In October 2004 the Environment Agency became the enforcement authority for the Reservoirs Act 1975 (the Act) in England and Wales. Since the Environment Agency took on this role, the authors have been considering the changes to the Act they would like to see incorporated. The Environment Agency's initial proposals were published in the last biennial report to the Department for the Environment Food and Rural Affairs (Defra) and the Welsh Assembly Government (WAG). Latest recommendations for changes to the Act follow the publication of the Pitt Review of the 2007 summer floods. Recommendation 58 of Sir Michael Pitt's review stated that ‘The Government should implement the legislative changes proposed in the Environment Agency's biennial report on dam and reservoir safety through the forthcoming flooding legislation.’ The key change proposed by the authors is to introduce a risk-based approach that would determine which reservoirs should come under the Act, instead of the current 25 000 m3 threshold. This paper describes the various proposals in more detail and outlines the potential programme for including these changes in the forthcoming Floods and Water Bill.
Article navigation
June 2009
Research Article|
June 01 2009
Reservoirs Act 1975—Environment Agency proposals for change
Liana J Hamilton-King, BSc;
Liana J Hamilton-King, BSc
1
Environment Agency
Exeter, UK
Search for other works by this author on:
Ian M Hope, BSc, MA, CEng, FICE
Ian M Hope, BSc, MA, CEng, FICE
2
Environment Agency
Exeter, UK
Search for other works by this author on:
Publisher: Emerald Publishing
Online ISSN: 1756-8404
Print ISSN: 1368-1494
© 2009 Thomas Telford
2009
Dams and Reservoirs (2009) 19 (2): 49–54.
Citation
Hamilton-King LJ, Hope IM (2009), "Reservoirs Act 1975—Environment Agency proposals for change". Dams and Reservoirs, Vol. 19 No. 2 pp. 49–54, doi: https://doi.org/10.1680/dare.2009.19.2.49
Download citation file:
134
Views
New and popular articles
Suggested Reading
ICE Reservoirs Committee's advice on applications for appointment and reappointment as a panel engineer
Dams and Reservoirs (September,2009)
Behaviour of dams in the Wenchuan earthquake
Dams and Reservoirs (September,2009)
Meeting report: Summary of ICOLD committee meetings held in Seattle – August 2013
Dams and Reservoirs (June,2013)
Meeting report: BDS supervising engineers’ forum 2013 – post-event analysis
Dams and Reservoirs (June,2013)
Technical visit: Black Esk reservoir enlargement
Dams and Reservoirs (June,2013)
Related Chapters
Earth and tailings dams
ICE Handbook of Geosynthetic Engineering: Geosynthetics and their applications
Containment ponds, reservoirs and canals
ICE Handbook of Geosynthetic Engineering: Geosynthetics and their applications
Postscript
Operational Safety of Dams and Reservoirs: Understanding the reliability of flow-control systems
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.