimating process through 5D BIM: a case study
”,
Construction Research Congress 2012: Construction Challenges in a Flat World, Proceedings of the 2012 Construction Research Congress
, pp.
778
-
786
, doi: .
Fürstenberg
,
D.
,
Hjelseth
,
E.
,
Laedre
,
O.
and
Wikström
,
L.
(
2021
), “
Enabling automation of BIM-based cost estimation by semantic web technology
”,
Conference CIB W782021
.
Gohil
,
P.P.
,
Malek
,
M.
,
Bachwani
,
D.
,
Patel
,
D.
,
Upadhyaya
,
D.
and
Hathiwala
,
A.
(
2022
), “
Application of 5D building information modeling for construction management
”,
ECS Transactions
, Vol.
107
No.
1
, pp.
2637
-
2649
, doi: .
Gökçe
,
K.U.
,
Gökçe
,
H.U.
and
Katranuschkov
,
P.
(
2013
), “
IFC-Based product catalog formalization for software interoperability in the construction management domain
”,
Journal of Computing in Civil Engineering
, Vol.
27
No.
1
, pp.
36
-
50
, doi: .
Grilo
,
A.
and
Jardim-Goncalves
,
R.
(
2010
), “
Value proposition on interoperability of BIM and collaborative working environments
”,
Automation in Construction
, Vol.
19
No.
5
, pp.
522
-
530
.
Guo
,
D.
,
Onstein
,
E.
and
La Rosa
,
A.D.
(
2020
), “
An approach of automatic Sparql generation for BIM data extraction
”,
Applied Sciences (Switzerland)
, Vol.
10
No.
24
, pp.
1
-
17
, doi: .
Haider
,
U.
,
Khan
,
U.
,
Nazir
,
A.
and
Humayon
,
M.
(
2020
), “
Cost comparison of a building project by manual and BIM
”,
Civil Engineering Journal
, Vol.
6
No.
1
, pp.
34
-
49
, doi: .
Han
,
P.A.
,
Francis Siu
,
M.F.
,
Abourizk
,
S.
,
Hu
,
D.
and
Hermann
,
U.
(
2017
), “
3D model-based quantity take-off for construction estimates
”,
Congress on Computing in Civil Engineering, Proceedings
, pp.
118
-
124
, doi: .
Harrison
,
C.
and
Thurnell
,
D.
(
2015
), “
BIM implementation in a New Zealand consulting quantity surveying practice
”,
International Journal of Construction Supply Chain Management
, Vol.
5
No.
1
, pp.
1
-
15
, doi: .
Herdyana
,
H.
and
Suroso
,
A.
(
2023
), “
The impacts of 5D-Building information modeling on construction’s time and cost performance
”,
Sinergi (Indonesia)
, Vol.
27
No.
3
, pp.
393
-
404
, doi: .
Hofmann
,
T.
(
1999
),“
Probabilistic latent semantic indexing
”,
Proceedings of the 22nd Annual International ACM SIGIR Conference on Research and Development in Information Retrieval, SIGIR 1999
, pp.
50
-
57
, doi: .
Hotho
,
A.
,
Nürnberger
,
A.
and
Paaß
,
G.
(
2005
), “
A brief survey of text mining
”,
Journal for Language Technology and Computational Linguistics
, Vol.
20
No.
1
, pp.
19
-
62
, doi: .
Hui
,
S.
,
Jing
,
K.T.
,
Yee
,
H.C.
,
Siyao
,
C.
,
Zihao
,
D.
and
Yangle
,
S.
(
2023
), “
The impacts of 5D building information modelling towards cost management in the construction industry
”,
Journal of Advanced Research in Applied Sciences and Engineering Technology
, Vol.
32
No.
3
, pp.
471
-
487
, doi: .
Innovaya
(
2023
), “
Innovaya home page
”,
available at:
Link to Innovaya home pageLink to the cited article (
accessed
27 October 2023).
International Organization for Standardization (ISO)
(
2018
), “
ISO 16739-1:2018 - Industry foundation classes (IFC) for data sharing in the construction and facility management industries – part 1: Data schema
”, available at: Link to ISO 16739-1:2018 - Industry foundation classes (IFC) for data sharing in the construction and facility management industries — part 1: Data schemaLink to the cited article (
accessed
28 June 2022).
International Organization for Standardization (ISO)
(
2023
), “
ISO 19650-1:2018 – Organization and digitization of information about buildings and civil engineering works, including building information modelling (BIM) – information management using building information modelling – part 1: Concepts and principles
”, available at: Link to ISO 19650-1:2018 - Organization and digitization of information about buildings and civil engineering works, including building information modelling (BIM) — information management using building information modelling — part 1: Concepts and principlesLink to the cited article (
accessed
29 October 2023).
Inzerillo
,
L.
,
Acuto
,
F.
,
Pisciotta
,
A.
,
Mantalovas
,
K.
and
Di Mino
,
G.
(
2024
), “
Exploring 4d and 5d analysis in BIM environment for infrastructures: a case study
”,
The International Archives of the Photogrammetry, Remote Sensing and Spatial Information Sciences
, Vol.
XLVIII-2/W4-2024
No.
2
, pp.
233
-
240
, doi: .
Isatto
,
E.L.
(
2021
),“An IFC representation for process-based cost modeling”,
Lecture Notes in Civil Engineering
, Vol.
98
, pp.
519
-
528
, doi: .
Jafary
,
P.
,
Shojaei
,
D.
,
Rajabifard
,
A.
and
Ngo
,
T.
(
2024
), “
BIM and real estate valuation: challenges, potentials and lessons for future directions
”,
Engineering, Construction and Architectural Management
, Vol.
31
No.
4
, pp.
1642
-
1677
, doi: .
Jia
,
J.
,
Gao
,
J.
,
Wang
,
W.
,
Ma
,
L.
,
Li
,
J.
and
Zhang
,
Z.
(
2022
), “
An automatic generation method of finite element model based on BIM and ontology
”,
Buildings
, Vol.
12
No.
11
, doi: .
Jin
,
R.
,
Hancock
,
C.M.
,
Tang
,
L.
and
Wanatowski
,
D.
(
2017
), “
BIM investment, returns, and risks in China’s AEC industries
”,
Journal of Construction Engineering and Management
, Vol.
143
No.
12
, doi: .
Keerthana
,
D.R.
and
Gunarani
,
G.I.
(
2019
), “
BIM aided real time progress management model for construction
”,
International Journal of Innovative Technology and Exploring Engineering
, Vol.
8
No.
7
, pp.
734
-
738
.
Khaleel
,
A.M.
and
Naimi
,
S.
(
2022
), “
Automation of cost control process in construction project building information modeling (BIM)
”,
Periodicals of Engineering and Natural Sciences (PEN)
, Vol.
10
No.
6
, doi: .
Khosakitchalert
,
C.
,
Yabuki
,
N.
and
Fukuda
,
T.
(
2018
), “
The accuracy enhancement of architectural walls quantity takeoff for schematic BIM models
”,
ISARC 2018 - 35th International Symposium on Automation and Robotics in Construction and International AEC/FM Hackathon: The Future of Building Things
, doi: .
Lawrence
,
M.
,
Pottinger
,
R.
,
Staub-French
,
S.
and
Nepal
,
M.P.
(
2014
), “
Creating flexible mappings between building information models and cost information
”,
Automation in Construction
, Vol.
45
, pp.
107
-
118
, doi: .
Le
,
H.T.T.
,
Likhitruangsilp
,
V.
and
Yabuki
,
N.
(
2021
), “
A BIM-database-integrated system for construction cost estimation
”,
ASEAN Engineering Journal
, Vol.
11
No.
1
, pp.
45
-
59
, doi: .
Lee
,
M.
,
Chai
,
C.
,
Xiong
,
Y.
and
Gui
,
H.
(
2022
), “
Technology acceptance model for building information modelling based virtual reality (BIM-VR) in cost estimation
”,
Journal of Information Technology in Construction
, Vol.
27
, pp.
914
-
925
, doi: .
Lee
,
S.K.
,
Kim
,
K.R.
and
Yu
,
J.H.
(
2014
), “
BIM and ontology-based approach for building cost estimation
”,
Automation in Construction
, Vol.
41
, pp.
96
-
105
, doi: .
Lee
,
S.
,
Kim
,
K.
and
Yu
,
J.
(
2015
), “
Ontological inference of work item based on BIM data
”,
KSCE Journal of Civil Engineering
, Vol.
19
No.
3
, pp.
538
-
549
, doi: .
Leicht
,
D.
,
Castro-Fresno
,
D.
,
Dìaz
,
J.
and
Baier
,
C.
(
2020
), “
Multidimensional construction planning and agile organized project execution-The 5D-PROMPT method
”,
Sustainability
, Vol.
12
No.
16
, doi: .
Liu
,
H.
,
Cheng
,
J.C.P.
and
Gan
,
V.J.L.
(
2021
), “
Developing a knowledge-based system for semantic enrichment and automatic BIM-based quantity take-off
”,
Proceedings of the International Symposium on Automation and Robotics in Construction
, Vol.
2021-November
, pp.
169
-
175
, doi: .
Liu
,
H.
,
Lu
,
M.
and
Al-Hussein
,
M.
(
2014
), “
BIM-based integrated framework for detailed cost estimation and schedule planning of construction projects
”,
31st International Symposium on Automation and Robotics in Construction and Mining, ISARC 2014 - Proceedings
, pp.
286
-
294
, doi: .
Liu
,
H.
,
Lu
,
M.
and
Al-Hussein
,
M.
(
2016
), “
Ontology-based semantic approach for construction-oriented quantity take-off from BIM models in the light-frame building industry
”,
Advanced Engineering Informatics
, Vol.
30
No.
2
, pp.
190
-
207
.
Lu
,
Q.
,
Won
,
J.
and
Cheng
,
J.C.P.
(
2016
), “
A financial decision making framework for construction projects based on 5D building information modeling (BIM)
”,
International Journal of Project Management
, Vol.
34
No.
1
, pp.
3
-
21
, doi: .
Ma
,
Z.
and
Liu
,
Z.
(
2014
), “
BIM-based intelligent acquisition of construction information for cost estimation of building projects
”,
Procedia Engineering
, Vol.
85
, pp.
358
-
367
, doi: .
Ma
,
Z.
,
Liu
,
Z.
and
Wei
,
Z.
(
2016
), “
Formalized representation of specifications for construction cost estimation by using ontology
”,
Computer-Aided Civil and Infrastructure Engineering
, Vol.
31
No.
1
, pp.
4
-
17
, doi: .
Ma
,
Z.
,
Wei
,
Z.
and
Zhang
,
X.
(
2013
), “
Semi-automatic and specification-compliant cost estimation for tendering of building projects based on IFC data of design model
”,
Automation in Construction
, Vol.
30
, pp.
126
-
135
, doi: .
Marzouk
,
M.
,
Azab
,
S.
and
Metawie
,
M.
(
2018
), “
BIM-based approach for optimizing life cycle costs of sustainable buildings
”,
Journal of Cleaner Production
, Vol.
188
, pp.
217
-
226
.
Matejka
,
P.
and
Vitasek
,
S.
(
2018
), “
Comparison of different cost estimation methods with use of building information modelling (BIM)
”,
Engineering for Rural Development
, Vol.
17
, pp.
843-849
, doi: .
Mesároš
,
P.
,
Smetanková
,
J.
and
Mandičák
,
T.
(
2019
), “
The fifth dimension of BIM - Implementation survey
”,
IOP Conference Series: Earth and Environmental Science
, Vol.
222
No.
1
, doi: .
Moses
,
T.
,
Heesom
,
D.
and
Oloke
,
D.
(
2020
), “
Implementing 5D BIM on construction projects: contractor perspectives from the UK construction sector
”,
Journal of Engineering, Design and Technology
, Vol.
18
No.
6
, pp.
1867
-
1888
.
Moshtaghian
,
F.
and
Noorzai
,
E.
(
2023
), “
Integration of risk management within the building information modeling (BIM) framework
”,
Engineering, Construction and Architectural Management
, Vol.
30
No.
5
, pp.
1951
-
1977
, doi: .
Nabavi
,
A.
,
Ramaji
,
I.
,
Sadeghi
,
N.
and
Anderson
,
A.
(
2023
), “
Leveraging natural language processing for automated information inquiry from building information models
”,
Journal of Information Technology in Construction
, Vol.
28
, pp.
266
-
285
, doi: .
Narlawar
,
G.S.
,
Chaphalkar
,
N.B.
and
Sandbhor
,
S.
(
2019
), “
Time and resource management of residential apartment construction using building information modeling
”,
International Journal of Innovative Technology and Exploring Engineering
, Vol.
8
No.
10
, pp.
4238
-
4246
, doi: .
Nsimbe
,
A.
and
Di
,
J.
(
2024
), “
The impact of building information modeling technology on cost management of civil engineering projects: a case study of the Mombasa port area development project
”,
Buildings
, Vol.
14
No.
4
, p.
1175
, doi: .
O’Brien
,
W.
(
2000
), “
Towards 5D CAD — dynamic cost and resource planning for specialist contractors
”,
Proceedings of Construction Congress VI: Building Together for a Better Tomorrow in an Increasingly Complex World
, Vol.
278
, pp.
1023
-
1028
, doi: .
Olatunji
,
O.
,
Sher
,
W.
and
Ogunsemi
,
D.
(
2010
), “
The impact of building information modelling on construction cost estimation
”,
Engineering
.
Papadonikolaki
,
E.
and
Aibinu
,
A.
(
2017
), “
The influence of leadership, resources and organisational structure on BIM adoption
”,
(ARCOM Working Papers 2017). Association of Researchers in Construction Management (ARCOM): Cambridge, UK. (2017)
,
available at:
Link to The influence of leadership, resources and organisational structure on BIM adoptionLink to a pdf of the cited article (
accessed
26 October 2023).
Pasquire
,
C.
,
Pennanen
,
A.
,
Ballard
,
G.
and
Haahtela
,
Y.
(
2011
), “
Target costing and designing to targets in construction
”,
Journal of Financial Management of Property and Construction
, Vol.
16
No.
1
, pp.
52
-
63
.
Pauwels
,
P.
and
Terkaj
,
W.
(
2016
), “
EXPRESS to OWL for construction industry: towards a recommendable and usable ifcOWL ontology
”,
Automation in Construction
, Vol.
63
, pp.
100
-
133
.
Pavan
,
A.
,
Giani
,
M.
and
Mirarchi
,
C.
(
2017
), “
BIM: metodi e strumenti : progettare, costruire e gestire nell’era digitale
”,
Tecniche nuove
,
available at:
Link to BIM: metodi e strumenti : progettare, costruire e gestire nell’era digitaleLink to the cited article (
accessed
14 March 2023).
Popov
,
V.
,
Juocevicius
,
V.
,
Migilinskas
,
D.
,
Ustinovichius
,
L.
and
Mikalauskas
,
S.
(
2010
), “
The use of a virtual building design and construction model for developing an effective project concept in 5D environment
”,
Automation in Construction
, Vol.
19
No.
3
, pp.
357
-
367
, doi: .
Porsani
,
G.B.
,
de Lersundi
,
K.D.V.
,
Gutiérrez
,
A.S.O.
and
Bandera
,
C.F.
(
2021
), “
Interoperability between building information modelling (BIM) and building energy model (BEM)
”,
Applied Sciences (Switzerland)
, Vol.
11
No.
5
, pp.
1
-
20
, doi: .
Project Jupyter
(
2023
), “
JupyterLab 1.0: Jupyter’s Next-Generation notebook interface
”, available at: Link to JupyterLab 1.0: Jupyter’s Next-Generation notebook interfaceLink to the cited article (
accessed
21 October 2023).
Pučko
,
Z.
,
Maučec
,
D.
and
Šuman
,
N.
(
2020
), “
Energy and cost analysis of building envelope components using BIM: a systematic approach
”,
Energies (Basel)
, Vol.
13
No.
10
, doi: .
Rafati Sokhangoo
,
L.
,
Orenga Panizza
,
R.
,
Nik-Bakht
,
M.
and
Han
,
S.H.
(
2019
), “
Conceptual cost models for energy simulation in building projects
”,
Proceedings, Annual Conference - Canadian Society for Civil Engineering
, Vol.
2019
, p.
2019
.
Ramaji
,
I.J.
and
Memari
,
A.M.
(
2015
), “
Information exchange standardization for BIM application to multi-story modular residential buildings
”,
AEI 2015: Birth and Life of the Integrated Building - Proceedings of the AEI Conference 2015
, pp.
13
-
24
, doi: .
Ramaji
,
I.J.
,
Richardson
,
N.
,
Mostavi
,
E.
and
Kermanshachi
,
S.
(
2018
), “
Investigation of leveraging BIM information exchange standards for conducting LOD-based cost estimating
”,
Construction Research Congress 2018: Construction Information Technology - Selected Papers from the Construction Research Congress 2018
, Vol.
2018-April
, pp.
480
-
490
, doi: .
Rehurek
,
R.
and
Sojka
,
P.
(
2010
), “
Software framework for topic modelling with large corpora
”,
Proceedings of the LREC 2010 Workshop on New Challenges for NLP
, doi: .
Ren
,
R.
,
Zhang
,
J.
,
Chen
,
Y.
and
Dib
,
H.N.
(
2022
), “
A BIM information processing framework to facilitate enriched BIM applications
”,
Construction Research Congress 2022: Computer Applications, Automation, and Data Analytics - Selected Papers from Construction Research Congress 2022
, vol.
2-B
, pp.
1135
-
1144
, doi: .
Ren
,
G.
,
Li
,
H.
,
Liu
,
S.
,
Goonetillake
,
J.
,
Khudhair
,
A.
and
Arthur
,
S.
(
2021
), “
Aligning BIM and ontology for information retrieve and reasoning in value for money assessment
”,
Automation in Construction
, Vol.
124
, p.
103565
, doi: .
Röder
,
M.
,
Both
,
A.
and
Hinneburg
,
A.
(
2015
), “
Exploring the space of topic coherence measures
”,
WSDM 2015 - Proceedings of the 8th ACM International Conference on Web Search and Data Mining
, pp.
399
-
408
, doi: .
Rouhanizadeh
,
B.
,
Kermanshachi
,
S.
,
Ramaji
,
I.J.
and
Shakerian
,
S.
(
2021
), “
Development of an automated tool for cost estimation of transportation projects
”,
International Conference on Transportation and Development 2021: Transportation Planning and Development - Selected Papers from the International Conference on Transportation and Development 2021
, pp.
178
-
190
, doi: .
Ruano-Ruiz
,
R.
,
Nieto-Julián
,
J.E.
and
Moyano
,
J.
(
2022
), “
Ifc data mapping based on a parametric BIM coding for an efficient workflow in the quantification and management of construction costs
”,
International Archives of the Photogrammetry, Remote Sensing and Spatial Information Sciences - ISPRS Archives
, Vol.
46
No.
5/W1-2022
, pp.
199
-
204
, doi: .
Sacks
,
R.
,
Eastman
,
C.
,
Lee
,
G.
and
Teicholz
,
P.
(
2018
),
BIM Handbook
, (3rd ed.)
John Wiley and Sons, Inc
.
Salton
,
G.
and
McGill
,
M.J.
(
1986
),
Introduction to Modern Information Retrieval
,
McGraw-Hill, Inc
.
Samphaongoen
,
P.
(
2010
), “
A visual approach to construction cost estimating
”.
Santos
,
R.
,
Costa
,
A.A.
and
Grilo
,
A.
(
2017
), “
Bibliometric analysis and review of building information modelling literature published between 2005 and 2015
”,
Automation in Construction
, Vol.
80
, pp.
118
-
136
, doi: .
Sattineni
,
A.
and
Macdonald
,
J.A.
(
2014
), “
5D-BIM: a case study of an implementation strategy in the construction industry
”,
31st International Symposium on Automation and Robotics in Construction and Mining, ISARC 2014 - Proceedings
,
University of Technology Sydney
, pp.
361
-
367
.
Scopus
(
2023
), “
Content – How Scopus Works – Scopus – | Elsevier solutions
”,
available at:
Link to Content - How Scopus Works - Scopus - | Elsevier solutionsLink to the cited article (accessed 21 October 2023).
Sepasgozar
,
S.M.E.
,
Costin
,
A.M.
,
Karimi
,
R.
,
Shirowzhan
,
S.
,
Abbasian
,
E.
and
Li
,
J.
(
2022
), “
BIM and digital tools for state-of-the-art construction cost management
”,
Buildings
, Vol.
12
No.
4
, doi: .
Shahinmoghadam
,
M.
,
Kahou
,
S.E.
and
Motamedi
,
A.
(
2024
), “
Neural semantic tagging for natural language-based search in building information models: Implications for practice
”,
Computers in Industry
, Vol.
155
, pp.
104063
, doi: .
Shen
,
Z.
and
Issa
,
R.R.A.
(
2010
), “
Quantitative evaluation of the BIM-assisted construction detailed cost estimates
”,
Electronic Journal of Information Technology in Construction
, Vol.
15
, pp.
234
-
257
.
Sherafat
,
B.
,
Taghaddos
,
H.
and
Shafaghat
,
E.
(
2022
), “
Enhanced automated quantity Take-Off in building information modeling enhanced automated quantity take-off in building information modeling
”.
Scientia Iranica
, Vol.
29
No.
3
, pp.
1024
-
1037
, doi: .
Silva
,
G.A.S.K.
and
Warnakulasooriya
,
B.N.F.
(
2017
), “
Criteria for construction project success: a literature review
”,
SSRN Electronic Journal
, doi: .
Smetanková
,
J.
,
Behúnová
,
A.
,
Mandičák
,
T.
and
Mesároš
,
P.
(
2018
), “
5D of BIM – research studies at home and selected countries around the world
”,
Acta Tecnología
, Vol.
4
No.
3
, pp.
39
-
43
, doi: .
Smith
,
P.
(
2014
), “
BIM and the 5D project cost manager
”,
Procedia - Social and Behavioral Sciences
, Vol.
119
, pp.
475
-
484
, doi: .
Stanley
,
R.
and
Thurnell
,
D.
(
2014
), “
The benefits of, and barriers to, implementation of 5D BIM for quantity surveying in New Zealand
”,
Construction Economics and Building
, Vol.
14
No.
1
, pp.
105
-
117
, doi: .
Stransky
,
M.
and
Dlask
,
P.
(
2018
), “
Process of matching work items between BIM model and cost estimating software
”,
Engineering for Rural Development
, Vol.
17
, pp.
856
-
864
, doi: .
Suarez
,
J.C.
,
Zapata
,
J.
and
Brioso
,
X.
(
2020
), “
Using 5D models and CBA for planning the foundations and concrete structure stages of a complex office building
”,
IGLC 28 - 28th Annual Conference of the International Group for Lean Construction 2020
, pp.
913
-
924
, doi: .
Tan
,
T.
,
Chen
,
K.
,
Xue
,
F.
and
Lu
,
W.
(
2019
), “
Barriers to building information modeling (BIM) implementation in China’s prefabricated construction: an interpretive structural modeling (ISM) approach
”,
Journal of Cleaner Production
, Vol.
219
, pp.
949
-
959
, doi: .
Terkaj
,
W.
and
Šojić
,
A.
(
2015
), “
Ontology-based representation of IFC EXPRESS rules: an enhancement of the ifcOWL ontology
”,
Automation in Construction
, Vol.
57
, pp.
188
-
201
.
Toan
,
N.Q.
,
Anh
,
P.X.
and
Van Tam
,
N.
(
2023
), “Trends in BIM tools adoption in construction project implementation: a case study in Vietnam”, ”
Lecture Notes in Civil Engineering
, Vol.
282
, pp.
9
-
19
, doi: .
Trimble
(
2023
), “
Vico office introduction
”,
available at:
Link to Vico office introductionLink to the cited article (
accessed
27 October 2023).
Turkyilmaz
,
E.
(
2013
), “
A proposal for energy efficient design: an IFC based design decision system and its application
”,
WIT Transactions on Ecology and the Environment
, Vol.
179
1
, pp.
663
-
670
, doi: .
Vakaj
,
E.
,
Cheung
,
F.
,
Tawil
,
A.-R.H.
,
Patlakas
,
P.
and
Alyania
,
K.
(
2020
), “
ifcOWL-DfMA a new ontology for the offsite construction domain
”,
LDAC
.
Valinejadshoubi
,
M.
,
Moselhi
,
O.
,
Iordanova
,
I.
,
Valdivieso
,
F.
and
Bagchi
,
A.
(
2024
), “
Automated system for high-accuracy quantity takeoff using BIM
”,
Automation in Construction
, Vol.
157
, p.
105155
, doi: .
Vigneault
,
M.A.
,
Boton
,
C.
,
Chong
,
H.Y.
and
Cooper-Cooke
,
B.
(
2020
), “
An innovative framework of 5D BIM solutions for construction cost management: a systematic review
”,
Archives of Computational Methods in Engineering
, Vol.
27
No.
4
, pp.
1013
-
1030
, doi: .
Wahab
,
A.
and
Wang
,
J.
(
2022
), “
Factors-driven comparison between BIM-based and traditional 2D quantity takeoff in construction cost estimation
”,
Engineering, Construction and Architectural Management
, Vol.
29
No.
2
, pp.
702
-
715
.
Wan Abdul Basir
,
W.N.F.A.
,
Ujang
,
U.
and
Majid
,
Z.
(
2023
), “
Adaptation 4D and 5D BIM for BIM/GIS data integration in construction project management
”,
IOP Conference Series: Earth and Environmental Science
, Vol.
1274
No.
1
, doi: .
Wang
,
K.C.
and
Tung
,
S.H.
(
2023
), “
Cost estimation model based on building information modeling and virtual reality for customizing presold homes
”,
KSCE Journal of Civil Engineering
, Vol.
27
No.
4
, pp.
1397
-
1411
, doi: .
Wasim
,
M.
,
Wang
,
K.
,
Yuan
,
Z.
,
Jin
,
M.
,
Abadel
,
A.
and
Nehdi
,
M.L.
(
2023
), “
An optimized energy efficient design of a light gauge steel building
”,
Case Studies in Construction Materials
, Vol.
19
, p.
e02398
, doi: .
Xiao
,
M.
,
Chao
,
Z.
,
Coelho
,
R.F.
and
Tian
,
S.
(
2022
), “
Investigation of classification and anomalies based on machine learning methods applied to large scale building information modeling
”,
Applied Sciences
, Vol.
12
No.
13
, doi: .
Xu
,
S.
,
Liu
,
K.
and
Tang
,
L.C.M.
(
2013
), “
Cost estimation in building information models
”,
ICCREM 2013: Construction and Operation in the Context of Sustainability - Proceedings of the 2013 International Conference on Construction and Real Estate Management
, pp.
555
-
566
, doi: .
Xu
,
S.
,
Liu
,
K.
and
Tang
,
L.C.M.
(
2015a
), “
Applying organizational semiotics for developing Knowledge-Based cost estimation of construction project
”,
IFIP Adv Inf Commun Technol
, Vol.
449
, pp.
80
-
91
, doi: .
Xu
,
S.
,
Liu
,
K.
and
Tang
,
L.C.M.
(
2015b
), “
Incorporation of expert reasoning into the BIM-based cost estimating process
”,
Proceedings of the 31st Annual Association of Researchers in Construction Management Conference, ARCOM 2015, Association of Researchers in Construction Management
, pp.
651
-
660
.
Xu
,
S.
,
Liu
,
K.
,
Tang
,
L.C.M.
and
Li
,
W.
(
2016
), “
A framework for integrating syntax, semantics and pragmatics for computer-aided professional practice: with application of costing in construction industry
”,
Computers in Industry
, Vol.
83
, pp.
28
-
45
, doi: .
Yalcinkaya
,
M.
and
Singh
,
V.
(
2015
), “
Patterns and trends in building information modeling (BIM) research: a latent semantic analysis
”,
Automation in Construction
, Vol.
59
, pp.
68
-
80
, doi: .
Yang
,
S.W.
,
Moon
,
S.W.
,
Jang
,
H.
,
Choo
,
S.
and
Kim
,
S.A.
(
2022
), “
Parametric method and building information modeling-based cost estimation model for construction cost prediction in architectural planning
”,
Applied Sciences
, Vol.
12
No.
19
, p.
9553
, doi: .
Yao
,
Y.
,
Qin
,
H.
and
Wang
,
J.
(
2020
), “
Barriers of 5D BIM implementation in prefabrication construction of buildings
”,
IOP Conference Series: Earth and Environmental Science
, Vol.
580
No.
1
, doi: .
Yin
,
M.
,
Tang
,
L.
,
Webster
,
C.
,
Xu
,
S.
,
Li
,
X.
and
Ying
,
H.
(
2023
), “
An ontology-aided, natural language-based approach for multi-constraint BIM model querying
”,
Journal of Building Engineering
, Vol.
76
, p.
107066
, doi: .
Yoon
,
J.H.
and
Pishdad-Bozorgi
,
P.
(
2022
), “
Potentials of 5D BIM with blockchain-enabled smart contracts for expediting cash flow in construction projects
”,
Proceedings of the International Symposium on Automation and Robotics in Construction
, Vol.
2022-July
, pp.
238
-
245
, .
Zhang
,
X.
,
Azhar
,
S.
,
Nadeem
,
A.
and
Khalfan
,
M.
(
2018
), “
Using building information modelling to achieve lean principles by improving efficiency of work teams
”,
International Journal of Construction Management
, Vol.
18
No.
4
, pp.
293
-
300
, doi: .
Zhao
,
P.A.
and
Wang
,
C.C.
(
2014
), “
A comparison of using traditional cost estimating software and BIM for construction cost control
”,
ICCREM 2014: Smart Construction and Management in the Context of New Technology – Proceedings of the 2014 International Conference on Construction and Real Estate Management
, pp.
256
-
264
, doi: .
Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence maybe seen at Link to the terms of the CC BY 4.0 licenceLink to the terms of the CC BY 4.0 licence.