Skip to Main Content
Purpose

The energy performance gap (EPG) in building construction has been one of the major barriers to the realization of environmental and economic sustainability in the built environment. Although there have been a few studies addressing this issue, studying this topic with a special focus on the project delivery process has been almost overlooked. Hence, this study aims to address the EPG in building construction through the lens of collaborative and life cycle-based project delivery.

Design/methodology/approach

In order to realize the objective of this study, the development of a theoretical framework based on the literature review was followed by a qualitative study in which 21 semi-structured interviews were conducted with Finnish project professionals representing clients, design/planning experts, constructors and building operation/maintenance experts to explore their views on the topic under study.

Findings

The findings reveal the project delivery-related causes of EPG in building construction. Moreover, the obtained results present a collaborative and life cycle-based delivery model that integrates project and product (i.e. building) life cycles, and it is compatible with all types of contractual frameworks in building construction projects.

Research limitations/implications

Although the findings of this study significantly contribute to theory and practice in the field of collaborative and sustainable construction project delivery, it is acknowledged that these findings are based on Finnish professionals’ input, and expanding this research to other regions is a potential area for further studies. Moreover, the developed model, although validated in Finland, needs to be tested in a broader context as well to gain wider generalizability.

Originality/value

The obtained results reveal the significance and impact of collaborative and life cycle-based project development and delivery on the realization of environmentally sustainable building construction.

Buildings, in general, consume a striking amount of energy, accounting almost to 40% of the whole energy consumption in the world (Laconte and Gossop, 2016). This huge consumption profiles buildings as one of the main areas under focus for further research and development. Consequently, sustainable development goals (SDGs), outlined by United Nations, to a high extend apply to construction industry and, in particular, building construction projects. This high-level recognition has resulted in extensive research on the energy efficiency of building construction and renovation. Regarding building construction, there have been significant advancements (e.g. building information modeling, geothermal energy system), and subsequently the enhanced design expertise and capability in the past decade has aimed for high efficiency or even net-zero energy buildings, in which the amount of consumed and produced energy (i.e. electricity) are even. Although there have been some successes in the construction of highly energy efficient or net-zero-energy buildings in some of the developed countries (e.g. USA) (Kibert, 2016), many of newly constructed buildings have been still struggling to achieve the energy efficiency targets, developed in the design phase. This phenomenon is called energy performance gap (EPG) (Laconte and Gossop, 2016).

Energy performance gap has been one of the major barriers for the realization of environmental and economic sustainability in the built environment. Looking at the definition of EPG, it basically refers to one or more factors in the project life cycle and probably in the commissioning phase of the constructed building, which hinders the efficient performance of the building in terms of energy consumption. In this regard, studies addressing the barriers and enables of the EPG in building construction (e.g. Häkkinen and Belloni, 2011; Li and Yao, 2012; Moradi et al., 2023; Qian et al., 2015) have found that factors such as collaboration between parties, early involvement of key participants, designer’s competence and integrating project delivery contribute toward solving the performance gap issue. These findings imply project delivery model’s prominent role in filling the EPG because it accounts for the successful accomplishment of building construction projects. In this regard, there have been very few, if any, studies, employing collaborative project delivery as a theoretical lens for looking into the EPG issue. An important point to note is that the project delivery model’s impact is not limited to the project life cycle; it also considerably affects the completed building’s operational life cycle and the realization of energy efficiency goals. Thus, construction project delivery model needs to be collaborative and inclusive in terms of covering both project and product (i.e. building) life cycle.

However, the existing construction project delivery models mostly address project life cycle and almost avoid completed building’s operation period. This is not a surprise as the terminology highlights the focus of the delivery model on the project only and not the product (i.e. constructed building). Consequently, the project parties are not usually held accountable in terms of their responsibility for the performance of the constructed building. This is particularly important for three reasons. First, the research shows that a completed building’s operating costs in its operational life cycle can be even higher than its construction costs (Mike et al., 2015). Second, realizing sustainable built environment is highly dependent on the actual performance of the buildings in terms of energy efficiency, not the design intentions. And third, actual performance of the building can be seen only in the operation phase. Hence, it seems that project and product life cycle and management are interconnected and need to be integrated in the context of building construction. Thus, further developments and improvements are needed.

In this regard, it is necessary to acknowledge that construction project delivery models have evolved significantly over the past 30 years. In the big picture, the mainstream typology of project delivery models divides them into three categories of traditional, collaborative, hybrid (Moradi et al., 2022). Traditional delivery models in construction projects refer to design-bid-build, design-build and different types of construction management (e.g. Construction Management (CM) and CM at Risk) (Forbes and Ahmed, 2010). In other words, the terminology associated with traditional delivery models comes from the name of the contract type used in those delivery models. The same logic somewhat applies to the collaborative delivery models which include alliance, partnering, lean project delivery (LPD) and integrated project delivery (IPD) (Engebø et al., 2020; Lähdenpera, 2012; Mesa et al., 2019). The hybrid category refers to those project delivery models which employ traditional contract but also take advantage of collaborative working practices like co-location of the project participants (Darrington, 2011; Moradi et al., 2021a). Traditional delivery models are usually characterized by adversarial relationships, mistrust, unfair share of risk-reward, working in silos and dominance of low prince criteria for contractor selection. Conversely, collaborative delivery models feature early involvement of key participants; joint design, planning, control and decision making; open book cost management; aligned interests of stakeholders, continuous learning, fair share of risk-reward; open communication; and trust-based relationships (Moradi et al., 2021b).

The emergence of collaborative delivery models has had a significant impact on the performance results of construction projects (e.g. Hanna, 2016; Ibrahim et al., 2020). However, there are still two problematic issues left. The first one is the fact that traditional project delivery models are still dominant in many developing and developed countries and these countries are struggling to realize productive and sustainable building construction. The second issue is that even in collaborative project delivery models the shared risk-reward mechanism applies to the project life cycle and therefore the completed building’s operational life cycle is taken into account in a limited manner. Thus, it is imperative to discover a solution for overcoming the mentioned challenges. Such solution could be developing a delivery model which is compatible with various contractual frameworks and tendering process in building construction projects and covers constructed building’s life cycle. This study aims to realize this solution in order to the fill the mentioned knowledge gap and enable the realization of productive building construction and sustainable built environment in practice. Accordingly, this study’s objective is to answer the following research questions:

RQ1.

What are the project delivery-related barriers and solutions which affect the realization of energy efficiency targets in the operation phase of the constructed buildings?

RQ2.

What kind of model can enable collaborative and life cycle-based delivery of building construction projects for filling the EPG?

The resultant article is structured in six sections, including the introduction, theoretical background, methodology, results, discussion and conclusions.

When the measured (or actual) energy consumption of buildings differs from the expected energy consumption, the building is said to have an EPG (Zou et al., 2018). This can mean the difference between simulated and measured energy performance or the difference between targets set by specifications or standards vs the measured performance. The EPG may exist may be observed in existing building as well as in retrofitting and new construction projects (Mahdavi et al., 2021). In Europe, building energy efficiency is typically measured through the energy efficiency classification from A to G. While the EPG is typically mentioned in the context of higher-than-expected energy consumption, the gap may exist in either direction. For example, in the Swiss residential building stock buildings of low energy classification generally consume significantly less energy than assumed, while buildings of higher energy efficiency class tend to consume slightly more energy than expected (Cozza et al., 2020). However, Laconte and Gossop (2016) refer to cases where buildings are consuming as much as two or three times the designed energy. The EPG is also related to other types of building performance gaps, like issues with operations and indoor conditions (Rasmussen and Jensen, 2020). Frei et al. (2017) noted that the EPG can arise in three life cycle phases of the building: (1) design and planning (poor early design decisions, uncertainty in energy modeling, oversizing of systems), (2) construction and commissioning (economy over design, poor commissioning) and (3) operation (equipment issues, user interaction and change of building purpose). Boge et al. (2018) especially highlighted the role of early-phase planning. Saving money by not investing enough in the early stage may result in costly remedies in the operational stage and sometimes even permanent problems that cannot be fixed.

In the operational phase of the building, facility managers have a significant role. Borgstein et al. (2018) found that energy performance issues relate to poor management and improper operation of systems. Insufficient energy performance guidelines and poor documentation can result in a lack of proper setpoints or high night-time loads. Floor plans with too large control zones for equipment also prevent correct operation of building automation systems. Facility managers from the USA report that the main reasons for the EPG are (1) higher than expected use of energy by the occupants, (2) there being more than the designed number of occupants and (3) technology failures (Liang et al., 2019). Facility managers are in principle expected to continually improve energy efficiency in buildings, but are not actually required or incentivized to do so. In fact, some facility managers actively avoid trying to fix issues so as not be held responsible for possible worsening of the gap, referring to unavoidable differences between theory and practice (Willan et al., 2020). Fears of causing disturbances in building operations and unfamiliarity with data-driven tools prevent the use of data-based recommendations (Markus et al., 2022). However, it can be argued that continual energy performance improvement should be a key role for facility managers. This role should be started early on, while planning and construction is still taking place (Boge et al., 2018). While the complexity of modern building services technology can be a cause of the EPG, new technologies may also offer a solution. For example, machine learning can be used to predict EPG based on risk data. This allows the project participants to react to potential energy performance issues early on, before final decisions are made (Yılmaz et al., 2023).

Building construction projects go through different phases which include definition, design, planning, construction, closure and handover. This process is usually called project delivery model which is also known as project delivery method or project delivery system. In this article, the term project delivery model is utilized. Project delivery model, according to Mesa et al. (2019), has three defining elements which are project organization, operational system and contractual relationships. Although the mentioned elements by Mesa et al. (2019) are inclusive, they seem to be missing an important piece which is the delivery process, referring to the steps and activities encompassing project and/or building life cycle and the involved people in each phase. If the delivery process is added to this collection, a new framework can be developed for defining project delivery model. This framework is shown in Figure 1. This theoretical foundation is of prime importance as the authors’ have often observed in the literature and practice that a certain contract type or operational system or project organization is called as project delivery model whereas all the defining elements shown in Figure 1 need to be in place to have a construction project delivery model.

According to Moradi et al. (2022), “Collaborative delivery model is one of the umbrella terms which has been utilized by different scholars in reference to alliance, partnering, integrated project delivery, and lean project delivery.” In terms of typology, according to Engebø et al. (2020), Mesa et al. (2019) and Lähdenpera (2012), it can be argued that partnering, alliance, IPD and LPD are the pure collaborative project delivery models. However, this study aims to provide an in-depth conceptualization of collaborative project delivery model in construction. To do so, if the framework shown in Figure 1 combined with the features of collaborative delivery models (mentioned earlier in the introduction), the result would be something like Figure 2, which provides a new framework for defining/distinguishing collaborative project delivery model in construction. The framework, shown in Figure 2, is consisted of two main elements. The first element is the defining factors of construction project delivery which include project organization, operational system, contractual framework and delivery process. And the second element is the relevant features of collaborative project delivery to the mentioned defining factors. For instance, the collaborative features related to project organization are trust-based relationships and join decision making.

Collaborative project delivery models have been extensively discussed in the recent review studies (e.g. Engebø et al., 2020; Moradi et al., 2022), and this study neither has aim to repeat those discussions in different words, nor it fits to the scope of this article. Instead, an abstract level analysis of the major studied themes is presented in Figure 3.

As can be seen, success factors and barriers is the only common theme among the conducted research on alliance, partnering, LPD and IPD. The study conducted by Moradi and Kähkönen (2022) has identified commonalities between success factors of collaborative delivery models. Among the research themes shown in Figure 3, success factors, trust and working relationship and team integration are the most relevant topics to the scope of this article. Hence, the findings of the studies representing those themes have been summarized and are shown in Table 1.

Collaborative project delivery models emerged, mainly, as a response and reaction to the five common challenges in traditional construction projects. These challenges include accident-free construction, reliability of planning, constructability of design, adversarial working relationships and dominance of low price for selecting the contractor (Forbes and Ahmed, 2010; Oakland and Marosszeky, 2017). The research shows that collaborative delivery models have had promising results in overcoming those challenges (e.g. Ibrahim et al., 2020).

However, while the building code sets requirements for building energy consumption and developers set their own energy performance targets, a pitfall in both traditional and collaborative delivery models has been lackluster enforcement of these targets over the building’s operational life cycle. Malfunctioning or inadequately calibrated systems due to lacking construction processes can often result in higher-than-expected energy consumption – an EPG. This gap is of prime importance for realizing sustainability goals, in particular environmental sustainability (energy efficiency and emission), as buildings account for almost 40% of global energy consumption (Laconte and Gossop, 2016).

This becomes even more important if it is noted that there is usually a considerable EPG in building construction projects in terms of the discrepancy between design intentions and actual energy consumption of the building (Laconte and Gossop, 2016). In this regard, the project delivery model seems to have a big role in this EPG. Thus, studying sustainable and collaborative project delivery for building construction with a life cycle perspective is a major research gap which needs to be addressed. Hence, this study aims to do so through developing a conceptual framework (see Figure 4), identifying the causes of EPG associated with the project delivery and validating the developed framework to be resulted in the development of a state-of-the-art delivery model which can enable the realization of productive building construction and sustainable built environment in practice.

This study aims to address the EPG in building construction through the lens of project delivery model. To do so, the research process started with formulating the following research questions:

  • What are the challenges/barriers of achieving energy efficiency in building construction projects which are related to project delivery process?

  • What kind of project delivery model could contribute toward filling the EPG in building construction projects?

Due to the adequacy of literature on the addressed topic in this study, the deductive approach was adopted (Saunders et al., 2019). Accordingly, literature study and semi-structured interviews were selected as the data collection methods and thematic as well as content analysis as the data analysis methods. These choices were justified with regard to the exploratory purpose of the research (Saunders et al., 2019). The next step in the research design was to determine the context of study and make a choice about the sampling method. To do so, building construction and renovation projects was selected as the focus of the study. In terms of the building type (construction category), residential buildings, institutional buildings (i.e. school and hospital) and commercial buildings (i.e. shopping mall and office building) were included in the scope of the study.

Concerning sampling method, a combination of quota sampling and purposive sampling method (Saunders et al., 2019) was utilized in this study through which four groups of interviewees were specified by the research team. These interviewee groups included (1) client project manager, (2) contractor project manager, (3) design manager and (4) property management (i.e. building operation and maintenance) experts. The research team targeted at least five interviewees in each group with a provision to conduct more interviews in each group if data saturation was not achieved (Saunders et al., 2019). Then, the research team filled each quota by intentionally choosing relevant individuals (i.e. interviewees) in the possession of relevant knowledge and experiences related to the quota and the research topic. The defined interviewee groups in this study provided a basis for life cycle-based and inclusive study of performance gap through the lens of project delivery process based on the input from key project participants in different phases of project life cycle. The life-perspective in data collection was imperative due to the diversity of disciplines involved in the design, construction and operation of a building.

Data collection started with formulating the protocol and questions of the semi-structured interviews. The developed questions aimed to the explore the project delivery-related causes behind the EPG in building construction projects based on the viewpoints of key project participants involved in different phases of project life cycle. The developed interview protocol and questions was piloted in the first four interviews (one interview in each interviewee group) to seek feedback from the interviewees. Since there was neither negative feedback nor any changes in the interview protocol and questions, the first four interviews, which had been conducted with piloting purpose, were also considered valid to be analyzed in the data analysis stage.

In the next step, the research team conducted 21 semi-structured interviews in Finland with project professionals representing client, design/planning experts, contractors and building operation/maintenance experts. Since data saturation was achieved in each interviewee group, there was no need for conducting additional interviews (Saunders et al., 2019). The conducted interviews were audio recorded based on the obtained consent from the interviewees. Then they were transcribed and translated to English language by the native Finnish speaking member of the research team. Table 2 shows interviewees’ discipline, role and their latest project’s type, budget and duration. In addition, Figure 5 shows the demographic information of the interviewees.

The analysis process started with thematic analysis which was performed by inductively coding the extracted research data as a result of analyzing the interview transcripts. The labels of the codes were data derived by the researcher (Saunders et al., 2019). Validating the generated codes was accomplished through reviewing them three times (each time by one member of the research team) and making the required corrections. The validated codes representing project delivery were formed a theme titled “project delivery.” The establishment of the themes was done based on the sameness or similarity of the codes in terms of the meaning and/or title. Then, a content analysis was performed through which the challenges/barriers and solutions/enablers in the established themes were listed and synthesized based on the similarity or sameness of the title and/or meaning. Finally, the cross validation was carried out through showing the results of thematic and content analysis to the interviewees to ensure the interpretations made in the analysis process were valid. All the interviewees approved the results of thematic and content analysis.

Following the cross validation, the identified barriers and enablers together provided a basis for modifying the developed conceptual framework (Figure 4) in the literature study and developing a collaborative and life cycle-based delivery model for sustainable building construction. The developed model was validated in two steps. The first step of the validation included two case studies in which the modified model was shown to the project managers of one successful and one unsuccessful building construction project (in terms of energy efficiency and on time and on budget completion) to seek their feedback. The obtained feedback from the case projects was then applied, and the developed delivery model was validated.

Analyzing the conducted interviews resulted in the identification of several barriers and solutions for achieving energy efficiency in building construction projects (see  Appendix). Among them, some were frequently mentioned by the interviewees, which are shown in Table 3. As the barriers and enablers implies, the existing delivery models (both collaborative and traditional) ignore the building performance in its operational life cycle and lack sufficient strength for involving building services and maintenance experts in building design and construction phases. Moreover, limiting the contractor’s responsibility to the project life cycle causes fragmentation in the maintenance and optimization of building operation. Dominance of low-price criteria for tendering is another chronic problem which results in the selection of low-capacity contractors who fail to deliver the project efficiently and are incapable of taking responsibility for the building performance in its operational life cycle. Thus, collaborative and life cycle-based delivery model seems to be a viable solution for filling the EPG in building construction projects.

The literature study and obtained data provided a basis for the development of a collaborative and life cycle-based project delivery model (CLCPDM) for sustainable building construction. This model has two versions: (1) The abstract version, as can be seen in Figure 6, shows the main steps in the delivery of the project and operation of the building and the main output in each step, and (2) the detailed version also includes descriptions of what happens in each step (see Figure 7).

This model has two key differences with the existing delivery models in the literature. First, CLCPDM is inclusive and covers both project life cycle and operational life cycle of the constructed building. Second, it has a combined feature of both traditional and collaborative construction projects, thereby increasing its compatibility with both contexts. The second feature also combines the strengths of both collaborative and traditional delivery models and covers their weaknesses. In other words, it is new a generation of construction project delivery model with capability to realize productivity and sustainability in both project and product life cycle.

In short, the developed model:

  • Fully realizes the significance of proper project definition, feasibility study and competent as well as price-based contractor selection,

  • Involves the design team and contractor when they have the highest impact,

  • Features life cycle-based and collaborative project definition and design,

  • Treats essential design and planning as an iterative cycle to realize the required improvements,

  • Employs collaborative tools and working practices in design and construction phases and

  • prioritizes systematic and continuous documentation of project and building performance data.

Project delivery has been a mechanism for the successful completion of construction projects. The traditional model of this mechanism has not yielded satisfactory results most of the time, particularly in the complex projects, resulting in the over budget, waste, low quality, accident full and delayed delivery of building construction projects (e.g. Forbes and Ahmed, 2010; Moradi and Sormunen, 2023). Collaborative project delivery emerged to be an effective replacement, and it has had promising performance results (e.g. Hanna, 2016; Ibrahim et al., 2020). In spite of this advancement, building construction projects, to a high extent, are still struggling to meet the environmental sustainability goals; their actual energy consumption is considerably higher than expectations (e.g. Laconte and Gossop, 2016). Of course, there are several factors behind this EPG phenomenon one of which is project development and delivery process (Moradi and Sormunen, 2022). In fact, this factor happens to be a major cause of the EPG. In particular, the findings showed that inadequate and/or late involvement of key project participants (including building services people) together with fragmented project delivery and maintenance process and dominance of low-price criteria for contractor selection are the key barriers of achieving energy efficiency in building construction (Moradi et al., 2023). The identified enablers in this study were relevant to the barriers, which can be seen as an indication of the reliability of the obtained results.

The involvement issue can be explained as the missing impact which contractor as well as maintenance experts can have in the project definition and design stages. In other words, these people are a dynamic database of building performance data which can help the client and design team to first reasonably define the goals and then provide input for ensuring constructability of the design in the construction phase and functionality of building in its operation phase. The fragmented project delivery and maintenance exactly reflects on the discovered research gap in this study and its purpose, addressing the fact that project and product life cycle need to be integrated and the key people involved in project life cycle need to be involved and accountable in the product life cycle as well. Finally, the third issue, dominance of low-price criteria, has been a problem for a long time which results in the selection of low-capacity contractors which do not have the required resource and competence. Although collaborative delivery models (e.g. alliance, IPD) has removed this dominance and mostly consider the competency as the selection criteria, they are also missing an important point which is the reasonable price offered by the contractor. Thus, it seems that a mature contractor selection mechanism needs to take into account both tendering (based on a reasonable price range specified in the project definition) and contractor’s capacity (i.e. experience, knowledge, adequate financial resources, sufficient and competent workforce), as the competency criteria. The same selection logic must be also applied for employing the design team. The mentioned solutions in Table 3 concisely characterize the project delivery model, developed in this study, which can overcome the related barriers for achieving energy efficiency in building construction.

The obtained results in this study contribute to the existing body of knowledge in two aspects. First, the findings fill the knowledge gap on the role of project development and delivery in the EPG in building construction. To the best of the knowledge of the authors, this is the first study looking into the EPG in building construction through the lens of project development and delivery process. The second contribution is the development of a novel delivery model which features collaboration and life cycle perspective as its building blocks, and it is yet compatible with the traditional contracts and tendering processes. In other words, CLCPDM is the new generation of construction project delivery model which contributes toward productivity and sustainability achievement in both project and product (i.e. constructed building) life cycle.

From practical perspective, the discussed challenges and solutions together with the developed delivery model informs project professionals and clients on the project delivery related causes of EPG and then provide a practical solution for collaborative and life cycle-based project development and delivery. In particular, the model provides a practical guidance for clients on how to develop their project with a life cycle perspective over the benefits and loss resulting from different decisions. It also reveals the best time for involving the design team and contractor to benefit from their impact.

Although the main focus of the developed model (Figures 6 and 7) is on the delivery process, it still includes the application of relevant tools for measurement, simulation, monitoring and optimization purposes, but does not prescribe/recommend any specific tool. Such optimization could be performed with the help of a digital twin that allows the real-time comparison of actual energy performance to that predicted by simulations (Spudys et al., 2023). A digital twin might be created from building information modeling (BIM) data that are used in the design phase of the building. The combination of BIM and digital twins could also be used to expand the life cycle optimization to cover not only environmental, but also social and economic impacts (Boje et al., 2023). As more and more data from buildings becomes available, increasingly accurate prediction of building energy consumption can be made using machine learning methods (Miller et al., 2020). Artificial intelligence (AI)-based systems may be used to optimize various aspects of buildings, such as energy consumption, thermal comfort and lighting conditions, both in the design and operational phases of the building life cycle (Mousavi et al., 2023). Accordingly, there is a great potential for the continuous improvement of construction project delivery through the integration of dynamic digital tools like BIM and digital twins.

This study aimed at discovering the project delivery related barriers and solutions of realizing energy efficiency in building construction projects and to develop a collaborative and life cycle-based delivery model for sustainable building construction. This was accomplished through a literature review combined with a qualitative study involving semi-structured interviews. The opinion of project professionals representing client, design, contractor and property management (i.e. building operation and maintenance experts) were obtained and analyzed. Accordingly, it is concluded that:

  • The project delivery model considerably accounts for the success or failure of the realization of energy efficiency in building construction projects.

  • Involvement of building services experts and maintenance people in the project definition and design seem to enhance the constructability of the building services design and functionality of the building’s Heating, Ventilation, and Air conditioning (HVAC) system in the operation phase.

  • Project delivery contract should expand the responsibilities (including risk and reward) of project parties into the constructed building’s operational life cycle.

  • Collaborative and life cycle-based delivery model combines strengths of both traditional and collaborative delivery models’ and covers their weaknesses. The developed model in this study fulfills this purpose.

The obtained results in this study considerably contribute toward existing body of knowledge in two areas of EPG in building construction and collaborative project delivery. However, it is acknowledged that the findings are based on Finnish professionals’ input and expanding this research to other regions is a potential area for further research. Moreover, the developed model, although validated in Finland, needs to be tested in a broader context as well to increase its generalizability. Furthermore, it is also acknowledged that in this study the interviews were conducted with certain groups of professionals involved in project delivery process and building operation as well as maintenance, and including building users as the fifth groups of interviewees could have been value adding. Hence, obtaining building users’ input is suggested to be considered in the future relevant studies.

This study was financially supported by the “Hiilineutraalit energiaratkaisut ja lämpöpumpputeknologia” research project (No. 3122801074) at Tampere University in Finland. The funders of this research project are Tampereen korkeakoulusäätiö sr, Tampereen teknillisen yliopiston tukisäätiö sr / Paavo V. Suomisen rahasto, Sähkötekniikan ja energiatehokkuuden edistämiskeskus STEK ry, Granlund Oy, HUS Tilakeskus, HUS Kiinteistöt Oy, Senaatti- kiinteistöt, and Ramboll Finland Oy.

Data availability statement: The authors confirm that the data supporting the findings of this study are available within the article.

Aaltonen
,
K.
and
Turkulainen
,
V.
(
2018
), “
Creating relational capital through socialization in project alliances
”,
International Journal of Operations and Production Management
, Vol. 
38
No. 
6
, pp. 
1387
-
1421
, doi: .
Bellini
,
A.
,
Aarseth
,
W.
and
Hosseini
,
A.
(
2016
), “
Effective knowledge transfer in successful partnering projects
”,
Energy Procedia
, Vol. 
96
, pp. 
218
-
228
, doi: .
Boge
,
K.
,
Salaj
,
A.
,
Bjørberg
,
S.
and
Larssen
,
A.K.
(
2018
), “
Failing to plan – planning to fail: how early phase planning can improve buildings' lifetime value creation
”,
Facilities
, Vol. 
36
Nos
1/2
, pp. 
49
-
75
, doi: .
Boje
,
C.
,
Menacho
,
Á.J.H.
,
Marvuglia
,
A.
,
Benetto
,
E.
,
Kubicki
,
S.
,
Schaubroeck
,
T.
and
Gutiérrez
,
T.N.
(
2023
), “
A framework using BIM and digital twins in facilitating LCSA for buildings
”,
Journal of Building Engineering
, Vol. 
76
, 107232, doi: .
Borgstein
,
E.H.
,
Lamberts
,
R.
and
Hensen
,
J.L.M.
(
2018
), “
Mapping failures in energy and environmental performance of buildings
”,
Energy and Buildings
, Vol. 
158
, pp. 
476
-
485
, doi: .
Chan
,
A.P.
,
Chan
,
D.W.
,
Chiang
,
Y.H.
,
Tang
,
B.S.
,
Chan
,
E.H.
and
Ho
,
K.S.
(
2004a
), “
Exploring critical success factors for partnering in construction projects
”,
Journal of Construction Engineering and Management
, Vol. 
130
No. 
2
, pp. 
188
-
198
, doi: .
Chan
,
A.P.
,
Scott
,
D.
and
Chan
,
A.P.
(
2004b
), “
Factors affecting the success of a construction project
”,
Journal of Construction Engineering and Management
, Vol. 
130
No. 
1
, pp. 
153
-
155
, doi: .
Cheng
,
E.W.
and
Li
,
H.
(
2004
), “
Development of a practical model of partnering for construction projects
”,
Journal of Construction Engineering and Management
, Vol. 
130
No. 
6
, pp. 
790
-
798
, doi: .
Cho
,
K.
,
Hyun
,
C.
,
Koo
,
K.
and
Hong
,
T.
(
2010
), “
Partnering process model for public-sector fast-track design-build projects in Korea
”,
Journal of Management in Engineering
, Vol. 
26
No. 
1
, pp. 
19
-
29
, doi: .
Cozza
,
S.
,
Chambers
,
J.
and
Patel
,
M.K.
(
2020
), “
Measuring the thermal energy performance gap of labelled residential buildings in Switzerland
”,
Energy Policy
, Vol. 
137
, 111085, doi: .
Darrington
,
J.
(
2011
), “
Using a design-build contract for lean integrated project delivery
”,
Lean Construction Journal
, pp. 
85
-
91
,
available at:
 https://lean-construction-gcs.storage.googleapis.com/wp-content/uploads/2022/08/08161000/Design-build_contract_for_Lean_IPD.pdf
Drexler
,
J.A.
, Jr.
and
Larson
,
E.W.
(
2000
), “
Partnering: why project owner-contractor relationships change
”,
Journal of Construction Engineering and Management
, Vol. 
126
No. 
4
, pp. 
293
-
297
, doi: .
Engebø
,
A.
,
Lædre
,
O.
,
Young
,
B.
,
Larssen
,
P.F.
,
Lohne
,
J.
and
Klakegg
,
O.J.
(
2020
), “
Collaborative project delivery methods: a scoping review
”,
Journal of Civil Engineering and Management
, Vol. 
26
No. 
3
, pp. 
278
-
303
, doi: .
Forbes
,
L.H.
and
Ahmed
,
S.M.
(
2010
),
Modern Construction: Lean Project Delivery and Integrated Practices
,
CRC Press
,
Boca Raton, FL
,
ISBN: 9780429145278
.
Franz
,
B.
,
Leicht
,
R.
,
Molenaar
,
K.
and
Messner
,
J.
(
2017
), “
Impact of team integration and group cohesion on project delivery performance
”,
Journal of Construction Engineering and Management
, Vol. 
143
No. 
1
, doi: .
Frei
,
B.
,
Sagerschnig
,
C.
and
Gyalistras
,
D.
(
2017
), “
Performance gaps in Swiss buildings: an analysis of conflicting objectives and mitigation strategies
”,
Energy Procedia
, Vol. 
122
, pp. 
421
-
426
, doi: .
Häkkinen
,
T.
and
Belloni
,
K.
(
2011
), “
Barriers and drivers for sustainable building
”,
Building Research and Information
, Vol. 
39
No. 
3
, pp. 
239
-
255
, doi: .
Hanna
,
A.S.
(
2016
), “
Benchmark performance metrics for integrated project delivery
”,
Journal of Construction Engineering and Management
, Vol. 
142
No. 
9
, doi: .
Heidemann
,
A.
and
Gehbauer
,
F.
(
2010
), “
Cooperative project delivery in an environment of strict design-bid-build tender regulations
”,
Proceedings of the 18th Annual Conference of the International Group for Lean Construction (IGLC-18)
,
Perth
,
28-31 July
, pp. 
590
-
591
,
available at:
 https://iglc.net/Papers/Details/674
Hietajärvi
,
A.M.
,
Aaltonen
,
K.
and
Haapasalo
,
H.
(
2017a
), “
What is project alliance capability?
”,
International Journal of Managing Projects in Business
, Vol. 
10
No. 
2
, pp. 
404
-
422
, doi: .
Hietajärvi
,
A.M.
,
Aaltonen
,
K.
and
Haapasalo
,
H.
(
2017b
), “
Opportunity management in large projects: a case study of an infrastructure alliance project
”,
Construction Innovation
, Vol. 
17
No. 
3
, pp. 
340
-
362
, doi: .
Hietajärvi
,
A.M.
,
Aaltonen
,
K.
and
Haapasalo
,
H.
(
2017c
), “
Managing integration in infrastructure alliance projects: dynamics of integration mechanisms
”,
International Journal of Managing Projects in Business
, Vol. 
10
No. 
1
, pp. 
5
-
31
, doi: .
Ibrahim
,
C.K.I.C.
,
Costello
,
S.B.
and
Wilkinson
,
S.
(
2015a
), “
Establishment of quantitative measures for team integration assessment in alliance projects
”,
Journal of Management in Engineering
, Vol. 
31
No. 
5
, doi: .
Ibrahim
,
C.K.I.C.
,
Costello
,
S.B.
and
Wilkinson
,
S.
(
2015b
), “
Development of an assessment tool for team integration in alliance projects
”,
International Journal of Managing Projects in Business
, Vol. 
8
No. 
4
, pp. 
813
-
827
, doi: .
Ibrahim
,
C.K.I.C.
,
Costello
,
S.B.
and
Wilkinson
,
S.
(
2016
), “
Application of a team integration performance index in road infrastructure alliance projects
”,
Benchmarking: An International Journal
, Vol. 
23
No. 
5
, pp. 
1341
-
1362
, doi: .
Ibrahim
,
C.K.I.C.
,
Costello
,
S.B.
and
Wilkinson
,
S.
(
2018
), “
Making sense of team integration practice through the ‘lived experience’ of alliance project teams
”,
Engineering, Construction and Architectural Management
, Vol. 
25
No. 
5
, pp. 
598
-
622
, doi: .
Ibrahim
,
M.W.
,
Hanna
,
A.
and
Kievet
,
D.
(
2020
), “
Quantitative comparison of project performance between project delivery systems
”,
Journal of Management in Engineering
, Vol. 
36
No. 
6
, doi: .
Kent
,
D.C.
and
Becerik-Gerber
,
B.
(
2010
), “
Understanding construction industry experience and attitudes toward integrated project delivery
”,
Journal of Construction Engineering and Management
, Vol. 
136
No. 
8
, pp. 
815
-
825
, doi: .
Kibert
,
C.J.
(
2016
),
Sustainable Construction: Green Building Design and Delivery
,
John Wiley & Sons
.
Laconte
,
P.
and
Gossop
,
C.
(
2016
),
Sustainable Cities: Assessing the Performance and Practice of Urban Environments
,
Bloomsbury Publishing
,
New York, NY
,
ISBN: 978-1784532321
.
Lahdenperä
,
P.
(
2012
), “
Making sense of the multi-party contractual arrangements of project partnering, project alliancing and integrated project delivery
”,
Construction Management and Economics
, Vol. 
30
No. 
1
, pp. 
57
-
79
, doi: .
Lee
,
H.W.
,
Tommelein
,
I.D.
and
Ballard
,
G.
(
2013
), “
Energy-related risk management in integrated project delivery
”,
Journal of Construction Engineering and Management
, Vol. 
139
No. 
12
, A4013001, doi: .
Li
,
B.
and
Yao
,
R.
(
2012
), “
Building energy efficiency for sustainable development in China: challenges and opportunities
”,
Building Research and Information
, Vol. 
40
No. 
4
, pp. 
417
-
431
, doi: .
Liang
,
J.
,
Qiu
,
Y.
and
Hu
,
M.
(
2019
), “
Mind the energy performance gap: evidence from green commercial buildings
”,
Resources, Conservation and Recycling
, Vol. 
141
, pp. 
364
-
377
, doi: .
Lichtig
,
W.A.
(
2005
), “
Sutter health: developing a contracting model to support lean project delivery
”,
Lean Construction Journal
, Vol. 
2
, pp. 
105
-
112
, doi: .
Ling
,
F.Y.
,
Teo
,
P.X.
,
Li
,
S.
,
Zhang
,
Z.
and
Ma
,
Q.
(
2020
), “
Adoption of integrated project delivery practices for superior project performance
”,
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
, Vol. 
12
No. 
4
, 05020014, doi: .
Lloyd
,
H.L.
and
Varey
,
R.J.
(
2003
), “
Factors affecting internal communication in a strategic alliance project
”,
Corporate Communications: An International Journal
, Vol. 
8
No. 
3
, pp. 
197
-
207
, doi: .
Love
,
P.E.
,
Mistry
,
D.
and
Davis
,
P.R.
(
2010
), “
Price competitive alliance projects: identification of success factors for public clients
”,
Journal of Construction Engineering and Management
, Vol. 
136
No. 
9
, pp. 
947
-
956
, doi: .
Mahdavi
,
A.
,
Berger
,
C.
,
Amin
,
H.
,
Ampatzi
,
E.
,
Andersen
,
R.K.
,
Azar
,
E.
,
Barthelmes
,
V.M.
,
Favero
,
M.
,
Hahn
,
J.
,
Khovalyg
,
D.
and
Knudsen
,
H.N.
(
2021
), “
The role of occupants in buildings' energy performance gap: myth or reality?
”,
Sustainability
, Vol. 
13
No. 
6
, 3146, doi: .
Markus
,
A.A.
,
Hobson
,
B.W.
,
Gunay
,
H.B.
and
Bucking
,
S.
(
2022
), “
Does a knowledge gap contribute to the performance gap? Interviews with building operators to identify how data-driven insights are interpreted
”,
Energy and Buildings
, Vol. 
268
, 112238, doi: .
Mesa
,
H.A.
,
Molenaar
,
K.R.
and
Alarcón
,
L.F.
(
2019
), “
Comparative analysis between integrated project delivery and lean project delivery
”,
International Journal of Managing Projects in Business
, Vol. 
37
No. 
3
, pp. 
395
-
409
, doi: .
Mike
,
E.M.
,
Schmitz
,
A.
and
Netherton
,
L.M.
(
2015
), Real Estate Development.
Principles and Process
, (5th ed.) ,
ULI Urban Land Institute
,
Washington, DC
, ISBN:
978-0874203431
.
Miller
,
C.
,
Arjunan
,
P.
,
Kathirgamanathan
,
A.
,
Fu
,
C.
,
Roth
,
J.
,
Park
,
J.Y.
,
Balbach
,
C.
,
Gowri
,
K.
,
Nagy
,
Z.
,
Fontanini
,
A.D.
and
Haberl
,
J.
(
2020
), “
The ASHRAE great energy predictor III competition: overview and results
”,
Science and Technology for the Built Environment
, Vol. 
26
No. 
10
, pp. 
1427
-
1447
, doi: .
MohammadHasanzadeh
,
S.
,
Hosseinalipour
,
M.
and
Hafezi
,
M.
(
2014
), “
Collaborative procurement in construction projects performance measures, case study: partnering in Iranian construction industry
”,
Procedia - Social and Behavioral Sciences
, Vol. 
119
, pp. 
811
-
818
, doi: .
Mollaoglu-Korkmaz
,
S.
,
Swarup
,
L.
and
Riley
,
D.
(
2013
), “
Delivering sustainable, high-performance buildings: influence of project delivery methods on integration and project outcomes
”,
Journal of Management in Engineering
, Vol. 
29
No. 
1
, pp. 
71
-
78
, doi: .
Moradi
,
S.
and
Kähkönen
,
K.
(
2022
), “
Success in collaborative construction through the lens of project delivery elements
”,
Built Environment Project and Asset Management
, Vol. 
12
No. 
6
, pp. 
973
-
991
, doi: .
Moradi
,
S.
and
Sormunen
,
P.
(
2022
), “
Lean and sustainable project delivery in building construction: development of a conceptual framework
”,
Buildings
, Vol. 
12
No. 
10
, 1757, doi: .
Moradi
,
S.
and
Sormunen
,
P.
(
2023
), “
Revisiting the concept of waste and its causes in construction from analytical and conceptual perspectives
”,
Construction Management and Economics
, Vol. 
41
No. 
8
, pp. 
621
-
633
, doi: .
Moradi
,
S.
,
Kähkönen
,
K.
,
Klakegg
,
O.J.
and
Aaltonen
,
K.
(
2021a
), “
A competency model for the selection and performance improvement of project managers in collaborative construction projects: behavioral studies in Norway and Finland
”,
Buildings
, Vol. 
11
No. 
4
, p.
4
, doi: .
Moradi
,
S.
,
Kähkönen
,
K.
,
Klakegg
,
O.
and
Aaltonen
,
K.
(
2021b
), “
Profile of project managers' competencies for collaborative construction projects
”, in
Scott
,
L.
and
Neilson
,
C.J.
(Eds),
Proceedings of the 37th Annual ARCOM Conference
,
6-7 September
,
Association of Researchers in Construction Management
, pp. 
350
-
359
,
available at:
 https://www.arcom.ac.uk/-docs/archive/2021-Indexed-Papers.pdf
Moradi
,
S.
,
Kähkönen
,
K.
and
Sormunen
,
P.
(
2022
), “
Analytical and conceptual perspectives toward behavioral elements of collaborative delivery models in construction projects
”,
Buildings
, Vol. 
12
No. 
3
, p.
316
, doi: .
Moradi
,
S.
,
Hirvonen
,
J.
and
Sormunen
,
P.
(
2023
), “
A qualitative and life cycle-based study of the energy performance gap in building construction: perspectives of Finnish project professionals and property maintenance experts
”,
Building Research and Information
, pp. 
1
-
13
, doi: .
Mousavi
,
S.
,
Marroquín
,
M.G.V.
,
Hajiaghaei-Keshteli
,
M.
and
Smith
,
N.R.
(
2023
), “
Data-driven prediction and optimization toward net-zero and positive-energy buildings: a systematic review
”,
Building and Environment
, Vol. 
242
, 110578, doi: .
Nevstad
,
K.
,
Børve
,
S.
,
Karlsen
,
A.T.
and
Aarseth
,
W.
(
2018
), “
Understanding how to succeed with project partnering
”,
International Journal of Managing Projects in Business
, Vol. 
11
No. 
4
, pp. 
1044
-
1065
, doi: .
Ng
,
S.T.
,
Rose
,
T.M.
,
Mak
,
M.
and
Chen
,
S.E.
(
2002
), “
Problematic issues associated with project partnering—the contractor perspective
”,
International Journal of Project Management
, Vol. 
20
No. 
6
, pp. 
437
-
449
, doi: .
Oakland
,
J.S.
and
Marosszeky
,
M.
(
2017
),
Total Construction Management: Lean Quality in Construction Project Delivery
,
Routledge
,
Abingdon
,
ISBN: 9781315694351
.
Qian
,
Q.K.
,
Chan
,
E.H.
and
Khalid
,
A.G.
(
2015
), “
Challenges in delivering green building projects: unearthing the transaction costs (TCs)
”,
Sustainability
, Vol. 
7
No. 
4
, pp. 
3615
-
3636
, doi: .
Radziszewska-Zielina
,
E.
and
Szewczyk
,
B.
(
2016
), “
Supporting partnering relation management in the implementation of construction projects using AHP and fuzzy AHP methods
”,
Procedia Engineering
, Vol. 
161
, pp. 
1096
-
1100
, doi: .
Raslim
,
F.M.
and
Mustaffa
,
N.E.
(
2017
), “
The success factors of relationship-based procurement (RBP) in Malaysia
”,
International Journal of Civil Engineering and Technology
, Vol. 
8
, pp. 
1616
-
1625
,
available at:
 http://www.iaeme.com/ijciet/issues.asp?JType=IJCIET&VType=8&IType=8
Rasmussen
,
H.L.
and
Jensen
,
P.A.
(
2020
), “
A facilities manager's typology of performance gaps in new buildings
”,
Journal of Facilities Management
, Vol. 
18
No. 
1
, pp. 
71
-
87
, doi: .
Saunders
,
M.N.K.
,
Lewis
,
P.
and
Thornhill
,
A.
(
2019
),
Research Methods for Business Students
, (8th ed.) ,
Pearson Education
,
Harlow
,
ISBN: 9781292208787
.
Spudys
,
P.
,
Afxentiou
,
N.
,
Georgali
,
P.Z.
,
Klumbyte
,
E.
,
Jurelionis
,
A.
and
Fokaides
,
P.
(
2023
), “
Classifying the operational energy performance of buildings with the use of digital twins
”,
Energy and Buildings
, Vol. 
290
, 113106, doi: .
Sundquist
,
V.
,
Hulthén
,
K.
and
Gadde
,
L.E.
(
2018
), “
From project partnering towards strategic supplier partnering
”,
Engineering, Construction and Architectural Management
, Vol. 
25
No. 
3
, pp. 
358
-
373
, doi: .
Whang
,
S.-W.
,
Park
,
K.S.
and
Kim
,
S.
(
2019
), “
Critical success factors for implementing integrated construction project delivery
”,
Engineering, Construction and Architectural Management
, Vol. 
26
No. 
10
, pp. 
2432
-
2446
, doi: .
Willan
,
C.
,
Hitchings
,
R.
,
Ruyssevelt
,
P.
and
Shipworth
,
M.
(
2020
), “
Talking about targets: how construction discourses of theory and reality represent the energy performance gap in the United Kingdom
”,
Energy Research and Social Science
, Vol. 
64
, 101330, doi: .
Yılmaz
,
D.
,
Tanyer
,
A.M.
and
Toker
,
İ.D.
(
2023
), “
A data-driven energy performance gap prediction model using machine learning
”,
Renewable and Sustainable Energy Reviews
, Vol. 
181
, 113318, doi: .
Young
,
B.
,
Hosseini
,
A.
and
Lædre
,
O.
(
2016
), “
The characteristics of Australian infrastructure alliance projects
”,
Energy Procedia
, Vol. 
96
, pp. 
833
-
844
, doi: .
Zhang
,
X.
and
Kumaraswamy
,
M.M.
(
2001
), “
Procurement protocols for public-private partnered projects
”,
Journal of Construction Engineering and Management
, Vol. 
127
No. 
5
, pp. 
351
-
358
, doi: .
Zhang
,
L.
,
Cheng
,
J.
and
Fan
,
W.
(
2016
), “
Party selection for integrated project delivery based on interorganizational transactive memory system
”,
Journal of Construction Engineering and Management
, Vol. 
142
No. 
3
, doi: .
Zou
,
P.X.
,
Xu
,
X.
,
Sanjayan
,
J.
and
Wang
,
J.
(
2018
), “
Review of 10 years research on building energy performance gap: life-cycle and stakeholder perspectives
”,
Energy and Buildings
, Vol. 
178
, pp. 
165
-
181
, doi: .
Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at http://creativecommons.org/licences/by/4.0/legalcode

Data & Figures

Figure 1
A framework for elements of the project delivery model, featuring a header and four text boxes, is shown.The framework consists of a header at the top labeled “Defining Elements of Project Delivery Model”. Below the header, four rectangular text boxes are arranged in a horizontal row from left to right. All the text boxes are labeled as follows: The first box is labeled “Project organization” and contains the description “(Clear definition of roles and responsibilities between project participants)”. The second box is labeled “Operational system” and contains the description “(Appropriate timing and sequence of events and practices and techniques management)”. The third box is labeled “Contractual framework” and contains the description “(Promises of project parties and their contractual relationships)”. The fourth box is labeled “Delivery process” and contains the description “(Steps and activities encompassing project and single forward slash or building life cycle and the involved people)”.

Framework for defining project delivery model

Figure 1
A framework for elements of the project delivery model, featuring a header and four text boxes, is shown.The framework consists of a header at the top labeled “Defining Elements of Project Delivery Model”. Below the header, four rectangular text boxes are arranged in a horizontal row from left to right. All the text boxes are labeled as follows: The first box is labeled “Project organization” and contains the description “(Clear definition of roles and responsibilities between project participants)”. The second box is labeled “Operational system” and contains the description “(Appropriate timing and sequence of events and practices and techniques management)”. The third box is labeled “Contractual framework” and contains the description “(Promises of project parties and their contractual relationships)”. The fourth box is labeled “Delivery process” and contains the description “(Steps and activities encompassing project and single forward slash or building life cycle and the involved people)”.

Framework for defining project delivery model

Close modal
Figure 2
A figure describes the framework for elements of the project delivery model, showing a title above four quadrants in a grid.The figure features a header at the top labeled “Conceptualization of Collaborative Project Delivery Model in Construction”. Below the header, four rounded rectangular text boxes are arranged in a two-by-two grid, forming four quadrants separated by thick perpendicular lines. All the text boxes are labeled as follows: The top-left box is labeled “Project Organization” and contains the bullet points “Trust-based relationships” and “Joint decision making”. The top-right box is labeled “Operational System” and contains the bullet points “Joint planning, design and control” and “Open book cost management”. The bottom-left box is labeled “Contractual Framework” and contains the bullet points “Multiparty or poliparty contract” and “Fair share of risk-reward”. The bottom-right box is labeled “Delivery process” and contains the bullet points “Early involvement of contractor” and “Continuous improvement and learning”.

Conceptualization of collaborative project delivery model in construction

Figure 2
A figure describes the framework for elements of the project delivery model, showing a title above four quadrants in a grid.The figure features a header at the top labeled “Conceptualization of Collaborative Project Delivery Model in Construction”. Below the header, four rounded rectangular text boxes are arranged in a two-by-two grid, forming four quadrants separated by thick perpendicular lines. All the text boxes are labeled as follows: The top-left box is labeled “Project Organization” and contains the bullet points “Trust-based relationships” and “Joint decision making”. The top-right box is labeled “Operational System” and contains the bullet points “Joint planning, design and control” and “Open book cost management”. The bottom-left box is labeled “Contractual Framework” and contains the bullet points “Multiparty or poliparty contract” and “Fair share of risk-reward”. The bottom-right box is labeled “Delivery process” and contains the bullet points “Early involvement of contractor” and “Continuous improvement and learning”.

Conceptualization of collaborative project delivery model in construction

Close modal
Figure 3
A figure describes the structural model for elements of project delivery model, connecting four major delivery concepts.The structural model features four large circles located at the corners of a complex network, which are labeled as “Alliance” at the top left, “I P D” at the top right, “Partnering” at the bottom left, and “L P D” at the bottom right. Thin arrows lead from these circles to smaller oval nodes scattered throughout the center. From “Alliance” at the top left, thin arrows lead to four oval nodes at the right, labeled as “Team integration”, “Relationship building and management”, “Success factors and barriers”, and “Risk management”. From “I P D” at the top right, thin arrows lead to five oval nodes at the left and bottom, labeled as “Integration and collaboration”, “Project performance”, “Success factors and barriers”, “Risk and insurance”, and “Trust and relationship”. From “Partnering” at the bottom left, thin arrows lead to five oval nodes at the right and top, labeled as “Partnering definition”, “Partnering performance”, “Partnering and B I M”, “Success factors and barriers”, and “Trust and relationship”. From “L P D” at the bottom right, thin arrows lead to three oval nodes at the top and left, labeled as “Contractual issues”, “Success factors and barriers”, and “Combination of L C with I P D or B I M or sustainability”. A series of thick arrows form a central loop connecting the oval node labeled “Success factors and barriers” from all four nodes. A thin double-headed arrow connects “Team integration” at the top to “Integration and collaboration” at the top. Another thin double-headed arrow connects “Relationship building and management” at the top left to “Trust and relationship” at the bottom center. A thin line also connects “Partnering performance” at the left to “Project performance” at the right. A thin line also connects “Risk management” at the middle left to “Risk and insurance” at the middle right.

Major themes in the previous studies addressing collaborative project delivery models

Figure 3
A figure describes the structural model for elements of project delivery model, connecting four major delivery concepts.The structural model features four large circles located at the corners of a complex network, which are labeled as “Alliance” at the top left, “I P D” at the top right, “Partnering” at the bottom left, and “L P D” at the bottom right. Thin arrows lead from these circles to smaller oval nodes scattered throughout the center. From “Alliance” at the top left, thin arrows lead to four oval nodes at the right, labeled as “Team integration”, “Relationship building and management”, “Success factors and barriers”, and “Risk management”. From “I P D” at the top right, thin arrows lead to five oval nodes at the left and bottom, labeled as “Integration and collaboration”, “Project performance”, “Success factors and barriers”, “Risk and insurance”, and “Trust and relationship”. From “Partnering” at the bottom left, thin arrows lead to five oval nodes at the right and top, labeled as “Partnering definition”, “Partnering performance”, “Partnering and B I M”, “Success factors and barriers”, and “Trust and relationship”. From “L P D” at the bottom right, thin arrows lead to three oval nodes at the top and left, labeled as “Contractual issues”, “Success factors and barriers”, and “Combination of L C with I P D or B I M or sustainability”. A series of thick arrows form a central loop connecting the oval node labeled “Success factors and barriers” from all four nodes. A thin double-headed arrow connects “Team integration” at the top to “Integration and collaboration” at the top. Another thin double-headed arrow connects “Relationship building and management” at the top left to “Trust and relationship” at the bottom center. A thin line also connects “Partnering performance” at the left to “Project performance” at the right. A thin line also connects “Risk management” at the middle left to “Risk and insurance” at the middle right.

Major themes in the previous studies addressing collaborative project delivery models

Close modal
Figure 4
A conceptual model shows project phases, mapping lean thinking across project and operation stages.The complex conceptual model is presented as a grid with headers at the top and labels on the left. The first row at the top is labeled “Phase” in a rectangular text box and points to the right by an arrow, which contains four rectangular text boxes, arranged from left to right, labeled “Project definition”, “Design and planning”, “Construction”, and “Operation”. The second row is labeled “Lean thinking” in a rectangular text box to the left and points to the right by an arrow to three horizontal rectangular text boxes: “Sustainable value specification and justification” under the “Project definition” header, “Sustainable flow of value adding products and processes and their continuous improvement” under the “Design and planning” and “Construction” headers, and “Learning, rethinking and improving” under the “Operation” header. The third row labeled “Lean and sustainable target value definition and management for process and product”, from which a arrow leads to the right that contains nine numbered rectangular text boxes: “1. Conceptualize”, “2. Explore”, and “3. Justify” under “Project definition”; “4. Design and plan”, “5. Visualize and simulate”, “6. Measure”, and “7. Improve” under “Design and planning”; “8. Build, learn, and enhance” under “Construction”; and “9. Use, learn, and update” under “Operation”. Continuing in the third row, the arrow leads to a central grid of descriptive text boxes aligned under the nine numbered steps: “Understand the need, means, and the end” under “1. Conceptualize”; “Explore the economic, social, and environmental sustainability impacts of the required process and target product” under “2. Explore”; “Set the sustainable target value and cost and analyze feasibility of achieving those targets” under “3. Justify”; “Design and plan process and product together with involvement of project delivery team” under “4. Design and plan”; “Visualize and simulate the designed processes and products to see how they work if employed and built” under “5. Visualize and simulate”; “Measure the function of visualized and simulated processes and products against environmental, social and economic sustainability indicators” under “6. Measure”; “Improve the design (of the product and process) according to measurement results and repeat the measurement until the results meet target values and cost” under “7. Improve”; “Perform construction based on the approved design of process and product”, “Pursue waste elimination and value maximization throughout construction”, “Monitor the realization of process and product target values”, and “Update product and process design after each improvement or change” under “8. Build, learn, and enhance”; and “Monitor the building performance throughout its operation”, “Compare the real results with the expectations”, and “Update the sustainability assessment criteria (indicators) for process and product design” under “9. Use, learn, and update”. Below this, the row labeled “Decision making” in a rectangular text box to the left points to the right by an arrow to a box labeled “Stage gate: Yes or no decision to fund and start project design and planning” under “Project definition” and “Design and planning”, and a box labeled “Stage gate: Approval for starting construction phase” under “Design and planning” and “Construction”. In the same section, a rectangular text box is labeled “The contract(s) must provide clear and agreed basis for fair share of risk-reward, open cost management, and joint project governance by key parties” under “Project definition” and “Design and planning”, and another box is labeled “Approval at this stage means that project goals (including sustainability related ones) can be met based on the output of design and planning phase” under “Design and planning” and “Construction”. Below this, the row labeled “Lean and sustainable tools and techniques for different phases” in a rectangular text box to the left points to the right by an arrow to stacked horizontal boxes including “Building Information Modelling and related techniques and technologies for visualization, simulation and other digitalization purposes” spanning the first three phase headers, “Comprehensive Life Cycle Assessment, analysis of environmental, social and economic impacts” spanning the first three phase headers, “Last Planner System for design, planning, and construction management” under “Design and planning” and “Construction”, “Value Stream Mapping for continuous waste elimination and productivity” under “Design and planning” and “Construction”, “Target Value Design” under “Design and planning” and “Construction”, “Target costing for performing feasibility study” under “Project definition”, “5 S (sort, set in order, shine, standardize, and sustain) and Just in Time” under “Construction”, and “Building operation monitoring and control via sensors or other relevant tools” under the “Operation” header. At the bottom right, a rectangular text box is labeled “Foundation” to the left, from which a thick arrow leads to the right through a wide gray shaded bar labeled “Built-in sustainability, lean thinking, and building information modelling” spanning all headers.

Conceptual model for collaborative and sustainable delivery of building construction projects

Figure 4
A conceptual model shows project phases, mapping lean thinking across project and operation stages.The complex conceptual model is presented as a grid with headers at the top and labels on the left. The first row at the top is labeled “Phase” in a rectangular text box and points to the right by an arrow, which contains four rectangular text boxes, arranged from left to right, labeled “Project definition”, “Design and planning”, “Construction”, and “Operation”. The second row is labeled “Lean thinking” in a rectangular text box to the left and points to the right by an arrow to three horizontal rectangular text boxes: “Sustainable value specification and justification” under the “Project definition” header, “Sustainable flow of value adding products and processes and their continuous improvement” under the “Design and planning” and “Construction” headers, and “Learning, rethinking and improving” under the “Operation” header. The third row labeled “Lean and sustainable target value definition and management for process and product”, from which a arrow leads to the right that contains nine numbered rectangular text boxes: “1. Conceptualize”, “2. Explore”, and “3. Justify” under “Project definition”; “4. Design and plan”, “5. Visualize and simulate”, “6. Measure”, and “7. Improve” under “Design and planning”; “8. Build, learn, and enhance” under “Construction”; and “9. Use, learn, and update” under “Operation”. Continuing in the third row, the arrow leads to a central grid of descriptive text boxes aligned under the nine numbered steps: “Understand the need, means, and the end” under “1. Conceptualize”; “Explore the economic, social, and environmental sustainability impacts of the required process and target product” under “2. Explore”; “Set the sustainable target value and cost and analyze feasibility of achieving those targets” under “3. Justify”; “Design and plan process and product together with involvement of project delivery team” under “4. Design and plan”; “Visualize and simulate the designed processes and products to see how they work if employed and built” under “5. Visualize and simulate”; “Measure the function of visualized and simulated processes and products against environmental, social and economic sustainability indicators” under “6. Measure”; “Improve the design (of the product and process) according to measurement results and repeat the measurement until the results meet target values and cost” under “7. Improve”; “Perform construction based on the approved design of process and product”, “Pursue waste elimination and value maximization throughout construction”, “Monitor the realization of process and product target values”, and “Update product and process design after each improvement or change” under “8. Build, learn, and enhance”; and “Monitor the building performance throughout its operation”, “Compare the real results with the expectations”, and “Update the sustainability assessment criteria (indicators) for process and product design” under “9. Use, learn, and update”. Below this, the row labeled “Decision making” in a rectangular text box to the left points to the right by an arrow to a box labeled “Stage gate: Yes or no decision to fund and start project design and planning” under “Project definition” and “Design and planning”, and a box labeled “Stage gate: Approval for starting construction phase” under “Design and planning” and “Construction”. In the same section, a rectangular text box is labeled “The contract(s) must provide clear and agreed basis for fair share of risk-reward, open cost management, and joint project governance by key parties” under “Project definition” and “Design and planning”, and another box is labeled “Approval at this stage means that project goals (including sustainability related ones) can be met based on the output of design and planning phase” under “Design and planning” and “Construction”. Below this, the row labeled “Lean and sustainable tools and techniques for different phases” in a rectangular text box to the left points to the right by an arrow to stacked horizontal boxes including “Building Information Modelling and related techniques and technologies for visualization, simulation and other digitalization purposes” spanning the first three phase headers, “Comprehensive Life Cycle Assessment, analysis of environmental, social and economic impacts” spanning the first three phase headers, “Last Planner System for design, planning, and construction management” under “Design and planning” and “Construction”, “Value Stream Mapping for continuous waste elimination and productivity” under “Design and planning” and “Construction”, “Target Value Design” under “Design and planning” and “Construction”, “Target costing for performing feasibility study” under “Project definition”, “5 S (sort, set in order, shine, standardize, and sustain) and Just in Time” under “Construction”, and “Building operation monitoring and control via sensors or other relevant tools” under the “Operation” header. At the bottom right, a rectangular text box is labeled “Foundation” to the left, from which a thick arrow leads to the right through a wide gray shaded bar labeled “Built-in sustainability, lean thinking, and building information modelling” spanning all headers.

Conceptual model for collaborative and sustainable delivery of building construction projects

Close modal
Figure 5
A figure shows four pie charts arranged in a two-by-two grid.The first pie chart at the top left is titled “Gender” and contains 2 slices. The data from the top of the chart and in the clockwise sense are as follows: Male: 81 percent. Female: 19 percent. The second pie chart at the top right is titled “Age group” and contains 4 slices. The data from the top of the chart and in the clockwise sense are as follows: 30 to 39: 19 percent. 40 to 49: 38 percent. 50 to 59: 29 percent. Over 60: 14 percent. The third pie chart at the bottom left is titled “Years of experience” and contains 4 slices. The data from the top of the chart and in the clockwise sense are as follows: 5 to 9: 9 percent. 10 to 20: 33 percent. 20 to 30: 48 percent. Greater than 30: 10 percent. The fourth pie chart at the bottom right is titled “Education” and contains 3 slices. The data from the top of the chart and in the clockwise sense are as follows: Bachelor's degree: 57 percent. Master's degree: 33 percent. P h D: 10 percent.

Demographic information of the interviewees

Figure 5
A figure shows four pie charts arranged in a two-by-two grid.The first pie chart at the top left is titled “Gender” and contains 2 slices. The data from the top of the chart and in the clockwise sense are as follows: Male: 81 percent. Female: 19 percent. The second pie chart at the top right is titled “Age group” and contains 4 slices. The data from the top of the chart and in the clockwise sense are as follows: 30 to 39: 19 percent. 40 to 49: 38 percent. 50 to 59: 29 percent. Over 60: 14 percent. The third pie chart at the bottom left is titled “Years of experience” and contains 4 slices. The data from the top of the chart and in the clockwise sense are as follows: 5 to 9: 9 percent. 10 to 20: 33 percent. 20 to 30: 48 percent. Greater than 30: 10 percent. The fourth pie chart at the bottom right is titled “Education” and contains 3 slices. The data from the top of the chart and in the clockwise sense are as follows: Bachelor's degree: 57 percent. Master's degree: 33 percent. P h D: 10 percent.

Demographic information of the interviewees

Close modal
Figure 6
A flowchart shows a collaborative and life cycle-based project delivery model for sustainable building construction.The flowchart consists of a wide horizontal rectangular title bar at the top center that reads “Collaborative and Life Cycle-based Project Delivery Model (C L C P D M) for Sustainable Building Construction (Abstract Version)”. Below this, two parallel life-cycle streams are arranged from left to right. The upper stream is labeled “Project Life Cycle” and is divided into a long horizontal segment labeled “Pre-construction activities” followed by a shorter horizontal segment labeled “Construction and Handover”. The lower right stream is labeled “Building Life Cycle” with a horizontal segment labeled “Building Commissioning, Use, and Management”. Under “Pre-construction activities” on the far left, a vertical rectangular box titled “Project Definition” contains a smaller rectangular box labeled “Step 1: Exploring the client’s needs and limits”. A curved arrow begins at the right side of the “Project Definition” box and leads rightwards to a rectangular box titled “Pre-design and Feasibility study” containing “Step 2: Defining the project and its delivery basis in further detail”. From the right side of this box, a curved arrow leads upward and right to a rectangular box titled “Tendering” containing “Step 3: Forming the collaborative project delivery team”. From the bottom right of the “Tendering” box, a curved arrow leads downward and right to a large central rectangular box titled “Essential Design and Planning”. Inside this box, on the left side is “Step 4: Designing and planning a process and project plan”. In the center is a circular loop graphic labeled “Steps 4, 5, and 6” indicating iteration. On the right side is “Step 6: Engineering the design and plan”. At the bottom inside the same box is another smaller rectangular box labeled “Step 5: Visualizing and simulating to check functionality”. From the right edge of the “Essential Design and Planning” box, a rightward arrow leads to a rectangular box under “Construction and Handover” titled “Construction” containing “Step 7: Active target measurement and documentation throughout the construction phase”. From the right edge of the “Construction” box, a rightward arrow leads to another rectangular box titled “Closure and Handover” containing “Step 8: Completing the project and building’s life cycle”. From the right side of the “Closure and Handover” box, a rightward arrow leads downward into the “Building Life Cycle” stream to a rectangular box titled “Commissioning, User induction” containing “Step 9: Testing the building’s energy systems and providing training for users”. From this box, a rightward arrow leads to a rectangular box titled “Operation” containing “Step 10: Using the building, performance monitoring, and planned maintenance and operational actions”. From the right side of the “Operation” box, a rightward arrow leads to the final rectangular box titled “Maintenance, Optimization and Renovation planning” containing “Step 11: Performing planned maintenance and optimization, monitoring building performance, and planning future renovations”. Along the bottom of the diagram, a row of smaller horizontally aligned rectangular boxes labeled “Output of Step 1” through “Output of Step 11” appears directly beneath their corresponding steps. The bottom left rectangular box is labeled “Output of Step 1” and contains “1. General specifications of the desired building”, “2. The estimated time and cost of constructing the building”, “3. Client’s available money and time”. This box is positioned directly below the “Project Definition” box and is horizontally aligned with the first stage of the project life cycle. The next rectangular box to the right is labeled “Output of Step 2” and contains “1. Pre-design documents”, “2. Results of the detailed feasibility study”, “3. Risks to consider”, “4. Building documents”, “5. Proposed performance risk-reward sharing mechanism”, “6. Explanation of contractor’s role in building operation for 15 to 20 years”. This box is positioned directly below the “Pre-design and Feasibility study” box and is vertically aligned with it. The third rectangular box from the left is labeled “Output of Step 3” and contains “1. Delivery team contract”, “2. Contractor selection”, “3. Agreed risk-reward sharing performance for the client and contractor”, “4. Signed collaboration agreement between the project parties”. This box is positioned directly below the “Tendering” box and aligned with that stage. The fourth rectangular box is labeled “Output of Steps 4, 5, and 6” and contains “1. The detailed target time for the overall design”, “2. The defined target cost for the overall design”, “3. Detailed budget for constructing the building”, “4. Essential design documents for starting the construction activities”, “5. The master schedule and price plan for construction activities”, “6. Records of the conducted simulations and improvements made in the overall design”. This box is positioned directly below the large “Essential Design and Planning” box and spans the width of that central stage. The fifth rectangular box to the right is labeled “Output of Step 7” and contains “1. Constructed building”, “2. Lessons learned during construction”, “3. Measurement and documentation results from the construction phase”. This box is positioned directly below the “Construction” box and aligned with it. The sixth rectangular box is labeled “Output of Step 8” and contains “1. Completed building”, “2. Final project documentation”, “3. Handover documents”. This box is positioned directly below the “Closure and Handover” box and aligned vertically with it. The seventh rectangular box is labeled “Output of Step 9” and contains “1. Commissioning report”, “2. User manuals”, “3. Training documentation for users”. This box is positioned directly below the “Commissioning, User induction” box within the building life cycle stream. The eighth rectangular box is labeled “Output of Step 10” and contains “1. Operational performance data”, “2. Maintenance records”, “3. Monitoring reports”. This box is positioned directly below the “Operation” box and aligned with it. The final rectangular box on the far right is labeled “Output of Step 11” and contains “1. Optimization results”, “2. Renovation plans”, “3. Long-term performance evaluation reports”. This box is positioned directly below the “Maintenance, Optimization and Renovation planning” box and marks the end of the bottom-row outputs.

Abstract version of collaborative and life cycle-based project delivery model (CLCPDM) for sustainable building construction

Figure 6
A flowchart shows a collaborative and life cycle-based project delivery model for sustainable building construction.The flowchart consists of a wide horizontal rectangular title bar at the top center that reads “Collaborative and Life Cycle-based Project Delivery Model (C L C P D M) for Sustainable Building Construction (Abstract Version)”. Below this, two parallel life-cycle streams are arranged from left to right. The upper stream is labeled “Project Life Cycle” and is divided into a long horizontal segment labeled “Pre-construction activities” followed by a shorter horizontal segment labeled “Construction and Handover”. The lower right stream is labeled “Building Life Cycle” with a horizontal segment labeled “Building Commissioning, Use, and Management”. Under “Pre-construction activities” on the far left, a vertical rectangular box titled “Project Definition” contains a smaller rectangular box labeled “Step 1: Exploring the client’s needs and limits”. A curved arrow begins at the right side of the “Project Definition” box and leads rightwards to a rectangular box titled “Pre-design and Feasibility study” containing “Step 2: Defining the project and its delivery basis in further detail”. From the right side of this box, a curved arrow leads upward and right to a rectangular box titled “Tendering” containing “Step 3: Forming the collaborative project delivery team”. From the bottom right of the “Tendering” box, a curved arrow leads downward and right to a large central rectangular box titled “Essential Design and Planning”. Inside this box, on the left side is “Step 4: Designing and planning a process and project plan”. In the center is a circular loop graphic labeled “Steps 4, 5, and 6” indicating iteration. On the right side is “Step 6: Engineering the design and plan”. At the bottom inside the same box is another smaller rectangular box labeled “Step 5: Visualizing and simulating to check functionality”. From the right edge of the “Essential Design and Planning” box, a rightward arrow leads to a rectangular box under “Construction and Handover” titled “Construction” containing “Step 7: Active target measurement and documentation throughout the construction phase”. From the right edge of the “Construction” box, a rightward arrow leads to another rectangular box titled “Closure and Handover” containing “Step 8: Completing the project and building’s life cycle”. From the right side of the “Closure and Handover” box, a rightward arrow leads downward into the “Building Life Cycle” stream to a rectangular box titled “Commissioning, User induction” containing “Step 9: Testing the building’s energy systems and providing training for users”. From this box, a rightward arrow leads to a rectangular box titled “Operation” containing “Step 10: Using the building, performance monitoring, and planned maintenance and operational actions”. From the right side of the “Operation” box, a rightward arrow leads to the final rectangular box titled “Maintenance, Optimization and Renovation planning” containing “Step 11: Performing planned maintenance and optimization, monitoring building performance, and planning future renovations”. Along the bottom of the diagram, a row of smaller horizontally aligned rectangular boxes labeled “Output of Step 1” through “Output of Step 11” appears directly beneath their corresponding steps. The bottom left rectangular box is labeled “Output of Step 1” and contains “1. General specifications of the desired building”, “2. The estimated time and cost of constructing the building”, “3. Client’s available money and time”. This box is positioned directly below the “Project Definition” box and is horizontally aligned with the first stage of the project life cycle. The next rectangular box to the right is labeled “Output of Step 2” and contains “1. Pre-design documents”, “2. Results of the detailed feasibility study”, “3. Risks to consider”, “4. Building documents”, “5. Proposed performance risk-reward sharing mechanism”, “6. Explanation of contractor’s role in building operation for 15 to 20 years”. This box is positioned directly below the “Pre-design and Feasibility study” box and is vertically aligned with it. The third rectangular box from the left is labeled “Output of Step 3” and contains “1. Delivery team contract”, “2. Contractor selection”, “3. Agreed risk-reward sharing performance for the client and contractor”, “4. Signed collaboration agreement between the project parties”. This box is positioned directly below the “Tendering” box and aligned with that stage. The fourth rectangular box is labeled “Output of Steps 4, 5, and 6” and contains “1. The detailed target time for the overall design”, “2. The defined target cost for the overall design”, “3. Detailed budget for constructing the building”, “4. Essential design documents for starting the construction activities”, “5. The master schedule and price plan for construction activities”, “6. Records of the conducted simulations and improvements made in the overall design”. This box is positioned directly below the large “Essential Design and Planning” box and spans the width of that central stage. The fifth rectangular box to the right is labeled “Output of Step 7” and contains “1. Constructed building”, “2. Lessons learned during construction”, “3. Measurement and documentation results from the construction phase”. This box is positioned directly below the “Construction” box and aligned with it. The sixth rectangular box is labeled “Output of Step 8” and contains “1. Completed building”, “2. Final project documentation”, “3. Handover documents”. This box is positioned directly below the “Closure and Handover” box and aligned vertically with it. The seventh rectangular box is labeled “Output of Step 9” and contains “1. Commissioning report”, “2. User manuals”, “3. Training documentation for users”. This box is positioned directly below the “Commissioning, User induction” box within the building life cycle stream. The eighth rectangular box is labeled “Output of Step 10” and contains “1. Operational performance data”, “2. Maintenance records”, “3. Monitoring reports”. This box is positioned directly below the “Operation” box and aligned with it. The final rectangular box on the far right is labeled “Output of Step 11” and contains “1. Optimization results”, “2. Renovation plans”, “3. Long-term performance evaluation reports”. This box is positioned directly below the “Maintenance, Optimization and Renovation planning” box and marks the end of the bottom-row outputs.

Abstract version of collaborative and life cycle-based project delivery model (CLCPDM) for sustainable building construction

Close modal
Figure 7
A detailed tabular figure shows a collaborative and life-cycle-based project delivery model.The tabular figure consists of a wide horizontal rectangular title bar at the top center that reads “Collaborative and Life Cycle-based Project Delivery Model (C L C P D M) for Sustainable Building Construction (Detailed Version)”. Below this, a horizontal bar is divided into two parts: “Project Life Cycle” on the left and “Building Life Cycle” on the right. Below these, a row of rectangular boxes represents specific sub-phases. Under “Project Life Cycle”, the boxes are “Project Definition”, “Pre-design and Feasibility study”, “Tendering”, “Essential Design and Planning”, “Construction (plus complementary design and planning)”, and “Closure and Handover”. Under “Building Life Cycle”, a larger header reads “Building Commissioning, Use, and Management”, which contains sub-phases “Commissioning and User Induction”, “Operation”, and “Maintenance, Optimization and Renovation planning”. Below the sub-phases, a row of rectangular boxes details eleven specific steps. A rectangular box is labeled “Step 1 Exploring the client’s needs and limits”. A rectangular box is labeled “Step 2 Defining the project and its delivery team in further detail”. A rectangular box is labeled “Step 3 Forming the collaborative project delivery team”. A rectangular box is labeled “Step 4 Designing and planning the process and product together”. A rectangular box is labeled “Step 5 Visualizing and simulating to check functionality”. A rectangular box is labeled “Step 6 Improving the design and plan”. A rectangular box is labeled “Step 7 Active target management and documenting the construction process”. A rectangular box is labeled “Step 8 Connecting the project and building’s life cycle”. A rectangular box is labeled “Step 9 Commissioning and tuning the building’s energy system”. A rectangular box is labeled “Step 10 Utilizing the building, documenting its performance, and planning required maintenance and optimizations”. A rectangular box is labeled “Step 11 Performing the planned maintenance and optimizations, monitoring building performance, and planning future renovations”. The row below the numbered steps contains comprehensive descriptions for the entire life cycle. Under “Step 1”, the details are “The client hires a consultant to assist him or her in the project definition”, “The consultant explores client’s needs and limits through answering following questions:”, “What type of building does the client need question mark”, “How is the building going to be used question mark”, “How much money and time would be needed to construct such a building question mark”, “Dose the client have the required time and money question mark”, and “If the answer to the questions is YES, then client approves STEP 1”. Under “Step 2”, the details are “The consultant hires a design team to develop the pre-design documents in active collaboration with the client and its consultant”, “The pre-design documents include, but not limited to, the building’s specifications and requirements (eample, energy consumption target, required energy system)”, “When the pre-design is done, the feasibility questions in STEP 1 are answered again, this time, based on the pre-design documents”, “If the answer is YES, then the client asks the consultant to preparing the bidding documents”, and “The bidding documents must include, among other things, the percentage for the risk-reward sharing and clearly explain contractor’s responsibilities for the maintenance of the constructed building”. Under “Step 3”, the details are “The client first awards the design team’s contract”, “Then, the tendering is conducted to select a competent contractor”, “The competent contractor must meet the explained eligibility criteria in the bid documents and offer a price which is not too low or high”, “A collaboration framework is prepared and signed by project parties to guide their collaboration in the project”, “Regardless of the contract type used for the project, it should contain the risk-reward sharing mechanism”, and “The percentage of risk-reward sharing comes from the bidding documents”. Under “Step 4”, the details are “The design team in collaboration with client, consultant, and contractor’s team undertake the essential design and planning of process and product (i.e. building) together to be aware of their interdependencies”, “BIM is utilized for Essential Design”, “Target cost and time are used in the Essential Design”, and “Last planner system is used in the Essential Planning”. Under “Step 5”, the details are “After completion of the essential design and planning, visualizing and simulating the designed process and product (that is building) start” and “The purpose of visualization and simulation is to see how the building would work if constructed”. Under “Step 6”, the details are “The essential design and planning are revised and improved according to simulation results” and “This cycle of simulation and improvement repeats until the results meet the target cost and requirements of the building, specified in Step 2 and 4”. Under “Step 7”, the details are “The building is constructed according to the completed design and planning”, “Target management is actively pursued in the construction phase”, “Both contractor and design team actively look for any possibility for waste elimination and value maximization throughout construction”, “The changes in the design are documented”, and “Last Planner System, BIM (building information modelling), and Value Stream Mapping are used by the contractor and its team (including sub-contractors) for the planning and accomplishment of construction activities”. Under “Step 8”, the details are “The required quality inspections are performed to ensure that the completed building meets the client’s requirements”, “Building maintenance team are involved in the handover process”, “The contractor submits as-built drawings or B I M model of the completed building to the client”, and “The contractor shares the as-built drawings of the completed building with maintenance team”. Under “Step 9”, the details are “A full commissioning of the building’s energy system is undertaken”, “At the beginning of the commissioning, a user induction is performed to provide necessary training for the building occupants”, and “The building’s energy performance during commissioning is monitored and documented”. Under “Step 10”, the details are “The building’s energy performance after commissioning is monitored and compared with its performance during commissioning”, “The building’s energy performance after commissioning is compared also with the set goals in the project definition and design”, “The building’s energy performance is documented in a database for using it in the design of future relevant buildings”, and “The implementation of required maintenance and optimization, arising from utilization of the building, is planned”. Under “Step 11”, the details are “The planned maintenance and optimizations are performed”, “The building’s energy performance during and after the planned maintenance and optimizations is monitored and documented”, “The building’s energy performance is documented in a database for using it in the design of future relevant buildings”, “Monitoring and optimization of the building operation is continued, particularly until the energy consumption target of the building is realized”, and “Planning of future renovations is carried out regularly”. At the bottom, a row of rectangular text boxes lists the outputs. A rectangular box is labeled “Output of Step 1” and contains “1. General specifications of the desired building”, “2. The estimated time and cost of completing the building”, and “3. Client’s available money and time”. A rectangular box is labeled “Output of Step 2” and contains “1. Pre-design documents”, “2. Results of the detailed feasibility study”, “3. Client’s decision for funding or not funding the project”, “4. Bidding documents (if the clients decides to fund the project)”, “5. Proposed percentage of risk-reward sharing”, and “6. Explanation of contractor’s tasks in building’s operation for 10 or 20 years”. A rectangular box is labeled “Output of Step 3” and contains “1. Design team’s contract”, “2. Contractor selection”, “3. Agreed risk-reward sharing percentages for the client, contractor and design team”, and “4. Signed Collaboration Framework between the project parties”. A rectangular box is labeled “Output of Step 4, 5 and 6” and contains “1. The defined target time for the essential design”, “2. The defined target cost (i.e., equal or less than client's budget) for constructing the building”, “3. Essential design documents for starting the construction activities”, “4. The master schedule and phase plan for construction activities”, and “5. Records of the conducted simulations and improvement made in the essential design”. A rectangular box is labeled “Output of Step 7” and contains “1. Constructed building”, “2. Lessons learned from construction phase”, and “3. As-built drawings or BIM model of the completed building”. A rectangular box is labeled “Output of Step 8” and contains “1. Results of completed building’s quality inspections” and “2. Payments related to the shared risk-reward in the project for both the design team and contractor”. A rectangular box is labeled “Output of Step 9” and contains “1. Full commissioning of the completed building’s energy system”, “2. Building’s energy performance data in the commissioning”, and “3. Evidence of provided training for building users”. A rectangular box is labeled “Output of Step 10” and contains “1. Documented lessons learned of the planned and realized energy performance of the building”, “2. An up-to-date database of completed buildings’ energy performance”, and “3. Plan for required maintenance and optimizations”. A rectangular box is labeled “Output of Step 11” and contains “1. Reports of performed maintenance and optimizations”, “2. Data of changes in building performance after completed maintenance and optimizations”, and “3. Plan of future renovations”.

Detailed version of collaborative and life cycle-based project delivery model (CLCPDM) for sustainable building construction

Figure 7
A detailed tabular figure shows a collaborative and life-cycle-based project delivery model.The tabular figure consists of a wide horizontal rectangular title bar at the top center that reads “Collaborative and Life Cycle-based Project Delivery Model (C L C P D M) for Sustainable Building Construction (Detailed Version)”. Below this, a horizontal bar is divided into two parts: “Project Life Cycle” on the left and “Building Life Cycle” on the right. Below these, a row of rectangular boxes represents specific sub-phases. Under “Project Life Cycle”, the boxes are “Project Definition”, “Pre-design and Feasibility study”, “Tendering”, “Essential Design and Planning”, “Construction (plus complementary design and planning)”, and “Closure and Handover”. Under “Building Life Cycle”, a larger header reads “Building Commissioning, Use, and Management”, which contains sub-phases “Commissioning and User Induction”, “Operation”, and “Maintenance, Optimization and Renovation planning”. Below the sub-phases, a row of rectangular boxes details eleven specific steps. A rectangular box is labeled “Step 1 Exploring the client’s needs and limits”. A rectangular box is labeled “Step 2 Defining the project and its delivery team in further detail”. A rectangular box is labeled “Step 3 Forming the collaborative project delivery team”. A rectangular box is labeled “Step 4 Designing and planning the process and product together”. A rectangular box is labeled “Step 5 Visualizing and simulating to check functionality”. A rectangular box is labeled “Step 6 Improving the design and plan”. A rectangular box is labeled “Step 7 Active target management and documenting the construction process”. A rectangular box is labeled “Step 8 Connecting the project and building’s life cycle”. A rectangular box is labeled “Step 9 Commissioning and tuning the building’s energy system”. A rectangular box is labeled “Step 10 Utilizing the building, documenting its performance, and planning required maintenance and optimizations”. A rectangular box is labeled “Step 11 Performing the planned maintenance and optimizations, monitoring building performance, and planning future renovations”. The row below the numbered steps contains comprehensive descriptions for the entire life cycle. Under “Step 1”, the details are “The client hires a consultant to assist him or her in the project definition”, “The consultant explores client’s needs and limits through answering following questions:”, “What type of building does the client need question mark”, “How is the building going to be used question mark”, “How much money and time would be needed to construct such a building question mark”, “Dose the client have the required time and money question mark”, and “If the answer to the questions is YES, then client approves STEP 1”. Under “Step 2”, the details are “The consultant hires a design team to develop the pre-design documents in active collaboration with the client and its consultant”, “The pre-design documents include, but not limited to, the building’s specifications and requirements (eample, energy consumption target, required energy system)”, “When the pre-design is done, the feasibility questions in STEP 1 are answered again, this time, based on the pre-design documents”, “If the answer is YES, then the client asks the consultant to preparing the bidding documents”, and “The bidding documents must include, among other things, the percentage for the risk-reward sharing and clearly explain contractor’s responsibilities for the maintenance of the constructed building”. Under “Step 3”, the details are “The client first awards the design team’s contract”, “Then, the tendering is conducted to select a competent contractor”, “The competent contractor must meet the explained eligibility criteria in the bid documents and offer a price which is not too low or high”, “A collaboration framework is prepared and signed by project parties to guide their collaboration in the project”, “Regardless of the contract type used for the project, it should contain the risk-reward sharing mechanism”, and “The percentage of risk-reward sharing comes from the bidding documents”. Under “Step 4”, the details are “The design team in collaboration with client, consultant, and contractor’s team undertake the essential design and planning of process and product (i.e. building) together to be aware of their interdependencies”, “BIM is utilized for Essential Design”, “Target cost and time are used in the Essential Design”, and “Last planner system is used in the Essential Planning”. Under “Step 5”, the details are “After completion of the essential design and planning, visualizing and simulating the designed process and product (that is building) start” and “The purpose of visualization and simulation is to see how the building would work if constructed”. Under “Step 6”, the details are “The essential design and planning are revised and improved according to simulation results” and “This cycle of simulation and improvement repeats until the results meet the target cost and requirements of the building, specified in Step 2 and 4”. Under “Step 7”, the details are “The building is constructed according to the completed design and planning”, “Target management is actively pursued in the construction phase”, “Both contractor and design team actively look for any possibility for waste elimination and value maximization throughout construction”, “The changes in the design are documented”, and “Last Planner System, BIM (building information modelling), and Value Stream Mapping are used by the contractor and its team (including sub-contractors) for the planning and accomplishment of construction activities”. Under “Step 8”, the details are “The required quality inspections are performed to ensure that the completed building meets the client’s requirements”, “Building maintenance team are involved in the handover process”, “The contractor submits as-built drawings or B I M model of the completed building to the client”, and “The contractor shares the as-built drawings of the completed building with maintenance team”. Under “Step 9”, the details are “A full commissioning of the building’s energy system is undertaken”, “At the beginning of the commissioning, a user induction is performed to provide necessary training for the building occupants”, and “The building’s energy performance during commissioning is monitored and documented”. Under “Step 10”, the details are “The building’s energy performance after commissioning is monitored and compared with its performance during commissioning”, “The building’s energy performance after commissioning is compared also with the set goals in the project definition and design”, “The building’s energy performance is documented in a database for using it in the design of future relevant buildings”, and “The implementation of required maintenance and optimization, arising from utilization of the building, is planned”. Under “Step 11”, the details are “The planned maintenance and optimizations are performed”, “The building’s energy performance during and after the planned maintenance and optimizations is monitored and documented”, “The building’s energy performance is documented in a database for using it in the design of future relevant buildings”, “Monitoring and optimization of the building operation is continued, particularly until the energy consumption target of the building is realized”, and “Planning of future renovations is carried out regularly”. At the bottom, a row of rectangular text boxes lists the outputs. A rectangular box is labeled “Output of Step 1” and contains “1. General specifications of the desired building”, “2. The estimated time and cost of completing the building”, and “3. Client’s available money and time”. A rectangular box is labeled “Output of Step 2” and contains “1. Pre-design documents”, “2. Results of the detailed feasibility study”, “3. Client’s decision for funding or not funding the project”, “4. Bidding documents (if the clients decides to fund the project)”, “5. Proposed percentage of risk-reward sharing”, and “6. Explanation of contractor’s tasks in building’s operation for 10 or 20 years”. A rectangular box is labeled “Output of Step 3” and contains “1. Design team’s contract”, “2. Contractor selection”, “3. Agreed risk-reward sharing percentages for the client, contractor and design team”, and “4. Signed Collaboration Framework between the project parties”. A rectangular box is labeled “Output of Step 4, 5 and 6” and contains “1. The defined target time for the essential design”, “2. The defined target cost (i.e., equal or less than client's budget) for constructing the building”, “3. Essential design documents for starting the construction activities”, “4. The master schedule and phase plan for construction activities”, and “5. Records of the conducted simulations and improvement made in the essential design”. A rectangular box is labeled “Output of Step 7” and contains “1. Constructed building”, “2. Lessons learned from construction phase”, and “3. As-built drawings or BIM model of the completed building”. A rectangular box is labeled “Output of Step 8” and contains “1. Results of completed building’s quality inspections” and “2. Payments related to the shared risk-reward in the project for both the design team and contractor”. A rectangular box is labeled “Output of Step 9” and contains “1. Full commissioning of the completed building’s energy system”, “2. Building’s energy performance data in the commissioning”, and “3. Evidence of provided training for building users”. A rectangular box is labeled “Output of Step 10” and contains “1. Documented lessons learned of the planned and realized energy performance of the building”, “2. An up-to-date database of completed buildings’ energy performance”, and “3. Plan for required maintenance and optimizations”. A rectangular box is labeled “Output of Step 11” and contains “1. Reports of performed maintenance and optimizations”, “2. Data of changes in building performance after completed maintenance and optimizations”, and “3. Plan of future renovations”.

Detailed version of collaborative and life cycle-based project delivery model (CLCPDM) for sustainable building construction

Close modal
Table 1

Main findings of the previous studies addressing success factors, trust and relationship and team integration in the context of collaborative project delivery models

Common themeDelivery modelMain findingsReference
Success factors and barriersAlliance
  • According to the previous studies the common success factors for alliance, partnering and IPD include appropriate and relevant contract, commitment to win–win philosophy, collaboration and cooperation, equality, incentive system, open communication, mutual trust, selecting competent people for the project

Bellini et al. (2016) 
PartneringHietajärvi et al. (2017a) 
IPDKent and Becerik-Gerber (2010) 
Ling et al. (2020) 
Lichtig (2005) 
Moradi and Kähkönen (2022) 
Nevstad et al. (2018) 
Chan et al. (2004 a, b) 
Cheng and Li (2004) 
Cho et al. (2010) 
MohammadHasanzadeh et al. (2014) 
Ng et al. (2002) 
Raslim and Mustaffa (2017) 
Whang et al. (2019) 
Young et al. (2016) 
Zhang and Kumaraswamy (2001) 
LPD
  • Success factors for lean project delivery include a cooperative design phase including cross functional team members, supportive contract and procurement strategy, incorporating behavioral lean-based principles in the contract, fair share of risk/reward, incentive system, a combination of price competition, and competence-based criteria for selecting project team

Heidemann and Gehbauer (2010) 
Trust and relationship between project partiesAlliance
  • Trust, adequate resources, open communication, coordination, integration, top management support, creativity, and goal alignment are critical factors for the successful formation, operation, and evaluation phases of the relationship

Love et al. (2010) 
  • Free-flowing, integrated and bi-directional communication is important for having good client–contractor relationships in the alliance projects

Lloyd and Varey (2003) 
  • Informal socialization mechanisms are useful in both building relational capital (in terms of developing personal relationships, trust, and integration) in the tendering phase and enhancing it in the development phase, whereas formal socialization mechanisms (e.g. co-locational space) are mainly effective in the development phase for maintaining relational capital

Aaltonen and Turkulainen (2018) 
Partnering
  • There are four types of owner-contractor relationships: (1) Adversarial, (2) Guarded adversarial, (3) Informal partners, and (4) Project partners

Drexler and Larson (2000) 
  • The stability of working relationships varies depending upon how the relationship commence. Projects that begin as formal partnerships are the most stable with over two-thirds ending as they began

  • The reasons for a declining relationship include unclear contracts and resulting litigation, changes in scope and schedules, personnel, failure to perform, lack of trust, and underbidding contracts

  • The reasons for improving relationships include trust and positive relationships, shared goals, teamwork and communication, personnel changes and the presence of a clear contract

  • Developing a tool for supporting partnering relation management in the implementation of construction projects using AHP and Fuzzy AHP methods

Radziszewska-Zielina and Szewczyk (2016) 
  • Transformation towards strategic partnering should preferably be based on extension of project partnering in two dimensions: extension in time through relationship development with suppliers and extension in space through increasing network orientation across projects

Sundquist et al. (2018) 
Team integrationAlliance
  • Key indicators of alliance team integration, which include team leadership, trust and respect, single team focus on project objectives and key results areas, collective understanding, commitment from project alliance board, the creation of single and collocated alliance team, and free flow communication

Ibrahim et al. (2015a, b) 
Ibrahim et al. (2016) 
Ibrahim et al. (2018) 
  • Everyday dynamics are very important for managing integration. They also stated that project complexity and a lack of previous collaboration experience among participants increase the uncertainty of the project and create a need for high levels of integration

Hietajärvi et al. (2017b, c) 
IPD
  • Collaboration contributes toward team integration

Lee et al. (2013) 
  • Frequent interaction of project parties in IPD projects foster mutual trust and improve collaboration and team integration

Franz et al. (2017) 
Zhang et al. (2016) 
  • Factors such as the early involvement of the contractor in the project can be useful for team integration

Mollaoglu-Korkmaz et al. (2013) 
Alliance, IPD, LPD, and partnering
  • Establishing the equality and mutual respect between project team members is the fundamental step toward trust development and open communication

Moradi et al. (2022) 
  • Equality is the fair share of organizational and contractual authority, responsibility, risk, and reward between project parties and team members throughout the project

  • Equality and mutual respect together with mutual trust and open communication seem to be the prerequisites for constructive collaboration and cooperation between project team members

  • Achieving team integration requires collaboration (working together) and cooperation (exchanging information) between project participants for the best of the project

Source(s): Authors’ own work

Table 2

Interviewees’ discipline, role and their latest project’s type, budget and duration

Interviewee groupRole in the latest projectType of the latest projectBudget of the latest project’s
Project management (client)Project managerBuilding construction€150,000,000
Site managerBuilding renovation€52,000,000
Project managerBuilding construction€7,000,000
Project managerBuilding renovation€10,000,000
Project managerBuilding renovation€10,000,000
Design managementGeothermal heating design consultantBuilding construction€30,000,000
Principal HVAC designerBuilding construction€75,000,000
ArchitectBuilding construction€140,000,000
Structural designerBuilding construction€40,000,000
Design managerBuilding renovation€2,000,000
Project management (contractor)Design and sustainability managerBuilding renovation€80,000
Project managerBuilding construction€40,000,000
Project managerBuilding renovation€1,000,000
Project managerBuilding construction€90,000,000
Head of Project Business UnitBuilding construction€110,000,000
Property management (i.e. building operation and maintenance)Service delivery managerOngoing maintenance of existing buildings€300,000
Real estate managerBuilding construction€300,000,000
Real estate managerOngoing maintenance of existing buildings€60,000
Service unit directorOngoing maintenance of existing buildings€200,000
Chief strategy officerOngoing maintenance of existing buildings€500,000
Senior Specialist, indoor airOngoing maintenance of existing buildings€200,000,000

Source(s): Authors’ own work

Table 3

Project delivery-related challenges and solutions of realizing energy efficiency

Challenge/barrier
Lack of/inadequate involvement of HVAC contractors and operation/maintenance people in the project definition and design phase
Fragmented (i.e. divided/isolated) procurement, project delivery, and maintenance process (multiple contracts) of energy efficient systems
Dominance of low-price criteria in the tendering process for selecting contractors which usually have low capacity to deliver their promises
Solution/enabler
Life cycle contract
Collaborative project delivery model
Involving building services people in the project definition and design phase
Involvement of client and its representative (consultant) from project definition phase until the end of the project
Early definition of the use of the building and its spaces

Source(s): Authors’ own work

Table A1

Complete list of the project delivery related challenges and solutions

Representing challenge/barrierReferences
Lack of/inadequate involvement of HVAC contractors and operation/maintenance people in the project definition and design phaseINT 2 (PropertyMgmt)
INT 1 (PMContractor), INT 6 (PropertyMgmt), INT 4 (PMContractor)
Fragmented (i.e. divided/isolated) procurement, project delivery, and maintenance process (multiple contracts) of energy efficient systemsINT 1 (PMContractor), INT 2 (DM)
INT 5 (PMContractor)
INT 1 (PMClient)
Dominance of low-price criteria in the tendering process for selecting contractors which usually has low capacity to deliver their promisesINT 1 (DM), INT 5 (PMContractor)
Construction phase errors (e.g. problems in building structure, building services)INT 5 (PropertyMgmt)
Deviation between designed and purchased/installed devices/equipment by contractor for securing his/her own benefitsINT 3 (PMClient)
Delay and low quality in the work of low-capacity contractors, selected solely because of the low priceINT 5 (PMContractor)
Delivery problems in the supply chain of required equipmentINT 3 (DM)
Difficulty of diagnosing construction errors in use phase of the building with regard to their impact of energy efficiency (for instance in terms of air tightness)INT 5 (PropertyMgmt)
High variation between the design and the execution of building services systems (especially heating part)INT 3 (DM)
High variability among resources of different companies in projects with fragmented delivery processesINT 5 (PMContractor)
Inadequate investment of time and cost in project definition and design/planning phasesINT 4 (PMContractor)
Lack of integrated and directed efforts between people, processes and technologyINT 1 (PMContractor)
Lack of contracts with project and building life cycle responsibility and benefits for the key parties (including energy providers)INT 1 (PMContractor)
Low priority of energy efficiency as a goal in project definition phaseINT 2 (PMClient)
Lack of planning (in project definition and design phases) for details and processes of collecting and analyzing energy consumption data in the operation phaseINT 3 (PropertyMgmt)
Lack of standardized and routine process for design and implementation of hybrid energy systemsINT 4 (PMContractor)
Lack of attention to the delivery capacity (resource and competence), content of the offer (e.g. schedule) besides the priceINT 5 (PMContractor)
Scheduling issuesINT 3 (PMContractor)
Traditional contracting model (energy system providers are not involved and accountable for the performance of building energy system in the operation phase)INT 1 (PropertyMgmt)
Traditional contracts which foster isolated and fragmented workingINT 3 (PropertyMgmt)
Unreliable information flow between parties in the project definition, design, and construction phases about energy efficiency goalsINT 1 (PMClient)
Unavailability of required material/components due to the natural (e.g. corona pandemic) or political (war in Ukraine) crisesINT 5 (PMContractor)
Representing solution/enablerReferences
Life cycle contractINT 1 (PropertyMgmt)
INT 2 (PropertyMgmt)
INT 3 (DM)
INT 3 (PMClient)
INT 3 (PMContractor)
INT 3 (PropertyMgmt)
INT 4 (PMContractor)
INT 5 (DM)
INT 5 (PropertyMgmt)
INT 5 (PMContractor)
INT 5 (PMContractor)
INT 2 (DM)
Collaborative project delivery models (e.g., alliance)INT 1 (PMClient)
PMContractor
INT 2 (PMContractor)
INT 3 (DM)
Involving building services people in the project definition and design phaseINT 2 (PMContractor)
INT 2 (PropertyMgmt)
INT 3 (PMClient)
INT 4 (PMContractor)
Involvement of client and its representative (consultant) from project definition phase until the end of the projectINT 1 (DM)
INT 2 (PropertyMgmt)
INT 3 (PMClient)
Early definition of the use of building and its spacesINT 1 (PMContractor)
INT 3 (PMClient)
Applying a system thinking method in project definition phase to clarify the consequence of a change or choice about one aspect of the building on the other aspectsINT 3 (PMClient)
Creating more tempting incentives for achieving high energy efficiencyINT 4 (PMContractor)
Early definition and determination of the operational feature of the building for having an accurate and realistic estimation of energy consumptionINT 5 (PMContractor)
Flexible target setting for budgetINT 5 (PMClient)
Having a third-party inspector for assessing efficiency of building energy systemsINT 2 (PropertyMgmt)
Involvement of design team in the project definition phaseINT 1 (PMClient)
Identifying and analyzing the probability and impact of the risk of changing the use of the building space in the project definition phaseINT 3 (PMClient)
Involvement of maintenance experts in the design phaseINT 6 (PropertyMgmt)
Paying attention to the delivery capacity (resource and competence), content of the offer (e.g. schedule) besides the priceINT 5 (PMContractor)
Sufficient investment of time and cost in project definition phaseINT 3 (PMClient)
Updating the energy consumption target when there is a change in the design and use of building spaces andINT 3 (PMClient)
Using lessons learned of similar projects in the project definition and design phaseINT 2 (PMClient)

Source(s): Authors’ own work

Supplements

References

Aaltonen
,
K.
and
Turkulainen
,
V.
(
2018
), “
Creating relational capital through socialization in project alliances
”,
International Journal of Operations and Production Management
, Vol. 
38
No. 
6
, pp. 
1387
-
1421
, doi: .
Bellini
,
A.
,
Aarseth
,
W.
and
Hosseini
,
A.
(
2016
), “
Effective knowledge transfer in successful partnering projects
”,
Energy Procedia
, Vol. 
96
, pp. 
218
-
228
, doi: .
Boge
,
K.
,
Salaj
,
A.
,
Bjørberg
,
S.
and
Larssen
,
A.K.
(
2018
), “
Failing to plan – planning to fail: how early phase planning can improve buildings' lifetime value creation
”,
Facilities
, Vol. 
36
Nos
1/2
, pp. 
49
-
75
, doi: .
Boje
,
C.
,
Menacho
,
Á.J.H.
,
Marvuglia
,
A.
,
Benetto
,
E.
,
Kubicki
,
S.
,
Schaubroeck
,
T.
and
Gutiérrez
,
T.N.
(
2023
), “
A framework using BIM and digital twins in facilitating LCSA for buildings
”,
Journal of Building Engineering
, Vol. 
76
, 107232, doi: .
Borgstein
,
E.H.
,
Lamberts
,
R.
and
Hensen
,
J.L.M.
(
2018
), “
Mapping failures in energy and environmental performance of buildings
”,
Energy and Buildings
, Vol. 
158
, pp. 
476
-
485
, doi: .
Chan
,
A.P.
,
Chan
,
D.W.
,
Chiang
,
Y.H.
,
Tang
,
B.S.
,
Chan
,
E.H.
and
Ho
,
K.S.
(
2004a
), “
Exploring critical success factors for partnering in construction projects
”,
Journal of Construction Engineering and Management
, Vol. 
130
No. 
2
, pp. 
188
-
198
, doi: .
Chan
,
A.P.
,
Scott
,
D.
and
Chan
,
A.P.
(
2004b
), “
Factors affecting the success of a construction project
”,
Journal of Construction Engineering and Management
, Vol. 
130
No. 
1
, pp. 
153
-
155
, doi: .
Cheng
,
E.W.
and
Li
,
H.
(
2004
), “
Development of a practical model of partnering for construction projects
”,
Journal of Construction Engineering and Management
, Vol. 
130
No. 
6
, pp. 
790
-
798
, doi: .
Cho
,
K.
,
Hyun
,
C.
,
Koo
,
K.
and
Hong
,
T.
(
2010
), “
Partnering process model for public-sector fast-track design-build projects in Korea
”,
Journal of Management in Engineering
, Vol. 
26
No. 
1
, pp. 
19
-
29
, doi: .
Cozza
,
S.
,
Chambers
,
J.
and
Patel
,
M.K.
(
2020
), “
Measuring the thermal energy performance gap of labelled residential buildings in Switzerland
”,
Energy Policy
, Vol. 
137
, 111085, doi: .
Darrington
,
J.
(
2011
), “
Using a design-build contract for lean integrated project delivery
”,
Lean Construction Journal
, pp. 
85
-
91
,
available at:
 https://lean-construction-gcs.storage.googleapis.com/wp-content/uploads/2022/08/08161000/Design-build_contract_for_Lean_IPD.pdf
Drexler
,
J.A.
, Jr.
and
Larson
,
E.W.
(
2000
), “
Partnering: why project owner-contractor relationships change
”,
Journal of Construction Engineering and Management
, Vol. 
126
No. 
4
, pp. 
293
-
297
, doi: .
Engebø
,
A.
,
Lædre
,
O.
,
Young
,
B.
,
Larssen
,
P.F.
,
Lohne
,
J.
and
Klakegg
,
O.J.
(
2020
), “
Collaborative project delivery methods: a scoping review
”,
Journal of Civil Engineering and Management
, Vol. 
26
No. 
3
, pp. 
278
-
303
, doi: .
Forbes
,
L.H.
and
Ahmed
,
S.M.
(
2010
),
Modern Construction: Lean Project Delivery and Integrated Practices
,
CRC Press
,
Boca Raton, FL
,
ISBN: 9780429145278
.
Franz
,
B.
,
Leicht
,
R.
,
Molenaar
,
K.
and
Messner
,
J.
(
2017
), “
Impact of team integration and group cohesion on project delivery performance
”,
Journal of Construction Engineering and Management
, Vol. 
143
No. 
1
, doi: .
Frei
,
B.
,
Sagerschnig
,
C.
and
Gyalistras
,
D.
(
2017
), “
Performance gaps in Swiss buildings: an analysis of conflicting objectives and mitigation strategies
”,
Energy Procedia
, Vol. 
122
, pp. 
421
-
426
, doi: .
Häkkinen
,
T.
and
Belloni
,
K.
(
2011
), “
Barriers and drivers for sustainable building
”,
Building Research and Information
, Vol. 
39
No. 
3
, pp. 
239
-
255
, doi: .
Hanna
,
A.S.
(
2016
), “
Benchmark performance metrics for integrated project delivery
”,
Journal of Construction Engineering and Management
, Vol. 
142
No. 
9
, doi: .
Heidemann
,
A.
and
Gehbauer
,
F.
(
2010
), “
Cooperative project delivery in an environment of strict design-bid-build tender regulations
”,
Proceedings of the 18th Annual Conference of the International Group for Lean Construction (IGLC-18)
,
Perth
,
28-31 July
, pp. 
590
-
591
,
available at:
 https://iglc.net/Papers/Details/674
Hietajärvi
,
A.M.
,
Aaltonen
,
K.
and
Haapasalo
,
H.
(
2017a
), “
What is project alliance capability?
”,
International Journal of Managing Projects in Business
, Vol. 
10
No. 
2
, pp. 
404
-
422
, doi: .
Hietajärvi
,
A.M.
,
Aaltonen
,
K.
and
Haapasalo
,
H.
(
2017b
), “
Opportunity management in large projects: a case study of an infrastructure alliance project
”,
Construction Innovation
, Vol. 
17
No. 
3
, pp. 
340
-
362
, doi: .
Hietajärvi
,
A.M.
,
Aaltonen
,
K.
and
Haapasalo
,
H.
(
2017c
), “
Managing integration in infrastructure alliance projects: dynamics of integration mechanisms
”,
International Journal of Managing Projects in Business
, Vol. 
10
No. 
1
, pp. 
5
-
31
, doi: .
Ibrahim
,
C.K.I.C.
,
Costello
,
S.B.
and
Wilkinson
,
S.
(
2015a
), “
Establishment of quantitative measures for team integration assessment in alliance projects
”,
Journal of Management in Engineering
, Vol. 
31
No. 
5
, doi: .
Ibrahim
,
C.K.I.C.
,
Costello
,
S.B.
and
Wilkinson
,
S.
(
2015b
), “
Development of an assessment tool for team integration in alliance projects
”,
International Journal of Managing Projects in Business
, Vol. 
8
No. 
4
, pp. 
813
-
827
, doi: .
Ibrahim
,
C.K.I.C.
,
Costello
,
S.B.
and
Wilkinson
,
S.
(
2016
), “
Application of a team integration performance index in road infrastructure alliance projects
”,
Benchmarking: An International Journal
, Vol. 
23
No. 
5
, pp. 
1341
-
1362
, doi: .
Ibrahim
,
C.K.I.C.
,
Costello
,
S.B.
and
Wilkinson
,
S.
(
2018
), “
Making sense of team integration practice through the ‘lived experience’ of alliance project teams
”,
Engineering, Construction and Architectural Management
, Vol. 
25
No. 
5
, pp. 
598
-
622
, doi: .
Ibrahim
,
M.W.
,
Hanna
,
A.
and
Kievet
,
D.
(
2020
), “
Quantitative comparison of project performance between project delivery systems
”,
Journal of Management in Engineering
, Vol. 
36
No. 
6
, doi: .
Kent
,
D.C.
and
Becerik-Gerber
,
B.
(
2010
), “
Understanding construction industry experience and attitudes toward integrated project delivery
”,
Journal of Construction Engineering and Management
, Vol. 
136
No. 
8
, pp. 
815
-
825
, doi: .
Kibert
,
C.J.
(
2016
),
Sustainable Construction: Green Building Design and Delivery
,
John Wiley & Sons
.
Laconte
,
P.
and
Gossop
,
C.
(
2016
),
Sustainable Cities: Assessing the Performance and Practice of Urban Environments
,
Bloomsbury Publishing
,
New York, NY
,
ISBN: 978-1784532321
.
Lahdenperä
,
P.
(
2012
), “
Making sense of the multi-party contractual arrangements of project partnering, project alliancing and integrated project delivery
”,
Construction Management and Economics
, Vol. 
30
No. 
1
, pp. 
57
-
79
, doi: .
Lee
,
H.W.
,
Tommelein
,
I.D.
and
Ballard
,
G.
(
2013
), “
Energy-related risk management in integrated project delivery
”,
Journal of Construction Engineering and Management
, Vol. 
139
No. 
12
, A4013001, doi: .
Li
,
B.
and
Yao
,
R.
(
2012
), “
Building energy efficiency for sustainable development in China: challenges and opportunities
”,
Building Research and Information
, Vol. 
40
No. 
4
, pp. 
417
-
431
, doi: .
Liang
,
J.
,
Qiu
,
Y.
and
Hu
,
M.
(
2019
), “
Mind the energy performance gap: evidence from green commercial buildings
”,
Resources, Conservation and Recycling
, Vol. 
141
, pp. 
364
-
377
, doi: .
Lichtig
,
W.A.
(
2005
), “
Sutter health: developing a contracting model to support lean project delivery
”,
Lean Construction Journal
, Vol. 
2
, pp. 
105
-
112
, doi: .
Ling
,
F.Y.
,
Teo
,
P.X.
,
Li
,
S.
,
Zhang
,
Z.
and
Ma
,
Q.
(
2020
), “
Adoption of integrated project delivery practices for superior project performance
”,
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
, Vol. 
12
No. 
4
, 05020014, doi: .
Lloyd
,
H.L.
and
Varey
,
R.J.
(
2003
), “
Factors affecting internal communication in a strategic alliance project
”,
Corporate Communications: An International Journal
, Vol. 
8
No. 
3
, pp. 
197
-
207
, doi: .
Love
,
P.E.
,
Mistry
,
D.
and
Davis
,
P.R.
(
2010
), “
Price competitive alliance projects: identification of success factors for public clients
”,
Journal of Construction Engineering and Management
, Vol. 
136
No. 
9
, pp. 
947
-
956
, doi: .
Mahdavi
,
A.
,
Berger
,
C.
,
Amin
,
H.
,
Ampatzi
,
E.
,
Andersen
,
R.K.
,
Azar
,
E.
,
Barthelmes
,
V.M.
,
Favero
,
M.
,
Hahn
,
J.
,
Khovalyg
,
D.
and
Knudsen
,
H.N.
(
2021
), “
The role of occupants in buildings' energy performance gap: myth or reality?
”,
Sustainability
, Vol. 
13
No. 
6
, 3146, doi: .
Markus
,
A.A.
,
Hobson
,
B.W.
,
Gunay
,
H.B.
and
Bucking
,
S.
(
2022
), “
Does a knowledge gap contribute to the performance gap? Interviews with building operators to identify how data-driven insights are interpreted
”,
Energy and Buildings
, Vol. 
268
, 112238, doi: .
Mesa
,
H.A.
,
Molenaar
,
K.R.
and
Alarcón
,
L.F.
(
2019
), “
Comparative analysis between integrated project delivery and lean project delivery
”,
International Journal of Managing Projects in Business
, Vol. 
37
No. 
3
, pp. 
395
-
409
, doi: .
Mike
,
E.M.
,
Schmitz
,
A.
and
Netherton
,
L.M.
(
2015
), Real Estate Development.
Principles and Process
, (5th ed.) ,
ULI Urban Land Institute
,
Washington, DC
, ISBN:
978-0874203431
.
Miller
,
C.
,
Arjunan
,
P.
,
Kathirgamanathan
,
A.
,
Fu
,
C.
,
Roth
,
J.
,
Park
,
J.Y.
,
Balbach
,
C.
,
Gowri
,
K.
,
Nagy
,
Z.
,
Fontanini
,
A.D.
and
Haberl
,
J.
(
2020
), “
The ASHRAE great energy predictor III competition: overview and results
”,
Science and Technology for the Built Environment
, Vol. 
26
No. 
10
, pp. 
1427
-
1447
, doi: .
MohammadHasanzadeh
,
S.
,
Hosseinalipour
,
M.
and
Hafezi
,
M.
(
2014
), “
Collaborative procurement in construction projects performance measures, case study: partnering in Iranian construction industry
”,
Procedia - Social and Behavioral Sciences
, Vol. 
119
, pp. 
811
-
818
, doi: .
Mollaoglu-Korkmaz
,
S.
,
Swarup
,
L.
and
Riley
,
D.
(
2013
), “
Delivering sustainable, high-performance buildings: influence of project delivery methods on integration and project outcomes
”,
Journal of Management in Engineering
, Vol. 
29
No. 
1
, pp. 
71
-
78
, doi: .
Moradi
,
S.
and
Kähkönen
,
K.
(
2022
), “
Success in collaborative construction through the lens of project delivery elements
”,
Built Environment Project and Asset Management
, Vol. 
12
No. 
6
, pp. 
973
-
991
, doi: .
Moradi
,
S.
and
Sormunen
,
P.
(
2022
), “
Lean and sustainable project delivery in building construction: development of a conceptual framework
”,
Buildings
, Vol. 
12
No. 
10
, 1757, doi: .
Moradi
,
S.
and
Sormunen
,
P.
(
2023
), “
Revisiting the concept of waste and its causes in construction from analytical and conceptual perspectives
”,
Construction Management and Economics
, Vol. 
41
No. 
8
, pp. 
621
-
633
, doi: .
Moradi
,
S.
,
Kähkönen
,
K.
,
Klakegg
,
O.J.
and
Aaltonen
,
K.
(
2021a
), “
A competency model for the selection and performance improvement of project managers in collaborative construction projects: behavioral studies in Norway and Finland
”,
Buildings
, Vol. 
11
No. 
4
, p.
4
, doi: .
Moradi
,
S.
,
Kähkönen
,
K.
,
Klakegg
,
O.
and
Aaltonen
,
K.
(
2021b
), “
Profile of project managers' competencies for collaborative construction projects
”, in
Scott
,
L.
and
Neilson
,
C.J.
(Eds),
Proceedings of the 37th Annual ARCOM Conference
,
6-7 September
,
Association of Researchers in Construction Management
, pp. 
350
-
359
,
available at:
 https://www.arcom.ac.uk/-docs/archive/2021-Indexed-Papers.pdf
Moradi
,
S.
,
Kähkönen
,
K.
and
Sormunen
,
P.
(
2022
), “
Analytical and conceptual perspectives toward behavioral elements of collaborative delivery models in construction projects
”,
Buildings
, Vol. 
12
No. 
3
, p.
316
, doi: .
Moradi
,
S.
,
Hirvonen
,
J.
and
Sormunen
,
P.
(
2023
), “
A qualitative and life cycle-based study of the energy performance gap in building construction: perspectives of Finnish project professionals and property maintenance experts
”,
Building Research and Information
, pp. 
1
-
13
, doi: .
Mousavi
,
S.
,
Marroquín
,
M.G.V.
,
Hajiaghaei-Keshteli
,
M.
and
Smith
,
N.R.
(
2023
), “
Data-driven prediction and optimization toward net-zero and positive-energy buildings: a systematic review
”,
Building and Environment
, Vol. 
242
, 110578, doi: .
Nevstad
,
K.
,
Børve
,
S.
,
Karlsen
,
A.T.
and
Aarseth
,
W.
(
2018
), “
Understanding how to succeed with project partnering
”,
International Journal of Managing Projects in Business
, Vol. 
11
No. 
4
, pp. 
1044
-
1065
, doi: .
Ng
,
S.T.
,
Rose
,
T.M.
,
Mak
,
M.
and
Chen
,
S.E.
(
2002
), “
Problematic issues associated with project partnering—the contractor perspective
”,
International Journal of Project Management
, Vol. 
20
No. 
6
, pp. 
437
-
449
, doi: .
Oakland
,
J.S.
and
Marosszeky
,
M.
(
2017
),
Total Construction Management: Lean Quality in Construction Project Delivery
,
Routledge
,
Abingdon
,
ISBN: 9781315694351
.
Qian
,
Q.K.
,
Chan
,
E.H.
and
Khalid
,
A.G.
(
2015
), “
Challenges in delivering green building projects: unearthing the transaction costs (TCs)
”,
Sustainability
, Vol. 
7
No. 
4
, pp. 
3615
-
3636
, doi: .
Radziszewska-Zielina
,
E.
and
Szewczyk
,
B.
(
2016
), “
Supporting partnering relation management in the implementation of construction projects using AHP and fuzzy AHP methods
”,
Procedia Engineering
, Vol. 
161
, pp. 
1096
-
1100
, doi: .
Raslim
,
F.M.
and
Mustaffa
,
N.E.
(
2017
), “
The success factors of relationship-based procurement (RBP) in Malaysia
”,
International Journal of Civil Engineering and Technology
, Vol. 
8
, pp. 
1616
-
1625
,
available at:
 http://www.iaeme.com/ijciet/issues.asp?JType=IJCIET&VType=8&IType=8
Rasmussen
,
H.L.
and
Jensen
,
P.A.
(
2020
), “
A facilities manager's typology of performance gaps in new buildings
”,
Journal of Facilities Management
, Vol. 
18
No. 
1
, pp. 
71
-
87
, doi: .
Saunders
,
M.N.K.
,
Lewis
,
P.
and
Thornhill
,
A.
(
2019
),
Research Methods for Business Students
, (8th ed.) ,
Pearson Education
,
Harlow
,
ISBN: 9781292208787
.
Spudys
,
P.
,
Afxentiou
,
N.
,
Georgali
,
P.Z.
,
Klumbyte
,
E.
,
Jurelionis
,
A.
and
Fokaides
,
P.
(
2023
), “
Classifying the operational energy performance of buildings with the use of digital twins
”,
Energy and Buildings
, Vol. 
290
, 113106, doi: .
Sundquist
,
V.
,
Hulthén
,
K.
and
Gadde
,
L.E.
(
2018
), “
From project partnering towards strategic supplier partnering
”,
Engineering, Construction and Architectural Management
, Vol. 
25
No. 
3
, pp. 
358
-
373
, doi: .
Whang
,
S.-W.
,
Park
,
K.S.
and
Kim
,
S.
(
2019
), “
Critical success factors for implementing integrated construction project delivery
”,
Engineering, Construction and Architectural Management
, Vol. 
26
No. 
10
, pp. 
2432
-
2446
, doi: .
Willan
,
C.
,
Hitchings
,
R.
,
Ruyssevelt
,
P.
and
Shipworth
,
M.
(
2020
), “
Talking about targets: how construction discourses of theory and reality represent the energy performance gap in the United Kingdom
”,
Energy Research and Social Science
, Vol. 
64
, 101330, doi: .
Yılmaz
,
D.
,
Tanyer
,
A.M.
and
Toker
,
İ.D.
(
2023
), “
A data-driven energy performance gap prediction model using machine learning
”,
Renewable and Sustainable Energy Reviews
, Vol. 
181
, 113318, doi: .
Young
,
B.
,
Hosseini
,
A.
and
Lædre
,
O.
(
2016
), “
The characteristics of Australian infrastructure alliance projects
”,
Energy Procedia
, Vol. 
96
, pp. 
833
-
844
, doi: .
Zhang
,
X.
and
Kumaraswamy
,
M.M.
(
2001
), “
Procurement protocols for public-private partnered projects
”,
Journal of Construction Engineering and Management
, Vol. 
127
No. 
5
, pp. 
351
-
358
, doi: .
Zhang
,
L.
,
Cheng
,
J.
and
Fan
,
W.
(
2016
), “
Party selection for integrated project delivery based on interorganizational transactive memory system
”,
Journal of Construction Engineering and Management
, Vol. 
142
No. 
3
, doi: .
Zou
,
P.X.
,
Xu
,
X.
,
Sanjayan
,
J.
and
Wang
,
J.
(
2018
), “
Review of 10 years research on building energy performance gap: life-cycle and stakeholder perspectives
”,
Energy and Buildings
, Vol. 
178
, pp. 
165
-
181
, doi: .

Languages

or Create an Account

Close Modal
Close Modal