Skip to Main Content
Skip Nav Destination
Purpose

Projects that pose high risks to the funding or owning organizations, or those that require support, need oversight by senior managers. This is typically conducted through a Project Steering Committee (PSC). PSC members each have individual responsibilities stemming from the permanent and temporary (project) organizations. The PSC needs shared goals and mutual trust to balance those responsibilities. The relationship between PSC members acting according to individual responsibilities, shared goals, mutual trust and project success is unclear. This paper quantitatively tests these relationships and verifies the use of roles for members.

Design/methodology/approach

A conceptual model of the relationship between PSC members acting according to individual responsibilities and project success is tested using a survey with 178 valid responses. Additionally, the survey gathers opinions of PSC members and project managers on PSCs.

Findings

PSC members acting from individual responsibilities positively affect project success regardless of the degree of shared goals and mutual trust. Four representation roles are generally covered: funders, user groups, suppliers and groups that maintain the project’s products.

Originality/value

The study is unique in including PSC members as respondents. PSC members are agents for their stakeholder group and, at the group level, for the funding and owning organization. The study confirms the value of four stakeholder-representation roles for members. It emphasizes the importance of defining clear and distinct individual responsibilities for members, rather than focusing solely on shared goals and mutual trust.

Project success is positively related to project governance, where competent decision-makers influence both (Turner, 2025) and governance is needed to align the project with business objectives (Musawir et al., 2023). Project steering committees (PSCs) are one of the possibilities for the governance of a project (Müller et al., 2015; Wang et al., 2024). A PSC is a group that acts at a strategic level and is responsible for achieving the business case and the progress of the project (Zwikael and Meredith, 2018). This places PSCs in the research field of project governance, which studies the governance of a single project. It has four contemporary research strands (Sankaran et al., 2025). PSCs are in the strand Resilience, as they help deal with multiple stakeholders and viewpoints (Murphy, 2016). Also, the Organizational strand is relevant, as PSCs provide unified direction in case of multiple funders and owners (Miller and Lessard, 2000).

Committees, by definition, consist of several members (Merriam-Webster Incorporated, 2025). One of the members’ potential roles is representing the funder(s), often referred to as the project owner, which is well-studied (e.g. Breese et al., 2020). Less is known about the other roles of members in the PSC and the inner workings of the PSC in general (Lechler and Cohen, 2009; Murphy, 2016).

The PSC is responsible for achieving the business case (Zwikael and Meredith, 2018). Changes in the project environment or in the project itself can influence the business case (Al-Twairesh and Al-Mudimigh, 2011), which the PSC must recognize and act upon (Loch et al., 2017). The PSC’s performance should be evaluated using a broad definition of project success that encompasses the owner’s and investor’s success (Zwikael and Meredith, 2021). This study uses the definition for success by Joslin and Müller (2016, p. 613) as “… the achievement of a particular combination of objective and subjective measures, manifested in the success criteria and measured at the end of a project”. The accountability of a PSC for the business case implies it must have decision-making authority (McGrath and Whitty, 2018; Stewart et al., 2023); therefore, our study does not include advisory boards.

This study is part of a series of consecutive studies on PSCs. A first study qualitatively explored the inner workings of PSCs, highlighting the lack of knowledge about individual roles and responsibilities of members (Stoppels et al., 2023). A second qualitative study therefore defined standard roles (Stoppels et al., 2025). It argued that having shared goals (Franco et al., 2016) and mutual trust (Benoliel and Somech, 2016) in the PSC influences the relationship between PSC members working from individual responsibilities and project success. Members should share a degree of trust in each other and agree on shared goals before acting on individual responsibilities. In practice, the individual responsibilities of a PSC member are primarily derived from their function within the permanent organization (Stoppels et al., 2023). The study presented in this paper takes a quantitative approach. It builds on our previous paper by investigating how members’ individual responsibilities, shared goals and mutual trust contribute to project success. It includes responses from PSC members: a group that does not often participate in such studies.

This study presents insights from theory and empirical data that could aid management practice by clarifying how individual PSC members contribute to project success. Additionally, it deepens the current application of agency theory (Breese et al., 2020) by distinguishing between governance at the group and individual levels. The PSC, as a whole, serves as the project owner. But the members themselves have individual and dual responsibilities: for the project as a whole and for the stakeholder group they represent (Stoppels et al., 2025). So, the PSC is an agent to the funding organization and a principal to the project manager. PSC members are agents to both the funding organization and their own stakeholder group, while also part of the group that is the principal towards the project manager. We also respond to the call of Murphy et al. (2018) to study the inner workings of PSCs.

In the remainder of this paper, we first provide the theoretical background. This leads to a conceptual model linking PSC members acting from individual responsibilities to project success. We then provide the research methodology and analyze the study’s reliability. The results are presented, leading to a discussion on the link between PSC members and project success. Lastly, we present conclusions, including theoretical and practical relevance.

One way to view PSCs is as the linking pin between permanent organizations and temporary projects (Lechler and Cohen, 2009), where stakeholders collaborate (Müller et al., 2015). Senior managers cooperate and form a boundary-spanning team (Murphy, 2016). Both agency theory and stewardship theory support the appointment of a project owner (Breese et al., 2020; Zwikael and Smyrk, 2019). The PSC as a group can have this role of project owner (Crawford, 2023; Crawford et al., 2008). The project owner focuses on project success on behalf of the funder, though should also take the interests of other stakeholders into account (Müller et al., 2017). The PSC members represent affected and contributing stakeholder groups (McGrath and Whitty, 2017; Murphy, 2016), of which the funder is significant but not the only stakeholder (Stoppels et al., 2025).

The PSC consists of senior managers who are primarily selected based on the stakeholders they represent within the permanent organization (Harvey et al., 2025; Murphy, 2016). As a result, members must balance the interests of the project with those of the permanent organizations they represent. Their responsibilities from the permanent function can conflict with the overall interest of the project. For example, ERP implementations (large integrated software systems) lead to process changes that may result in increased workload or complexity for the department a PSC member is responsible for (Allen, 2005).

Our previous studies have shown that members tend to struggle with these dual responsibilities (Stoppels et al., 2023, 2025). This can lead to them either focusing mainly on the interests of their permanent organization or prioritizing project goals and neglecting individual responsibilities derived from the permanent organization (Loch et al., 2017). This raises the question of whether PSCs should explicitly define individual responsibilities and then act accordingly to achieve project success.

A PSC and its members should govern and support the project (Crawford et al., 2008). The governance involves providing direction based on the interests of the funder and other stakeholders. It also involves holding the project manager accountable for performance and conduct (Müller et al., 2016). This means that information must be gathered and transformed to make decisions (Karlsen, 2010; Murphy, 2016). In practice, the project manager attends meetings to report, provides information during discussions and prepares the agenda (Stoppels et al., 2023). The project manager has no decision rights and is not a PSC member (Axelos, 2009). The support duty of PSC members involves them serving as champions (Andersen, 2012). At times, they need to act, such as ensuring compliance with decisions within their own stakeholder group. However, they should be careful not to manage the project team, as this is the project manager’s accountability (Zwikael and Meredith, 2018).

Project success and success criteria are well-researched (Joslin and Müller, 2015). It originated from a narrow definition of the triple constraints (cost, time and scope), later developed to include long-term stakeholder perspectives (Cellerino et al., 2025). Following Cooke-Davies (2002), the PSC is responsible for project success and not just project management success. Therefore, it should encompass the perspectives of stakeholder groups and the project’s long-term outcomes. Khan et al. (2013) define five project success dimensions: project efficiency, organizational benefits, project impact, future potential and stakeholder satisfaction. Project efficiency is generally managed by project management, though the PSC should provide direction and hold the project manager accountable (Stoppels et al., 2023). The individual with the project owner role, often chairing the PSC (McGrath and Whitty, 2020), is primarily responsible for benefits realization (Zwikael et al., 2019). Future potential is relevant to the success of future projects, as part of the responsibility of PSC members within their permanent organizations (Kloppenborg and Tesch, 2015). PSCs should consider the satisfaction of stakeholders, not only morally (OECD, 2016) but also since a stakeholder orientation helps project success (Joslin and Müller, 2016), and the PSC itself is a body where stakeholders collaborate (Lechler and Cohen, 2009).

Earlier work (Stoppels et al., 2025) provides an overview of why clear responsibilities for each member are needed. Firstly, clear responsibility among PSC members helps project success, as it shapes actions that contribute to the goals of the funder and other stakeholders (Müller et al., 2017; Too and Weaver, 2014; Turner, 2020). Zwikael et al. (2019) provide an overview of the responsibilities of the project owner, who is an agent for the funder and should focus on benefits realization both before and after the project’s output is delivered. Breese (2020) adds that the owner should take full ownership of the project’s benefits by separating the project’s oversight role from the permanent function. Secondly, Bechky (2006) describes how role clarity serves as a mechanism for coordination in temporary organizations, enabling each member to know what to do and what others can expect from them. Thirdly, explicit and communicated roles can prevent tensions within the team (DeFillippi and Sydow, 2016).

Standard roles can help determine members’ responsibilities. In earlier work, we proposed five roles for selecting members and as the starting point to determine individual members’ responsibilities and authorities (Stoppels et al., 2025). These roles are Representation of the Funder, Representation of User Groups, Representation of Suppliers of Project Resources, Representation of the Support organization for Project Deliverables and Quality Assurance towards the PSC.

A PSC must ensure alignment with the funding or owning organizations’ goals (Project Management Institute, 2016) and provide unified direction (Axelos, 2009). Besides, “goals affect performance by directing attention and action, mobilizing effort, and motivating individuals” (Clerkin and Jones, 2013). Members should agree on these goals since a previous study (Stoppels et al., 2023) showed that a PSC is more than an advisory board towards the owner and tends towards shared decision-making. Arnesson and Albinsson (2013) found that agreement among PSC members on the project’s goals is needed for success.

Schippers and Rus (2021) studied the influence of shared views among Top Management Team members on the quality of shared decision-making. They stress the importance of a common goal and task clarification via sharing, discussing and integrating information among team members. Loch et al. (2017) mention “goal agreement” as one of the important challenges of a PSC, in which they include the importance of achieving clarity on what the goals imply and where conflicts of interest among members exist.

Therefore, it is expected that members sharing goals help project success. We define “shared” as “to have in common” (Merriam-Webster Incorporated, 2025). This includes members knowing the goals, agreeing upon them and using them for guidance when acting or making decisions. Chow and Chan (2008) examined the influence of social networks, mutual trust and shared goals on employees’ intention to share knowledge in organizations. They found that shared goals positively affect knowledge-sharing intentions.

Joslin and Müller (2016) predicated that governance based on trust helps project success, which is supported by the findings from Zwikael et al. (2015) on trust between the project owner and project manager. Both focus on trust by the governors in Project Management. It can be expected that mutual trust inside the PSC is also important for project success. In ERP implementations, interdepartmental cooperation based on trust and clear goals is a key success factor (Somers and Nelson, 2001). PSC members sometimes struggle with their duties related to project oversight (Loch et al., 2017), so they should feel confident asking their fellow PSC members for help (Stoppels et al., 2025).

Research on management teams indicates that members sharing goals make them want to solve task conflicts (disagreement about the content of the task). This, in turn, leads to quality decision-making (Janssen et al., 1999) and members willing to accept decisions (Simons and Peterson, 2000). Relationship conflict (the perception of personal resentment and incompatibility), on the other hand, should be avoided, as it limits information processing and makes the members focus on each other instead of reaching group goals (Wit et al., 2012). When members lack mutual trust, they are likely to interpret task conflict (resulting from PSC members acting according to individual responsibilities) as hidden agendas or personal attacks. In the words of Simons and Peterson (2000, p. 109): “companies can realize the benefits of task conflict with minimal danger of relationship conflict if an appropriate basis of intragroup trust is established.”

We argue that PSC members acting from clear individual responsibilities (Bechky, 2006), having shared overall goals (Janssen et al., 1999) and having mutual trust (Simons and Peterson, 2000) helps achieve governance towards and support of the project. Thus, it could add to project success. Based on findings and literature from Organization Management and data from interviews in our earlier study (Stoppels et al., 2025), we add that PSC members will only engage in information sharing, discussing and integrating if they trust the other members and share overall goals (Franco et al., 2016). If not, we expect members to consider only the interests of their function within the permanent organization, leading to task conflict that can lead to relationship conflict (Simons and Peterson, 2000). On the contrary, if members trust each other and share the same overall goal, working from individual responsibilities enhances information processing by bringing diverse viewpoints to the table, enabling members to act effectively within their respective areas of responsibility.

The PSC being functionally heterogeneous (Murphy, 2016) underscores the relevance of both negative and positive effects, as well as the significance of mutual trust and goal sharing (Deng et al., 2020). The field of organization management shows that management teams with goal consensus capitalize on differences between team members (Bang and Midelfart, 2017).

Our findings are summarized in the conceptual model of Figure 1, suggesting that having Shared Goals and Mutal Trust moderates the relation between Acting according to Individual Responsibilities and Project Success.

Figure 1
Conceptual model linking “acting according to individual responsibilities” to “project success”.The conceptual model shows a box labeled “Acting according to Individual Responsibilities” on the left, with a horizontal arrow labeled “Effects” pointing to the right toward a box labeled “Project Success”. Above the center of the horizontal arrow is a box labeled “Shared Goals”, with a downward arrow labeled “Moderates” pointing to the center of the “Effects” arrow. Below the center of the horizontal arrow is a box labeled “Mutual Trust”, with an upward arrow labeled “Moderates” pointing to the center of the “Effects” arrow.

Conceptual model linking acting according to individual responsibilities to project success

Figure 1
Conceptual model linking “acting according to individual responsibilities” to “project success”.The conceptual model shows a box labeled “Acting according to Individual Responsibilities” on the left, with a horizontal arrow labeled “Effects” pointing to the right toward a box labeled “Project Success”. Above the center of the horizontal arrow is a box labeled “Shared Goals”, with a downward arrow labeled “Moderates” pointing to the center of the “Effects” arrow. Below the center of the horizontal arrow is a box labeled “Mutual Trust”, with an upward arrow labeled “Moderates” pointing to the center of the “Effects” arrow.

Conceptual model linking acting according to individual responsibilities to project success

Close modal

If this model holds ground, there must first be a relation between Acting according to Individual Responsibilities and Project Success. So, we pose hypothesis H1:

H1.

Acting according to Individual Responsibilities has an effect on Project Success

Secondly, we expect a degree of Shared Goals and Mutual Trust to be needed to prevent task conflict from becoming relationship conflict. Literature shows that task conflict helps project success, while relationship conflict does not. A minimum level of team trust is needed for knowledge sharing (Lee et al., 2010), and trust can be a moderator rather than directly affecting success (Dirks and Ferrin, 2001). Based on interviews with members from six PSCs, our previous study added that members should be free to act based on individual responsibilities. However, they are bound by preserving mutual trust and shared goals (Stoppels et al., 2025). Therefore, we expect a different effect of Acting according to Individual Responsibilities on Project Success, between high and low degrees of Shared Goals and Mutual Trust. So, we propose hypotheses H2, split into three parts.

H2a.

The effect of Acting according to Individual Responsibilities on Project Success is different when a certain degree of Shared Goals AND Mutual Trust are present, compared to when one or both are not present.

H2b.

The effect of Acting according to Individual Responsibilities on Project Success is different when a certain degree of Shared Goals is present, compared to when this degree of Shared Goals is not present.

H2c.

The effect of Acting according to Individual Responsibilities on Project Success is different when a certain degree of Mutual Trust is present, compared to when this degree of Mutual Trust is not present.

Given that the hypotheses are derived from literature and previous studies, we chose a deductive approach using new empirical data. We follow the epistemology of the cautious realist (Blaikie, 2009), stating that respondents’ perspectives can shed light on reality. Our previous studies were qualitative and exploratory, leading to a list of standard roles and the relevance of members working from clear and communicated individual responsibilities in a setting of mutual trust and shared goals. Quantitative research enables validating the occurrence of these roles and testing hypotheses about the influence of variables on project success. A structured survey enables the data collection needed to test hypotheses (Creswell and Creswell, 2018).

The survey questions were taken from previous studies, if available. This helps construct validity and adds reusable data to the field of project management research. The survey consists of four sections. The first is to check respondents’ agreement with using the data, how long ago they experienced the PSC, whether the project has delivered at least part of the end-products and whether the PSC was dedicated to a specific project. The second is to gather data on the four variables: Project Success, Acting according to Individual Responsibilities of PSC Members, Shared Goals and Mutual Trust. The third section gathers opinions about PSCs, such as whether individual responsibilities are clear and which roles are present. The fourth and last section is on the respondent, PSC and project metadata. The survey is added as supplementary material. It was available in English (43 responses), German (18 responses) and Dutch (117 responses).

To measure project success, we follow Joslin and Muller (2015, 2016), as their survey questions are based on existing project success dimensions, are extensive and have been used in two relevant studies. A review encompassing all aspects of Project Success, with studies by Bakker and de Kleijn (2018) and Zwikael and Meredith (2021), revealed no gaps.

For the variable Acting according to Individual Responsibilities of PSC members, the survey questions were grouped into three sets: about roles and responsibilities being defined, about members acting based on individual responsibilities and about the attitude members have towards these responsibilities. The questions in the first set were defined explicitly for this study. The questions for the other two sets were adapted from a quantitative study by Michie et al. (2006) about the impact of diversity on collaboration and decision-making in Top Management Teams.

The questions on Shared Goals were grouped into three sets: Knowing the goals by the members, agreement on the goals by the members and members working based on the shared goals. They were adapted to relevance and wording for a PSC from quantitative studies by Lee et al. (1991), Michie et al. (2006) and Chow and Chan (2008).

We defined two sets of questions to assess Mutual Trust. The first set concerns perceptions of the other PSC members’ personal characteristics regarding trust, with questions adapted from Simons and Peterson (2000). The questions in the second set concern the relationship between the members, adapted from Janssen et al. (1999). We addressed benevolence, honesty and competence (Simons and Peterson, 2000).

Each question has a five-point Likert scale. For example, in the resulting variable Project Success, a score of “5.0” means the respondent answered “Strongly agree” on all the underlying questions. Table 1 shows the variables, the sets and the source. This paper uses the abbreviation in brackets in formulas for readability.

Table 1

Variables and sets for the measurement

VariableSets of questionsSource
Acting according to Individual Responsibilities (ActingResponsibilities) Roles, defined Defined for this study specifically 
Roles, acted upon Adapted from Michie et al. (2006), who quantitatively studied the impact of diversity on collaboration and decision-making in TMTs 
Roles, attitude towards Adapted from Michie et al. (2006)  
Shared Goals (Goals) Knowing the goals Adapted from Lee et al. (1991), who quantitatively studied the relationship between goal setting and goal communication for interdependent tasks. Adapted for goals in PSCs and reduced the number of questions 
Agreement on the goal Adapted from Michie et al. (2006). Their questions were specific to a case, so they were adapted for PSCs and projects 
Working on the goals Adapted from Michie et al. (2006) and Chow and Chan (2008). The latter studied the relationship between shared goals and mutual trust on knowledge sharing in organizations 
Mutual Trust (Trust) Perceptions on personal characteristics of members Adapted from Simons et al. (2000), who studied task conflict and relationship conflict in TMTs 
Relations between members Adapted from Janssen et al. (1999), who studied role shaping in management teams 
Project Success (Success) Project efficiency
Organizational benefits
Project impact
Future potential
Stakeholder satisfaction 
Taken directly from Joslin and Müller (2015) with the kind cooperation of Robert Joslin. They studied the relationship between project management methodology and project success. The question on safety was adapted to “safety performance” since pilot testers from IT projects did not understand the original phrase 
VariableSets of questionsSource
Acting according to Individual Responsibilities (ActingResponsibilities) Roles, defined Defined for this study specifically 
Roles, acted upon Adapted from Michie et al. (2006), who quantitatively studied the impact of diversity on collaboration and decision-making in TMTs 
Roles, attitude towards Adapted from Michie et al. (2006)  
Shared Goals (Goals) Knowing the goals Adapted from Lee et al. (1991), who quantitatively studied the relationship between goal setting and goal communication for interdependent tasks. Adapted for goals in PSCs and reduced the number of questions 
Agreement on the goal Adapted from Michie et al. (2006). Their questions were specific to a case, so they were adapted for PSCs and projects 
Working on the goals Adapted from Michie et al. (2006) and Chow and Chan (2008). The latter studied the relationship between shared goals and mutual trust on knowledge sharing in organizations 
Mutual Trust (Trust) Perceptions on personal characteristics of members Adapted from Simons et al. (2000), who studied task conflict and relationship conflict in TMTs 
Relations between members Adapted from Janssen et al. (1999), who studied role shaping in management teams 
Project Success (Success) Project efficiency
Organizational benefits
Project impact
Future potential
Stakeholder satisfaction 
Taken directly from Joslin and Müller (2015) with the kind cooperation of Robert Joslin. They studied the relationship between project management methodology and project success. The question on safety was adapted to “safety performance” since pilot testers from IT projects did not understand the original phrase 

The first version of the survey was pilot-tested by 15 project managers, leading to minor adjustments in wording. These responses were not used in the analysis. Data collection was conducted through snowball sampling, as there is no formal organization of PSC members. Respondents were approached through the researchers’ network, and via six project management organizations (APM Austria, BPUG, GAPPS, IPMA-NL, PMI Benelux and NAP-network), and one organization of project owners (NETLIPSE). We explicitly asked respondents to forward the email invitation to PSC members, as these were the most difficult to approach. We included responses from project managers, as they attend PSC meetings and can evaluate project success for stakeholders (Cheung et al., 2010). The survey was conducted online between April 2023 and August 2024 using the Qualtrics platform (2023) and in two time periods. After the first period, 60% of the respondents were project managers. Therefore, we specifically targeted PSC members in the next round, resulting in a 53% response by project managers overall. We tested the variation for the four main variables between the two periods and found no significant effect. Responses were anonymous, and the University’s ethics committee approved the survey design.

We asked respondents with experience in a PSC dedicated to a project somewhere in the last three years. At least part of the end-products had to be delivered to ensure knowledge of project success (Cooke-Davies, 2002). We did not select the projects based on their type, size, or duration, but we did measure these factors. Checking for valid responses through the survey questions resulted in the exclusion of 29 out of 207 responses. Since the object of study is the PSC, respondents were asked to answer the questions for their most recent PSC that fits the criteria mentioned above.

The study employed recommendations by Kamakura (2010) and Podsakoff and MacKenzie (2003) to minimize common methods bias, ensuring anonymity through the survey and achieving construct validity by reusing questions from previous research and conducting pilot testing.

To provide insights into modeling relationships, data were presented and analyzed graphically, as Field (2017) recommends. Since we aim to find an association between several predictors and the Success variable, we used multiple linear regression as the primary data analysis technique. The three-dimensional graphics suggest linear modeling provides a good fit. The corresponding p-values are obtained by t-testing. All data analyses were conducted with the open-source statistical environment R (R Core Team, 2022). The studies used several regression models. For readability, we added a “#” followed by a sequence number to each model.

To test if the questions can be combined into sets and the sets can be combined into variables, we calculated Cronbach’s Alpha for each variable (Table 2). A value above 0.7 indicates a good match (Hair et al., 2010); when it is lower, further investigation is justified. For the variable Trust, Cronbach’s Alpha is on the low side. The end of the survey has optional text fields for the name of the PSC and for general remarks. We rechecked the underlying questions on Trust with the data from these text fields and other data, considering the context of the PSC and how respondents might interpret them. We also calculated the correlation matrix of the sets within Trust. We concluded that they measured various aspects of the same variable. The high Cronbach’s Alpha for the variable Success confirms the findings of Joslin and Müller (2016), who used the same construct and reported an alpha of 0.92.

Table 2

Cronbach’s alpha for the variables

VariableCronbach’s alpha
Actingresponsibilities 0.73 
Goals 0.85 
Trust 0.58 
Success 0.89 
VariableCronbach’s alpha
Actingresponsibilities 0.73 
Goals 0.85 
Trust 0.58 
Success 0.89 

Figure 2 provides the respondents’ demographics. There are slightly more project managers than PSC members, but the overall number of PSC members is unique for research in project governance. The data encompasses a diverse range of project types and sizes.

Figure 2
Four pie charts shows respondents’ and projects’ demographics.The top left pie chart is titled “Role towards the PSC”. The data presented in the chart clockwise is as follows: “Project manager: 53 percent”, “Member: 41 percent”, and “PMO: 6 percent”. The top right pie chart is titled “Function in the permanent organization”. The data presented in the chart clockwise is as follows: “Project manager: 53 percent”, “Executive board: 19 percent”, “Staff manager: 12 percent”, “Operations manager: 10 percent”, and “PMO: 5 percent”. The bottom left pie chart is titled “Type of project”. The data presented in the chart clockwise is as follows: “ICT: 45 percent”, “Engineering or Construction: 24 percent”, “Research and Development: 13 percent”, “Government: 9 percent”, and “Process change: 9 percent”. The bottom right pie chart is titled “Project size in millions of euros”. The data presented in the chart clockwise is as follows: “less than 0.5: 14 percent”, “0.5 to 1: 14 percent”, “1 to 5: 31 percent”, “5 to 25: 18 percent”, and “greater than 25: 23 percent”.

Respondents’ and projects’ demographics

Figure 2
Four pie charts shows respondents’ and projects’ demographics.The top left pie chart is titled “Role towards the PSC”. The data presented in the chart clockwise is as follows: “Project manager: 53 percent”, “Member: 41 percent”, and “PMO: 6 percent”. The top right pie chart is titled “Function in the permanent organization”. The data presented in the chart clockwise is as follows: “Project manager: 53 percent”, “Executive board: 19 percent”, “Staff manager: 12 percent”, “Operations manager: 10 percent”, and “PMO: 5 percent”. The bottom left pie chart is titled “Type of project”. The data presented in the chart clockwise is as follows: “ICT: 45 percent”, “Engineering or Construction: 24 percent”, “Research and Development: 13 percent”, “Government: 9 percent”, and “Process change: 9 percent”. The bottom right pie chart is titled “Project size in millions of euros”. The data presented in the chart clockwise is as follows: “less than 0.5: 14 percent”, “0.5 to 1: 14 percent”, “1 to 5: 31 percent”, “5 to 25: 18 percent”, and “greater than 25: 23 percent”.

Respondents’ and projects’ demographics

Close modal

Four of the six participating project management organizations were based in the Netherlands, resulting in 73% of the projects primarily located there. Both project managers and PSC members considered themselves experienced, with 84% of PSC members and 97% of project managers scoring 4 or 5.

To test the hypotheses for the conceptual model, we used linear regression. The first hypothesis (H1), that there is an effect of Actingresponsibilities on Success, can be confirmed via simple linear regression using the following model #1:

We found an effect of Actingresponsibilities of β1 = 0.48 ± 0.06, with a P-value smaller than 0.001 (Figure 3).

Figure 3
A scatter plot of “Project Success” versus “Acting according to Individual Responsibilities” with a trend line.The vertical axis is labeled “Project Success” and ranges from 1 to 5 in increments of 1unit. The horizontal axis is labeled “Acting according to Individual Responsibilities” and ranges from 1 to 5 in increments of 1 unit. The left end of the horizontal axis reads “Strongly disagree”, and the right end reads “Strongly agree”. A single straight trend line begins at (0.8, 2.6) and increases steadily to (5.3, 4.6). It extends diagonally upward from the lower left toward the upper right across the plotted points. Numerous individual data points are plotted across the chart area, scattered above and below the trend line. Note: All numerical data values are approximated.

Relationship between “acting according to individual responsibilities” and “project success” – scatterplot with trendline

Figure 3
A scatter plot of “Project Success” versus “Acting according to Individual Responsibilities” with a trend line.The vertical axis is labeled “Project Success” and ranges from 1 to 5 in increments of 1unit. The horizontal axis is labeled “Acting according to Individual Responsibilities” and ranges from 1 to 5 in increments of 1 unit. The left end of the horizontal axis reads “Strongly disagree”, and the right end reads “Strongly agree”. A single straight trend line begins at (0.8, 2.6) and increases steadily to (5.3, 4.6). It extends diagonally upward from the lower left toward the upper right across the plotted points. Numerous individual data points are plotted across the chart area, scattered above and below the trend line. Note: All numerical data values are approximated.

Relationship between “acting according to individual responsibilities” and “project success” – scatterplot with trendline

Close modal

Given that we know the values of Actingresponsibilities, Goals and Trust, we asked ourselves if this helps predict Success. First, we looked at correlations, of which Table 3 provides an overview. These are moderate to strong correlations, all well above 0.5.

Table 3

Correlations between the four variables

VariableActingresponsibilitiesGoalsTrustSuccess
Actingresponsibilities 1.00    
Goals 0.56 1.00   
Trust 0.56 0.70 1.00  
Success 0.56 0.63 0.59 1.00 
VariableActingresponsibilitiesGoalsTrustSuccess
Actingresponsibilities 1.00    
Goals 0.56 1.00   
Trust 0.56 0.70 1.00  
Success 0.56 0.63 0.59 1.00 

Working from the conceptual model relating Actingresponsibilities to Success, the three-dimensional linear model #2 predicts Success based on the other three variables:

This linear regression leads to estimates of β0, β1, β2 and β3, which are shown in Table 4.

Table 4

Estimated coefficients for the prediction of Success using Model #2

Variable in functionEstimateStd. Errorp-value
β0, intercept 1.41 0.20 <0.001 
β1, Goals 0.27 0.07 <0.001 
β2, Trust 0.16 0.07 0.02 
β3, Actingresponsibilities 0.21 0.06 <0.001 
Variable in functionEstimateStd. Errorp-value
β0, intercept 1.41 0.20 <0.001 
β1, Goals 0.27 0.07 <0.001 
β2, Trust 0.16 0.07 0.02 
β3, Actingresponsibilities 0.21 0.06 <0.001 

So, we can conclude that all three variables Actingresponsibilities, Trust and Goals predict Success although for Trust, the significance is less strong than the other two. The R-squared of model #2 is 0.48, so given Actingresponsibilities, Goals and Trust are known, 48% of the variation in Success can be predicted.

Hypothesis 2 claims that the effect of Actingresponsibilities on Success is different when a certain degree of shared Goals and Mutual Trust are present, compared to when one or both are not present. So, there should be a threshold value of both Goals and Trust, which changes the correlation between Actingresponsibilities and Success. For the threshold, we started with the mean values of Goals (3.86) and Trust (3.73). For each response in the database, we added a new variable 1, where 1 = 1 if the threshold value was met and 1 = 0 if not met. This provides two stratifications in the data, which makes it possible to test the significance of β3 (the difference between the effects of Actingresponsibilities between the stratifications). We need three models #3 to test the three sub-hypotheses:

  • Hypothesis H2a: both Goals AND Trust have met the threshold, Model #3A:

  • Hypothesis H2b: Goals has met the threshold, Model #3B:

  • Hypothesis H2c: Trust has met the threshold, Model #3C:

The left side of Table 5 shows the estimation results for β3 in the three models #3A, #3B and #3C.

Table 5

Estimated coefficients for the prediction of Success using Model #3

Threshold = meanThreshold = 3
ModelEstimate of β3P-value of the test β3 = 0Estimate of β3P-value of the test β3 = 0
Model #3A: Goals AND Trust −0.15 0.19 −0.18 0.15 
Model #3B: Goals −0.17 0.13 −0.17 0.13 
Model #3C: Trust −0.06 0.58 −0.06 0.58 
Threshold = meanThreshold = 3
ModelEstimate of β3P-value of the test β3 = 0Estimate of β3P-value of the test β3 = 0
Model #3A: Goals AND Trust −0.15 0.19 −0.18 0.15 
Model #3B: Goals −0.17 0.13 −0.17 0.13 
Model #3C: Trust −0.06 0.58 −0.06 0.58 

We found no significant difference between the effects of Actingresponsibilities on Success, assuming high or low Goals and Trust. So, it’s likely that hypotheses H2a, H2b and H2c must be rejected. Even if, in reality, there is a difference between the stratifications, this is small and will have no practical consequences. One reason might be that the range of measured Trust or Goals is too limited. Indeed, the average values for Goals and Trust are above the neutral (“neither agree nor disagree”) value of 3. Therefore, we retested the difference between stratifications with lower threshold values of 3. As presented on the right side of Table 5, this led to minimal differences.

Testing the hypotheses separately between project managers and PSC members leaves too few data points. We did, however, check if the indicated Success differs between project managers and PSC members, as shown in Figure 4.

Figure 4
A two-panel histogram of “Project Success” for “Project Manager” and “PSC member”.The top panel is labeled “Project Manager” along the right side, and the bottom panel is labeled “PSC member” along the right side. In both panels, the vertical axis on the left is labeled “Count” and ranges from 0 to 10 in increments of 5 units. The horizontal axis at the bottom is labeled “Project Success” and ranges from 1 to 5 in increments of 1 unit. The left end of the horizontal axis reads “Strongly disagree”, and the right end reads “Strongly agree”. In the “Project Manager” panel, most bars are concentrated between 3 and 5. The tallest bars occur around a value of 4, reaching a height of approximately 10 to 15 counts. Bars between 3 and 4 generally range from about 4 to 9 counts. There is a small bar near 1 with a height of about 1 count, and a few bars near 2 with heights of about 1 to 2 counts. In the “P S C member” panel, responses are also clustered between 3 and 5. The tallest bar appears around 4, reaching 17 counts. Bars between 3 and 4 range from about 4 to 8 counts. Bars near 5 reach about 2 to 4 counts. There are very few responses below 3, with bar heights of about 1 count. Note: All numerical data values are approximated.

Comparison of rating project success between project managers and PSC members

Figure 4
A two-panel histogram of “Project Success” for “Project Manager” and “PSC member”.The top panel is labeled “Project Manager” along the right side, and the bottom panel is labeled “PSC member” along the right side. In both panels, the vertical axis on the left is labeled “Count” and ranges from 0 to 10 in increments of 5 units. The horizontal axis at the bottom is labeled “Project Success” and ranges from 1 to 5 in increments of 1 unit. The left end of the horizontal axis reads “Strongly disagree”, and the right end reads “Strongly agree”. In the “Project Manager” panel, most bars are concentrated between 3 and 5. The tallest bars occur around a value of 4, reaching a height of approximately 10 to 15 counts. Bars between 3 and 4 generally range from about 4 to 9 counts. There is a small bar near 1 with a height of about 1 count, and a few bars near 2 with heights of about 1 to 2 counts. In the “P S C member” panel, responses are also clustered between 3 and 5. The tallest bar appears around 4, reaching 17 counts. Bars between 3 and 4 range from about 4 to 8 counts. Bars near 5 reach about 2 to 4 counts. There are very few responses below 3, with bar heights of about 1 count. Note: All numerical data values are approximated.

Comparison of rating project success between project managers and PSC members

Close modal

As the figure shows, the distributions are mainly the same. We quantified the difference in means using linear regression, which confirmed that the difference is not significant (p-value = 0.172).

Figure 5 provides an overview of the roles present in the PSC and in which combinations. The “Set size” on the left shows the role’s occurrence. One PSC member can have several roles. In a previous study (Stoppels et al., 2025), we defined the role of “Quality assurance”. In the survey questions and the figure below, we split this into a role to check quality assurance (No representation but a role to check quality on behalf of the PSC) and to advise (No representation but a role to advise/add skills not present in the PSC) because Karlsen (2020) only mentions the second.

Figure 5
The figure shows an UpSet chart with role counts on the left and intersection counts on the right, connected by a dot matrix.The figure shows a combined horizontal bar graph, vertical bar graph, and matrix diagram. On the right side, a vertical bar chart is labeled “Intersection count” along the vertical axis. The vertical axis ranges from 0 to 50 in increments of 10 units. The bars are arranged from tallest to shortest from left to right. The tallest bar reaches 47. The next bars have heights of 16 and 12, followed by bars with heights of 9, 9, 7, 6, 5, 4, 4, 3, 3, 3, and 3. These are followed by several bars with heights of 2, and multiple smaller bars with heights of 1. Below the vertical bars is a matrix of dots arranged in rows and columns. Some dots are connected vertically by lines, indicating role combinations corresponding to each intersection bar above. On the left side, a horizontal bar chart is labeled “Roles count” along the horizontal axis, which ranges from 0 to 100 in increments of 50 units. The horizontal bars extend leftward to varying lengths. “Repr. of a user group of the project’s products” is the longest bar, extending to approximately 110. “Repr. of the funder(s)” extends to about 95. “Repr. of a group maintaining the products after usage starts” extends to about 85. “Repr. of a supplier towards the project” extends to about 70. “No repr. but a role to advise or add skills not present” extends to about 45. “No repr. but a role to check quality on behalf of P S C” is the shortest, extending to about 35. Note: All numerical data values are approximated.

Roles that are present in the Project Steering Committee

Figure 5
The figure shows an UpSet chart with role counts on the left and intersection counts on the right, connected by a dot matrix.The figure shows a combined horizontal bar graph, vertical bar graph, and matrix diagram. On the right side, a vertical bar chart is labeled “Intersection count” along the vertical axis. The vertical axis ranges from 0 to 50 in increments of 10 units. The bars are arranged from tallest to shortest from left to right. The tallest bar reaches 47. The next bars have heights of 16 and 12, followed by bars with heights of 9, 9, 7, 6, 5, 4, 4, 3, 3, 3, and 3. These are followed by several bars with heights of 2, and multiple smaller bars with heights of 1. Below the vertical bars is a matrix of dots arranged in rows and columns. Some dots are connected vertically by lines, indicating role combinations corresponding to each intersection bar above. On the left side, a horizontal bar chart is labeled “Roles count” along the horizontal axis, which ranges from 0 to 100 in increments of 50 units. The horizontal bars extend leftward to varying lengths. “Repr. of a user group of the project’s products” is the longest bar, extending to approximately 110. “Repr. of the funder(s)” extends to about 95. “Repr. of a group maintaining the products after usage starts” extends to about 85. “Repr. of a supplier towards the project” extends to about 70. “No repr. but a role to advise or add skills not present” extends to about 45. “No repr. but a role to check quality on behalf of P S C” is the shortest, extending to about 35. Note: All numerical data values are approximated.

Roles that are present in the Project Steering Committee

Close modal

The roles of representing funder(s), user groups, suppliers towards the project and groups maintaining the project’s products are typically present. The roles of quality assurance or advice are rare, though they occur. The figure shows that some PSCs lack representation from the funder, so we contacted the respondents who voluntarily left their email addresses. They either indicated the funder was indirectly funding via a project owner or that the budget had to be approved by a portfolio board.

In the survey, we also asked whether each role should be present. Respondents strongly agreed on the need for all the representation roles, with more than 80% in agreement (score 4 or 5). These roles are Representation of the Funder, Representation of User Groups, Representation of Suppliers of Project Resources and Representation of the Support organization for Project Deliverables. Opinions on the need for a role solely for Quality Assurance towards the PSC were diverse: 49% scored 4 or 5.

The survey also asked respondents to rate the reasoning behind the hypotheses on a five-point Likert scale, thereby assessing their views on the conceptual model. Table 6 shows the questions and the percentage with scores 4 or 5. Results indicate that respondents seem to agree with the conceptual model, although our statistical testing does not support it.

Table 6

Opinions about acting according to individual responsibilities, shared goals and mutual trust (N = 163)

QuestionPercentage score 4 or 5
If members act according to agreed-upon personal responsibilities, this improves project success 79% 
Having shared goals are a prerequisite before members should act from their own responsibilities 90% 
Mutual trust among members is a prerequisite before members should act from their own responsibilities 90% 
QuestionPercentage score 4 or 5
If members act according to agreed-upon personal responsibilities, this improves project success 79% 
Having shared goals are a prerequisite before members should act from their own responsibilities 90% 
Mutual trust among members is a prerequisite before members should act from their own responsibilities 90% 

A PSC can be needed for governance or support (Crawford et al., 2008). Governance is needed for risk limitation towards the owning organizations. Therefore, we asked if the owning organization is at risk if the project fails. To address the potential need for support, we measured the perceived importance of the PSC in solving conflicts of interest between stakeholder groups and stakeholder commitment. Table 7 shows the percentage of responses for levels of perceived risk for the organization if the project fails and the need for PSC involvement in stakeholder management. Hardly any projects are in the low/low area, where, according to the literature, there is no need for a PSC.

Table 7

Responses on PSC needed to limit risk or for stakeholder management (N = 163)

PSC is needed for stakeholder commitment or resolving conflicts of interest in stakeholder groups
HighLow
In case the project fails, the owning organization is at risk High 48% 4% 
Medium 12% 3% 
Low 30% 2% 
PSC is needed for stakeholder commitment or resolving conflicts of interest in stakeholder groups
HighLow
In case the project fails, the owning organization is at risk High 48% 4% 
Medium 12% 3% 
Low 30% 2% 

We also asked if the project needs a PSC to succeed. Respondents see the need, with 90% in agreement (Agree or Strongly Agree).

This discussion section compares the survey results to the literature and the conceptual model.

Hypothesis 1 was confirmed, since Actingresponsibilities and Success were shown to have a strong positive correlation. Previous studies indicate this could be a causal relation, since acting from clear individual responsibilities sharpens decision-making, builds commitment, prevents conflict and prevents gaps in activities (Stoppels et al., 2025).

Hypothesis 2 states that the effect of Acting according to Individual Responsibilities on Project Success differs when a certain degree of Shared Goals and Mutual Trust are present, compared to when one of the two or both are not present. Based on the data gathered, this was not confirmed. However, respondents agreed with this hypothesis when asked directly, thus aligning with a previous qualitative study (Stoppels et al., 2025). The first reason for the discrepancy might be that the PSCs studied are mainly in the higher Mutual Trust and Shared Goals area (78% of responses have both above 3). Thus, the data lacks range, even while we calibrated towards the mean. The same lack of range in our data is in Project Success (88% of responses above 3). For projects in trouble, members might start acting primarily based on interests from their position in the permanent organization (Stoppels et al., 2025). Finding enough PSCs with lower trust to expand the dataset might not be feasible, given that in our study, seven professional organizations have cooperated. Follow-up studies can be qualitative on specific projects having difficulty moving forward or lacking trust among PSC members.

The second reason for the discrepancy might be that the conceptual model needs adjustment. Both this study and the previous study (Stoppels et al., 2025) indicate that project managers and PSC members think a minimum of Shared Goals and Mutual Trust are needed before Acting according to Individual Responsibilities improves Project Success. Our quantitative data show that Acting according to Individual Responsibilities always has a positive relationship with Project Success. So, it might be a matter of priority in team development: acting from individual responsibilities is always beneficial, but when shared goals or mutual trust are lacking, improving those takes priority over clarifying individual responsibilities.

A first alternative conceptual model could focus on the effort and timing of activities by the PSC to achieve shared goals, mutual trust and members acting according to their individual responsibilities. A second alternative conceptual model could include decision-making and holding the project manager to account as mediators. Thereby, following recent work by Turner (2025) on decision-making as a mediator between governance and project success and including the holding to account part of governance (Müller et al., 2016). In such a model, Mutual Trust, Shared Goals and Acting from Individual Responsibilities could be the influencing variables, with Project Success as the dependent variable.

Knowing Acting according to Individual Responsibilities, Mutual Trust and Shared Goals, 48% of Project Success can be predicted. We found a strong positive correlation between the four variables, but each variable adds to the prediction of Project Success. It seems advisable to work on achieving all three and measure them at project reviews.

Although we could not compare per project, the data suggest that whether the respondent is a project manager or PSC member does not influence the scores on Project Success. This finding is reassuring for previous and future research, as studies on project governance typically use project managers as respondents (e.g. Bucero, 2024; Joslin and Müller, 2016) or respondents who identify themselves as project owners on LinkedIn (e.g. Musawir et al., 2017).

We found that the four representation roles, as proposed in our earlier work (Stoppels et al., 2025) and in line with the project management method PRINCE2 (Axelos, 2009), are generally covered in the projects in our dataset. We found indications of quality assurance roles toward the PSC being present, thus confirming earlier findings (Stoppels et al., 2025). This earlier study suggested that members whose only role is Quality Assurance towards the PSC could add skills and knowledge on project oversight, the product to be delivered, or stakeholders. Based on a case study, Karlsen (2020) explicitly recommends including external members (not working at a funding, owning, or supplying organization) to bring expertise and trustworthiness. However, our previous study found examples where the lack of accountability towards a permanent organization led to free-riding or jeopardizing the authority of other PSC members. These pros and cons may be reflected in the survey respondents’ mixed opinions. We infer that individual roles and responsibilities should be considered when designing a governance structure. The PSC at the group level is an agent to the funder and a principal to the project manager. But so is each individual member.

Since the study reused the Project Success questions and the project categorization from Joslin and Muller (2016), the data can be used in future meta-studies. Given the high Cronbach’s Alpha (>0.9) of the variable Project Success found by both Joslin and Muller (2016) and this study, it could be considered to reduce the number of questions in future studies that only need Project Success on an aggregated level.

Literature suggests project efficiency is mainly independent of long-term value in the eyes of stakeholders (De Wit, 1988; Musawir et al., 2017). If so, we would expect the Cronbach’s Alpha for Project Success to be lower than 0.9. Therefore, this and previous studies may experience a halo effect on some respondents (Podsakoff et al., 2003). They might project their opinion on the more observable project success dimension, Project Efficiency, to the less observable ones, such as Future Potential and Stakeholder Satisfaction (Khan, 2012).

The data support the two reasons for a PSC, as stated by Crawford et al. (2008): governance and support. There are hardly any PSCs in the study where the need for both is low. In line with previous qualitative studies (Stoppels et al., 2023), projects with a high need for support require a PSC when “things get rough”. Respondents indicated that the project needed a PSC to succeed, but there may be a bias because respondents are accustomed to having one. So, follow-up research could focus on projects posing high risk and requiring support, where no PSC was used for oversight, but other governance institutions were used instead (Müller et al., 2017).

This study quantitatively measures the impact of Acting according to Individual Responsibilities, Shared Goals and Mutual Trust of PSC members on Project Success. It is unique in explicitly including PSC members as respondents, thereby addressing the call by Pitsis et al. (2014) to regard project governance as a concern beyond project managers.

We found a clear relationship among these four variables. We proposed that members should have a minimum level of shared goals and mutual trust before acting from their individual responsibilities. Our earlier explorative study suggested that this common foundation is needed to prevent transaction-based negotiation, which jeopardizes information sharing, discussion and integration. Organizational management literature supports this, showing that relationship conflict may arise when shared goals and mutual trust are lacking, potentially harming decision-making quality (Simons and Peterson, 2000).

However, our data did not support the hypothesis that a threshold of Shared Goals and Mutual Trust is required for Acting according to Individual Responsibilities to positively relate to Project Success. When asked directly in the survey, respondents indicated that members should first focus on achieving shared goals and mutual trust before acting on individual responsibilities. We conclude that members knowing individual responsibilities and acting on them is always beneficial, but there is a priority. This implies for practice that, when initiating a PSC, members should start by clarifying and sharing goals and building trust. Understanding how members do this justifies future research, such as longitudinal case studies of members’ role-taking.

The variables Acting according to Individual Responsibilities, Mutual Trust and Shared Goals are a predictor of 48% of Project Success. Although this study does not meet Van de Ven’s (2007) criteria for causality, our earlier exploratory study and the survey of respondents’ opinions suggest a causal association. Therefore, our study implies that members should take time at the launch of a PSC to discuss their own and other members’ responsibilities and how these influence actions and decision-making. Moreover, members should work on team processes to improve mutual trust and informed agreement on the overall goals.

The study is unique in that it quantitatively distinguishes standardized roles of members. We found support for using five roles to select PSC members and determine their individual responsibilities. The four representation roles for funders, user groups, suppliers to the project and groups maintaining the project’s products are generally covered in a PSC. These four roles are about representing the contributing and affected types of stakeholders (McGrath and Whitty, 2017) that influence project success. The role of quality assurance towards the PSC is often unfilled and should be used prudently, as members with only this role have limited accountability. The roles can be used in practice, and PSCs’ inner workings could be further studied based on these roles.

The study’s main weakness is the limited number of projects with low trust among members and low project success, which might limit the size of the effects we detect. With our snowballing approach, the non-response bias is unknown. There may be a bias towards more successful projects, as a project manager might have a better relationship with PSC members in these projects and be more inclined to forward the survey. Another limitation is that common-method bias cannot be ruled out: the same respondents answer questions about all variables. Future studies would benefit from benchmark data on project success related to project, governance and contextual indicators, to which our data can be a part of the input.

Our findings indicate that PSCs play a significant role in project success, based on the perspectives of both PSC members and project managers. This justifies further investigation into the inner workings, success factors and other variables that influence the effectiveness of PSCs in project oversight. Critical case studies of PSCs supervising failing projects (Flyvbjerg, 2006), combined with an interactionalist view of role theory (Bechky, 2006), can provide insights.

Our study adds to agency theory by highlighting that PSCs are not a uniform group but a heterogeneous governance body. The members are, at the same time, agents to their own stakeholder groups and to the funder and owner. Also, the members are part of a group that (at the group level) provides unified direction as a principal to the project manager. The study adds to the project-governance research strand Resilience (Sankaran et al., 2025), highlighting the added value of coping with a dynamic environment by having functionally diverse senior managers from contributing and affected stakeholders at the table. Our study adds to the research strand Organizational by showing the inner workings of a frequently used governance body, as a collaborative device between organizations and departments. Practitioners should make an effort to understand the impact of overall goals on PSC members’ individual responsibilities and should build mutual trust within the PSC by understanding the other members’ responsibilities. This enables PSCs to offer unified direction and contribute meaningfully to project success.

The supplementary material for this article can be found online.

Al-Twairesh
,
N.
and
Al-Mudimigh
,
A.S.
(
2011
), “
Business cases for ERP implementations
”,
Journal of Theoretical and Applied Information Technology
, Vol. 
25
No. 
1
, pp. 
43
-
49
,
available at:
 https://www.jatit.org/volumes/Vol25No1/6Vol25No1.pdf.
Allen
,
J.P.
(
2005
), “
Value conflicts in enterprise systems
”,
Information Technology and People
, Vol. 
18
No. 
1
, pp. 
33
-
49
, doi: .
Andersen
,
E.S.
(
2012
), “
Illuminating the role of the project owner
”,
International Journal of Managing Projects in Business
, Vol. 
5
No. 
1
, pp. 
67
-
85
, doi: .
Arnesson
,
K.
and
Albinsson
,
G.
(
2013
), “
Interaction patterns in a steering group: power and action outcome
”,
Economic and Industrial Democracy
, Vol. 
35
No. 
2
, pp. 
325
-
340
, doi: .
Axelos
(
2009
),
Directing Successful Projects with PRINCE2
, (1st ed.) ,
Axelos, Norwich
.
Bakker
,
H.L.M.
and
De Kleijn
,
J.P.
(
2018
),
Projects and People: Mastering Success
,
NAP – Process Industry Network
.
Bang
,
H.
and
Midelfart
,
T.N.
(
2017
), “
What characterizes effective management teams? A research-based approach
”,
Consulting Psychology Journal: Practice and Research
, Vol. 
69
No. 
4
, pp. 
334
-
359
, doi: .
Bechky
,
B.A.
(
2006
), “
Gaffers, gofers, and grips: role-based coordination in temporary organizations
”,
Organization Science
, Vol. 
17
No. 
1
, pp. 
3
-
21
, doi: .
Benoliel
,
P.
and
Somech
,
A.
(
2016
), “
Functional heterogeneity and senior management team effectiveness
”,
Journal of Educational Administration
, Vol. 
54
No. 
4
, pp. 
492
-
512
, doi: .
Blaikie
,
N.
(
2009
),
Designing Social Research
,
Polity Press
.
Breese
,
R.
,
Couch
,
O.
and
Turner
,
D.
(
2020
), “
The project sponsor role and benefits realisation: more than ‘just doing the day job’
”,
International Journal of Project Management
, Vol. 
38
No. 
1
, pp. 
17
-
26
, doi: .
Bucero
,
A.
(
2024
), “
Project sponsor effectiveness and project success
”,
European Project Management Journal
, Vol. 
14
No. 
2
, pp. 
3
-
16
, doi: .
Cellerino
,
F.
,
Mancini
,
M.
and
Ahola
,
T.
(
2025
), “
From perceptions to value: a multi-stakeholder framework for public infrastructure design
”,
International Journal of Managing Projects in Business
, pp. 
1
-
25
, doi: .
Cheung
,
Y.K.F.
,
Zolin
,
R.
,
Turner
,
J.R.
and
Remington
,
K.
(
2010
), “
Agree or disagree? Level of alignment between project manager and stakeholders on performance indicators
”,
Proceedings of the 7th Annual Project Management Australia Conference
.
Chow
,
W.S.
and
Chan
,
L.S.
(
2008
), “
Social network, social trust and shared goals in organizational knowledge sharing
”,
Information and Management
, Vol. 
45
No. 
7
, pp. 
458
-
465
, doi: .
Clerkin
,
T.A.
and
Jones
,
K.J.
(
2013
), “
A study of conflict in top management decision making: the impact of contribution motive
”,
The Coastal Business Journal
, Vol. 
12
No. 
1
,
available at:
 https://digitalcommons.coastal.edu/cbj/vol12/iss1/3.
Cooke-Davies
,
T.
(
2002
), “
The ‘real’ success factors on projects
”,
International Journal of Project Management
, Vol. 
20
No. 
3
, pp. 
185
-
190
, doi: .
Crawford
,
L.
(
2023
), “Steering committees as governance entities”, in
Research Handbook on the Governance of Projects
,
Edward Elgar Publishing
, pp. 
116
-
123
,
available at:
 https://www.scopus.com/inward/record.uri?eid=2-s2.0-85175126207&partnerID=40&md5=c899e74a11640c6146bc8383c188c8fa.
Crawford
,
L.
,
Cooke-Davies
,
T.
,
Hobbs
,
B.
,
Labuschagne
,
L.
,
Remington
,
K.
and
Cheng
,
P.
(
2008
), “
Governance and support in the sponsoring of projects and programs
”,
Project Management Journal
, Vol. 
39
No. 
S1
, pp. 
S43
-
S55
, doi: .
Creswell
,
J.W.
and
Creswell
,
D.J.
(
2018
),
Research Design: Qualitative, Quantitative, and Mixed Methods Approaches
, (5th ed.) ,
Sage Publications
.
De Wit
,
A.
(
1988
), “
Measurement of project success
”,
International Journal of Project Management
, Vol. 
6
No. 
3
, pp. 
164
-
170
, doi: .
DeFillippi
,
R.
and
Sydow
,
J.
(
2016
), “
Project networks: governance choices and paradoxical tensions
”,
Project Management Journal
, Vol. 
47
No. 
5
, pp. 
6
-
17
, doi: .
Deng
,
X.
,
Liu
,
Y.
,
Long
,
X.
,
Luo
,
Z.
and
Luo
,
H.
(
2020
), “
The impact of TMT functional heterogeneity on corporate performance: the mediating effect of managerial cognition and group conflict
”,
Journal of Industrial Engineering and Engineering Management
, Vol. 
3
No. 
34
, pp. 
32
-
44
.
Dirks
,
K.T.
and
Ferrin
,
D.L.
(
2001
), “
The role of trust in organizational settings
”,
Organization Science
, Vol. 
12
No. 
4
, pp. 
450
-
467
, doi: .
Field
,
A.M.
and
Jeremy
(
2017
),
Discovering Statistics Using R
, (5th ed.) ,
Sage
.
Flyvbjerg
,
B.
(
2006
), “
Five misunderstandings about case-study research. Qualitative inquiry
”,
Qualitative Inquiry
, Vol. 
12
No. 
2
, pp. 
219
-
245
, doi: .
Franco
,
L.A.
,
Rouwette
,
E.A.J.A.
and
Korzilius
,
H.
(
2016
), “
Different paths to consensus? The impact of need for closure on model-supported group conflict management
”,
European Journal of Operational Research
, Vol. 
249
No. 
3
, pp. 
878
-
889
, doi: .
Hair
,
J.
,
Black
,
W.
,
Babin
,
B.
and
Anderson
,
R.
(
2010
),
Multivariate Data Analysis
, (7th ed.) ,
Prentice Hall
.
Harvey
,
J.
,
Coulombe
,
C.
,
Rankohi
,
S.
and
Drouin
,
N.
(
2025
), “
Understanding the interacting layers of multi-level governance in Quebec’s public infrastructure projects
”,
International Journal of Managing Projects in Business
, Vol. 
18
No. 
3
, pp. 
455
-
478
, doi: .
Janssen
,
O.
,
Van de Vliert
,
E.
and
Veenstra
,
C.
(
1999
), “
How task and person conflict shape the role of positive interdependence in management teams
”,
Journal of Management
, Vol. 
25
No. 
2
, pp. 
117
-
142
, doi: .
Joslin
,
R.
and
Müller
,
R.
(
2015
), “
Relationships between a project management methodology and project success in different project governance contexts
”,
International Journal of Project Management
, Vol. 
33
No. 
6
, pp. 
1377
-
1392
, doi: .
Joslin
,
R.
and
Müller
,
R.
(
2016
), “
The relationship between project governance and project success
”,
International Journal of Project Management
, Vol. 
34
No. 
4
, pp. 
613
-
626
, doi: .
Kamakura
,
W.A.
(
2010
), “Common methods bias”, in
Wiley International Encyclopedia of Marketing
, doi: .
Karlsen
,
J.T.
(
2010
), “
Project owner involvement for information and knowledge sharing in uncertainty management
”,
International Journal of Managing Projects in Business
, Vol. 
3
No. 
4
, pp. 
642
-
660
, doi: .
Karlsen
,
J.T.
(
2020
), “
The project steering committee, project governance and trust: insights from a practical case study
”,
Management Research Review
, Vol. 
44
No. 
6
, pp. 
926
-
947
, doi: .
Khan
,
M.E.
(
2012
), “
Relationship between project attributes, project performance, and project governance dimensions-building the theoretical framework PMI global congress proceedings – EMEA
”.
Khan
,
K.A.
,
Turner
,
J.R.
and
Maqsood
,
T.
(
2013
),
Factors that Influence the Success of Public Sector Projects in Pakistan. IRNOP 2013 Conference
,
BI Norwegian Business School
,
Oslo, Norway
.
Kloppenborg
,
T.J.
and
Tesch
,
D.
(
2015
), “
How executive sponsors influence project success
”,
MIT Sloan Management Review
, Vol. 
56
No. 
3
, pp. 
27
-
30
.
Lechler
,
T.G.
and
Cohen
,
M.
(
2009
), “
Exploring the role of steering committees in realizing value from project management
”,
Project Management Journal
, Vol. 
40
No. 
1
, pp. 
42
-
54
, doi: .
Lee
,
C.
,
Earley
,
C.
,
Lituchy
,
T.R.
and
Wagner
,
M.
(
1991
), “
Relation of goal setting and goal sharing to performance and conflict for interdependent tasks
”,
British Journal of Management
, Vol. 
2
No. 
1
, pp. 
33
-
39
, doi: .
Lee
,
P.
,
Gillespie
,
N.
,
Mann
,
L.
and
Wearing
,
A.
(
2010
), “
Leadership and trust: their effect on knowledge sharing and team performance
”,
Management Learning
, Vol. 
41
No. 
4
, pp. 
473
-
491
, doi: .
Loch
,
C.
,
Mähring
,
M.
and
Sommer
,
S.
(
2017
), “
Supervising projects you don’t (fully) understand
”,
California Management Review
, Vol. 
59
No. 
2
, pp. 
45
-
67
, doi: .
McGrath
,
S.K.
and
Whitty
,
S.J.
(
2017
), “
Stakeholder defined
”,
International Journal of Managing Projects in Business
, Vol. 
10
No. 
4
, pp. 
721
-
748
, doi: .
McGrath
,
S.K.
and
Whitty
,
S.J.
(
2018
), “
Do steering committees really steer?
”,
International Journal of Managing Projects in Business
, Vol. 
12
No. 
3
, pp. 
785
-
807
, doi: .
McGrath
,
S.K.
and
Whitty
,
S.J.
(
2020
), “
What do project management practitioners think governance is? A study on perceptions in Queensland, Australia
”,
International Journal of Managing Projects in Business
, Vol. 
13
No. 
5
, pp. 
961
-
980
, doi: .
Merriam-Webster Incorporated
(
2025
), “
Dictionary
”,
available at:
 https://www.merriam-webster.com/dictionary/.
Michie
,
S.G.
,
Dooley
,
R.S.
and
Fryxell
,
G.E.
(
2006
), “
Unified diversity in top level teams
”,
International Journal of Organizational Analysis: Enhancing Collaboration and Quality in Strategic Decision‐Making
, Vol. 
14
No. 
2
, pp. 
130
-
1499
, doi: .
Miller
,
R.
and
Lessard
,
D.R.
(
2000
),
The Strategic Management of Large Engineering Projects: Shaping Institutions, Risks, and Governance
,
Massachusetts Institute of Technology
.
Müller
,
R.
,
Pemsel
,
S.
and
Shao
,
J.
(
2015
), “
Organizational enablers for project governance and governmentality in project-based organizations
”,
International Journal of Project Management
, Vol. 
33
No. 
4
, pp. 
839
-
851
, doi: .
Müller
,
R.
,
Shao
,
J.
and
Pemsel
,
S.
(
2016
),
Organizational Enablers for Project Governance
,
Project Management Institute
.
Müller
,
R.
,
Zhai
,
L.
and
Wang
,
A.
(
2017
), “
Governance and governmentality in projects: profiles and relationships with success
”,
International Journal of Project Management
, Vol. 
35
No. 
3
, pp. 
378
-
392
, doi: .
Murphy
,
K.
(
2016
),
A Theory of Steering Committee Capabilities for Implementing Enterprise-wide Information Systems
,
Case Western Reserve University
.
Murphy
,
K.
,
Lyytinen
,
K.
and
Somers
,
T.M.
(
2018
), “
A socio-technical model for project-based executive IT governance
”,
Proceedings of the 51st Hawaii International Conference on System Sciences
.
Musawir
,
A.U.
,
Serra
,
C.E.M.
,
Zwikael
,
O.
and
Ali
,
I.
(
2017
), “
Project governance, benefit management, and project success: towards a framework for supporting organizational strategy implementation
”,
International Journal of Project Management
, Vol. 
35
No. 
8
, pp. 
1658
-
1672
, doi: .
Musawir
,
A.U.
,
Mohd-Danuri
,
M.S.
and
Abd-Karim
,
S.B.
(
2023
), “
Making sense of project governance and its role in strategy implementation: a governance-as-practice perspective
”,
International Journal of Managing Projects in Business
, Vol. 
17
No. 
1
, pp. 
50
-
76
, doi: .
OECD
(
2016
), “
G20/OECD principles of corporate governance
”, doi: .
Pitsis
,
T.S.
,
Sankaran
,
S.
,
Gudergan
,
S.
and
Clegg
,
S.R.
(
2014
), “
Governing projects under complexity: theory and practice in project management
”,
International Journal of Project Management
, Vol. 
32
No. 
8
, pp. 
1285
-
1290
, doi: .
Podsakoff
,
P.M.
,
MacKenzie
,
S.B.
,
Lee
,
J.Y.
and
Podsakoff
,
N.P.
(
2003
), “
Common method biases in behavioral research: a critical review of the literature and recommended remedies
”,
Journal of Applied Psychology
, Vol. 
88
No. 
5
, pp. 
879
-
903
, doi: .
Project Management Institute
(
2016
),
Governance of Portfolios, Programs, and Projects: a Practice Guide
,
Project Management Institute
.
Qualtrics
,
P.
(
2023
), “
UT, USA
”,
Qualtrics
,
available at:
 https://www.qualtrics.com.
R Core Team
(
2022
),
R: a Language and Environment for Statistical Computing
,
R Foundation for Statistical Computing
.
Sankaran
,
S.
,
Drouin
,
N.
and
Locatelli
,
G.
(
2025
), “
Special issue: project governance: reflections on the past and suggestions for the future
”,
Project Management Journal
, Vol. 
56
No. 
1
, pp. 
3
-
14
, doi: .
Schippers
,
M.C.
and
Rus
,
D.C.
(
2021
), “
Majority decision-making works best under conditions of leadership ambiguity and shared task representations
”,
Frontiers in Psychology
, Vol. 
12
, pp. 
1
-
16
, doi: .
Simons
,
T.L.
and
Peterson
,
R.S.
(
2000
), “
Task conflict and relationship conflict in top management teams: the pivotal role of intragroup trust
”,
Journal of Applied Psychology
, Vol. 
85
No. 
1
, pp. 
102
-
111
, doi: .
Somers
,
T.M.
and
Nelson
,
K.G.
(
2001
), “
The impact of critical success factors across the stages of enterprise resource planning implementations
”,
Proceedings of the Hawaii International Conference on System Sciences
.
Stewart
,
V.R.
,
Snyder
,
D.G.
and
Kou
,
C.Y.
(
2023
), “
We hold ourselves accountable: a relational view of team accountability
”,
Journal of Business Ethics
, Vol. 
183
No. 
3
, pp. 
691
-
712
, doi: .
Stoppels
,
J.
,
Bosch-Rekveldt
,
M.
,
Mooi
,
H.
and
Bakker
,
H.L.M.
(
2023
), “
Exploring current practice in the formation and functioning of project steering committees
”,
The Journal of Modern Project Management
, Vol. 
11
No. 
2
, pp.
59
-
77
, doi: .
Stoppels
,
J.
,
Bosch-Rekveldt
,
M.
,
Mooi
,
H.
and
Bakker
,
H.L.M.
(
2025
), “
Roles and responsibilities in project steering committees
”,
Project Management Journal
, doi: .
Too
,
E.G.
and
Weaver
,
P.
(
2014
), “
The management of project management: a conceptual framework for project governance
”,
International Journal of Project Management
, Vol. 
32
No. 
8
, pp. 
1382
-
1394
, doi: .
Turner
,
J.R.
(
2020
), “
How does governance influence decision making on projects and in project-based organizations?
”,
Project Management Journal
, Vol. 
51
No. 
6
, pp. 
670
-
684
, doi: .
Turner
,
J.R.
(
2025
), “
How good governance leads to better project performance through improved decision-making
”,
International Journal of Managing Projects in Business
, Vol. 
18
No. 
2
, pp. 
434
-
452
, doi: .
Van de Ven
,
A.H.
(
2007
),
Engaged Scholarship: a Guide for Organizational and Social Research
,
Oxford University Press
.
Wang
,
L.
,
Wang
,
X.
and
Liu
,
X.
(
2024
), “
Project governance and governance of interorganizational project networks: toward understanding their relationships and future research agenda
”,
Project Management Journal
, Vol. 
56
No. 
1
, pp. 
31
-
40
, doi: .
Wit
,
F.R.D.
,
Greer
,
L.L.
and
Jehn
,
K.A.
(
2012
), “
The paradox of intragroup conflict: a meta-analysis
”,
Journal of Applied Psychology
, Vol. 
97
No. 
2
, pp. 
360
-
390
, doi: .
Zwikael
,
O.
and
Meredith
,
J.R.
(
2018
), “
Who’s who in the project zoo? The ten core project roles
”,
International Journal of Operations and Production Management
, Vol. 
38
No. 
2
, pp. 
474
-
492
, doi: .
Zwikael
,
O.
and
Meredith
,
J.
(
2021
), “
Evaluating the success of a project and the performance of its leaders
”,
IEEE Transactions on Engineering Management
, Vol. 
68
No. 
6
, pp. 
1745
-
1757
, doi: .
Zwikael
,
O.
and
Smyrk
,
J.
(
2015
), “
Project governance: balancing control and trust in dealing with risk
”,
International Journal of Project Management
, Vol. 
33
No. 
4
, pp. 
852
-
862
, doi: .
Zwikael
,
O.
and
Smyrk
,
J.
(
2019
),
Project Management: a Benefit Realisation Approach
,
Springer
.
Zwikael
,
O.
,
Meredith
,
J.R.
and
Smyrk
,
J.
(
2019
), “
The responsibilities of the project owner in benefits realization
”,
International Journal of Operations and Production Management
, Vol. 
39
No. 
4
, pp. 
503
-
524
, doi: .
Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) license. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at Link to the terms of the CC BY 4.0 licence.

Supplementary data

or Create an Account

Close Modal
Close Modal