Many disputes arise on engineering and construction contracts due to the risks that are inherent in the realisation of complex projects in challenging environments. While contracts encourage collaboration between parties, the commercial consequences of managing risk and uncertainty can create tension. This paper reflects some of the authors’ experience of the use of programmes in international construction contracts. It identifies some of the issues that arise from integrating the rights and obligations set out in contract conditions with time, cost and risk management activities. It highlights the challenges that face project funders, contract administrators, project managers, designers, contractors and their suppliers in planning and reporting on the progress achieved in their project. This paper illustrates the tension between the commercial consequences of risk and transparency of contractor performance. It discusses how issues can arise that reduce the effectiveness of the programme as a collaborative management tool. It also proposes how some of these issues can be guarded against when establishing the contracting environment and in the subsequent administration of the contract.
Article navigation
1 December 2015
Research Article|
October 14 2015
The use and abuse of programmes in construction contracts
Andrew Kidd, MEng, MA(Cantab), CEng MICE, MInstRE, MAPM;
Andrew Kidd, MEng, MA(Cantab), CEng MICE, MInstRE, MAPM
Manager, Capital Project Advisor
PwC, London, UK
Search for other works by this author on:
Stuart Appelbe, BEng, CEng MICE, MAPM;
Stuart Appelbe, BEng, CEng MICE, MAPM
Director, Head of Construction Disputes
PwC, London, UK
Search for other works by this author on:
Anthony Morgan, BSc(Eng) hons, FICE MCIArb
Anthony Morgan, BSc(Eng) hons, FICE MCIArb
Partner, Experienced Delay Expert Witness
PwC, London, UK
Search for other works by this author on:
Publisher: Emerald Publishing
Received:
October 31 2014
Accepted:
June 09 2015
Online ISSN: 1751-4312
Print ISSN: 1751-4304
ICE Publishing: All rights reserved
2015
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (2015) 168 (6): 294–301.
Article history
Received:
October 31 2014
Accepted:
June 09 2015
Citation
Kidd A, Appelbe S, Morgan A (2015), "The use and abuse of programmes in construction contracts". Proceedings of the Institution of Civil Engineers - Management, Procurement and Law, Vol. 168 No. 6 pp. 294–301, doi: https://doi.org/10.1680/jmapl.14.00044
Download citation file:
Suggested Reading
Time for the UK construction industry to become Lean
Proceedings of the Institution of Civil Engineers - Civil Engineering (May,2012)
Managing a programme under the NEC3 ECC contract
Proceedings of the Institution of Civil Engineers - Management, Procurement and Law (August,2010)
Briefing: Participation, consensus and adjudication in designing the A3 Hindhead tunnel, UK
Proceedings of the Institution of Civil Engineers - Engineering Sustainability (April,2013)
The fate of medieval English bridges since 1770: demolition, survival and preservation
Proceedings of the Institution of Civil Engineers - Engineering History and Heritage (February,2013)
Can carbon dioxide storage site qualification help meet a 2015 deadline?
Proceedings of the Institution of Civil Engineers - Energy (May,2012)
Related Chapters
Case studies
Programme Management in Construction
The Role of Operations in a Mega Project
Crossrail Project: Infrastructure Design and Construction
Civil engineering projects
Civil Engineering Procedure
Recommended for you
These recommendations are informed by your reading behaviors and indicated interests.