Thames Water owns a large number of non-impounding reservoirs. These have unusually long embankments with narrow clay cores and gravel shoulders, which could be susceptible to piping failure and erosion. They are typically located in urban areas. Thames Water has therefore reviewed its policy regarding emergency draw down capacity and started an improvement programme on the most critical reservoirs. The Queen Mary and King George V reservoirs are two of these critical non-impounding reservoirs with continuous embankment lengths of 6·3 km and 6·5 km and storage volumes of 30 Mm3 and 12 Mm3 respectively. Following the statutory inspection of these reservoirs, a safety recommendation was made that required a significant increase to the existing emergency draw down capacity of each reservoir. This required Queen Mary reservoir to achieve 0·75 m emergency draw down from top water level within 24 h and King George V reservoir to achieve 1 m draw down in 24 h. Studies instigated as a result looked at various options of achieving the draw down, with the final solution involving the design and construction of twin siphon pipes fitted with submerged discharge valves. It is believed that a number of UK reservoirs may require additional emergency draw down capacity over the next few years, as measures in the interest of safety, defined within the terms of the Reservoirs Act 1975. This paper looks at the options considered before arriving at the final solution and discusses challenges in the design and construction of the schemes.
Article navigation
June 2009
Research Article|
June 01 2009
Queen Mary and King George V emergency draw down schemes Available to Purchase
Bryn Philpott, CEng, MICE, MCIWEM;
Bryn Philpott, CEng, MICE, MCIWEM
1
Senior Reservoir Engineer, Thames Water, Middlesex, UK
Search for other works by this author on:
Yinka Oyeyemi, MSc, CEng, MICE;
Yinka Oyeyemi, MSc, CEng, MICE
2
Senior Engineer, Halcrow International Partnership, Dubai, formerly Jacobs, UK
Search for other works by this author on:
John Sawyer, MA, MBA, CEng, FICE
John Sawyer, MA, MBA, CEng, FICE
3
Engineering Manager, Ingula Project, Eskom, KZN, South Africa, formerly Jacobs, UK
Search for other works by this author on:
Publisher: Emerald Publishing
Online ISSN: 1756-8404
Print ISSN: 1368-1494
© 2009 Thomas Telford
2009
Dams and Reservoirs (2009) 19 (2): 79–84.
Citation
Philpott B, Oyeyemi Y, Sawyer J (2009), "Queen Mary and King George V emergency draw down schemes". Dams and Reservoirs, Vol. 19 No. 2 pp. 79–84, doi: https://doi.org/10.1680/dare.2009.19.2.79
Download citation file:
Suggested Reading
News: Honorary life membership for Michael Kennard, Andrew Charles, Iain Moffat and Paul Tedd
Dams and Reservoirs (September,2013)
BDS Corporate Members
Dams and Reservoirs (September,2013)
Behaviour of dams in the Wenchuan earthquake
Dams and Reservoirs (September,2009)
ICOLD European club symposium 2010 – a student's viewpoint
Dams and Reservoirs (December,2010)
Hydropower and panel engineers – a lasting legacy. Part 111th Binnie lecture
Dams and Reservoirs (December,2010)
Related Chapters
CONTENTS AND PRELIMINARY PAGES
Dams: Engineering in a Social and Environmental Context
Reservoir safety: what do we mean?
Dams: Engineering in a Social and Environmental Context
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.
