Purpose

Researchers in many countries have long argued that a harmful culture of long work hours and working weeks has become normalized in the construction industry. This has many negative impacts of workers' work-life balance, health and wellbeing, relationships and organizational outcomes. A shorter working week has been promoted by many researchers as one part of the solution to this problem. The purpose of this paper is to critique this debate and present the results of a large-scale empirical study into the pros and cons of a shorter working week in the Australian construction industry.

Design/methodology/approach

This paper investigates the individual and organizational pros and cons of a shorter working week based on the results of a survey (N = 1,475) and interviews (N = 111) with a representative sample of people and firms from across the Australian construction industry.

Findings

The findings show that widespread claims about the work-life balance benefits of a shorter working week should be treated with caution. The pros and cons of a shorter working week are highly contingent and vary over time, from project-to-project and person-to-person depending on a wide range of factors such as the shorter working week model employed, people's personal circumstances and life preferences, age, gender, job, marital status, wider economic conditions and the culture, nature and types of organizations they work for and projects they work on.

Originality/value

This research addresses the paucity of large-scale multi-method empirical research into the pros and cons of a shorter working week. It questions the overwhelmingly positive nature of this debate and highlights several methodological limitations with existing research. Contrary to most existing research, it concludes that the jury is still out on the pros and cons of a shorter working week and that the development of effective evidence-based policy in this area requires much more research across a variety of shorter week scenarios and contexts.

Research on shorter working weeks can be traced back to economic debates about how to manage the financial and social impacts of major economic crises such as the 1930s great depression (Carver, 1936; Roos, 1935; Brouwer, 1957). Since then, the debate has broadened to address contemporary socio-economic challenges such as workers' work-life balance and health and wellbeing (Stronge and Harper, 2019; Schor et al., 2022; Lewis et al., 2023), structural labour market inequalities (Stronge and Lewis, 2021; Olsaretti and Kalender, 2016) and improving organizational effectiveness and workplace sustainability (Briem and Olafsson, 2015; Golden, 2010; Pang, 2022; Kotlowska, 2024). However, the results of research about the benefits of shorter working weeks are complex and contradictory. While many recent studies claim significant benefits with few downsides (Schor et al., 2022; Lewis et al., 2023; 4 Day Week Global, 2023), others raise concerns about research reliability and validity (Veal, 2023), unintended consequences such as poorer safety, reduced productivity and increasing social inequality (Spencer, 2024) and numerous intervening factors which can affect the outcomes of a shorter working week in both negative and positive ways (Backmann et al., 2024; Mullens and Glorieux, 2024; Kamerade et al., 2020; Briem and Olafsson, 2015). Most recently Joyeaux's (2025) policy evaluation of Iceland's formative 4-day working week experiment between 2015 and 2019, challenges the increasingly accepted assumption that a shorter working week represents a solution to the growing levels of work-related health, economic and social challenges faced by contemporary society.

This empirical uncertainty about the merits of a shorter working week are also evident in construction industry research. As both Tijani et al. (2022) and Adah et al. (2023) show, despite many claims about the universal impacts of a shorter working week in construction, research is still inconclusive, embryonic and lacking large-scale empirical samples which are representative of the industry's diversity of roles, projects and organizations. The aim of this paper is to respond to this gap in research by reporting the results of a large-scale empirical research project which involved surveys and interviews with people working across the Australian construction industry. Specifically, two research questions are explored.

  1. What are the pros and cons of a shorter working week for employees in the Australian construction industry and what is the preferred model?

  2. What are the pros and cons of a shorter working week for employers in the Australian construction industry and what is the preferred model?

We defined a shorter working week as any requirement to work fewer days than the construction industry norm. In the context of the Australian construction industry, this industry norm is a 6-day week of 10 or more hours per day and 4–8 h on Saturday with an occasional Sunday (Lingard and Francis, 2004; Lingard et al., 2021; Crook and Tessler, 2021). This standard working week is considerably longer than in other industries and is mirrored in other countries. For example, 13% of construction workers in the UK report working 60 h per week, which is more than 5 h more per week than the average worker (Hertzog-Young, 2021).

This paper commences with a review of research relating to pros and cons of shorter working weeks within and outside the construction industry. After describing the methodology employed to explore the above research questions, the research results are reported and discussed in relation to extant research with the aim of advancing empirical understanding of these important questions. The paper concludes by identifying several new contributions to the advancement of existing shorter working week research in the field of construction and more widely. These contributions include: raising new questions about the widely assumed universal benefits of shorter working weeks; distinguishing between the merits and risks of hard and soft five-day week models; highlighting the largely ignored interdependence of worker and business risks; emphasizing the dangers of treating the construction workforce as homogeneous group and focussing primarily; and the limitations of overly focussing on individual outcomes at the expense of organizational outcomes. The paper finishes with some practical recommendations for managers and policy-makers about the most beneficial shorter working week model to improve health and wellbeing in the construction industry by emphasizing the need for equitable flexibility or what we call a “soft 5-day week” which we find best balances the interests of employees, employers and clients.

The contemporary shorter working week debate is being driven by claims that it represents a potential solution to several current concerns around the changing nature of work within and outside the construction industry. For example, increasing numbers of people are reporting feeling overworked, with many studies reporting direct links between long working hours and poor physical and mental health, relationship quality and life happiness (Wong et al., 2019; World Health Organization and International Labour Organization, 2021; Lefrançois and Trottier, 2022). A recent UK report by O'Halloran and Thomas (2024) argued that longer working hours are a far greater threat to national productivity and health and wellbeing than increasing absenteeism and recommended that the UK move towards a “health-led” economy. In Australia, where this research was undertaken, the evidence shows that levels of unpaid overtime are increasing and that a healthy work life balance is an increasingly unachievable aspiration for many working Australians (Standing Committee on Economy and Gender and Economic Equality, 2021). This trend is reflected in the international construction industry, with numerous international researchers linking long hours of work to poor mental and physical health, high levels of burnout, work-to-family conflict, deterioration of personal, family and marital relationships, sleep problems, alcohol abuse and antisocial behaviours (Francis et al., 2006; Bowen et al., 2018; Downey and Stough, 2018; Kotera et al., 2019; Hanna and Markam, 2019; Holdsworth et al., 2020; Bowen and Zhang, 2020; Crook and Tessler, 2021; Lingard and Turner, 2022).

The shorter working debate is also being driven by several gender-related concerns in the workplace. These include: a need for greater gender diversity and equality; increasing ender segregation; the extra pressures that long working hours place on women who often carry the additional burden of caring responsibilities; the increasing numbers of single parents, particularly mothers; changing attitudes towards men and women's role in society and the sharing of domestic and caring responsibilities; the decline of the traditional male breadwinner model; and higher qualification levels among women (Standing Committee on Economy and Gender and Economic Equality, 2021; International Labour Organization, 2022; Commonwealth of Australia, 2023). Again, this is reflected in the construction industry. For example, the Committee for Economic Development of Commonwealth of Australia (2023) recently labelled construction the most gender segregated industry in Australia and numerous researchers have linked this to its culture of long working hours and presenteeism (Townsend et al., 2011; Holdsworth et al., 2020; Galea et al., 2020).

Technological advancements and the global shift towards flexible and hybrid work have also driven calls for a shorter working week. As the World Economic Forum (2020) noted, rapid advances in digital technologies around the world are fundamentally changing the nature of work and the opportunities for people to work more flexibly. However, they also present increase risks of remote worker monitoring, constant connectivity and unmonitored overworking which could undermine worker health, safety and wellbeing. While the construction remains digitally immature compared to other sectors, McKinsey & Company (2020) predicts that new technologies will also fundamentally disrupt the way that people work in the industry.

Most recently, the COVID pandemic accelerated already changing employee expectations about the nature of work with construction among those most impacted by the post-pandemic “Great Resignation” (Morgan, 2023). In Australia, the pandemic forced about 40% of workers to experiment with working from home (Productivity Commission, 2021) and in Germany many jobs were saved by companies allowing their employees to reduce their hours of work (international Labour Organization, 2022). These forced experiments have subsequently prompted longer trials of shorter and hybrid working weeks across many industry sectors including construction (International Labour Organization, 2022; World Economic Forum, 2020; Mullens and Glorieux, 2024).

In response to the above trends an increasing number of construction companies are experimenting with shorter working week models, with numerous researchers advocating benefits to people's work life balance, physical and mental health and wellbeing, relationship quality and performance in work (see Townsend et al., 2006a, b, c, 2012; Lingard et al., 2007, 2008, 2021, 2024; Lingard and Francis, 2009; Berman, 2009; Bradley et al., 2010; Brown et al., 2010; Galea et al., 2020; Hertzog-Young, 2021; Lingard and Turner, 2022). These highly positive results are based on several key arguments in these studies which include:

  1. That the economic costs of adopting a shorter working week are minimal and worth the social and health benefits of giving people time to spend with families and other non-work activities;

  2. That the benefits of a 5-day week are particularly strong for women, people with caring responsibilities, people at risk of poor mental health and young people who must balance study, work and other responsibilities etc.;

  3. That businesses benefit significantly from shorter working weeks in terms of reduced absenteeism and improved staff engagement, retention, recruitment and productivity.

Research also describes a range of different shorter working week models being trailed in construction. These include:

  1. A hard 5-day week – where sites are shut down on weekends apart from in exceptional circumstances where activities pose unacceptable risk to worker and public health such as tower crane dismantling, erection and maintenance and demolition. This includes two sub-models:

    • Compressed hard 5-day week– where people work 1–2 h longer every day to make up for the lost weekend;

    • Pure hard 5-day week – where people work 5 days rather than 6 days and have to increase their productivity to keep their wages and hours the same during the week;

  2. A soft 5-day week – where people work a rotating schedule of 5-days per week while keeping sites open for 6 days (for example by giving people alternate Saturdays and weekdays off). This model includes two common sub-models:

    • Compressed soft 5-day week– where people work 1–2 h longer every day to make up for the lost weekend;

    • Pure soft 5-day week – where people work 5-days rather than 6-days and have to increase their productivity to keep their wages and hours the same during the week;

  3. Hybrid soft 5/6-day week – where people have the option of working 5 or 6-days and work alongside each other. For example, some trades people prefer to work weekends rather than extended hours during the week because of less interference from other trades and greater access to limited resources such as crane time. These options may also be conditional on factors such as project progress, criticality to the program and ability to safely and productively work longer working hours during the week.

However, concerns have been raised about the overwhelmingly positivity of research in this area with claimed benefits being highly contingent and being difficult to measure and verify (Kodz et al., 2002; International Labour Organization, 2022; The Society for Human Resource Management, 2021; Soga et al., 2022; Swinney et al., 2023). For example, Ditzell et al. (2024) found that outcomes from Unilever New Zealand's four-day week trial were not guaranteed and required careful planning and cultural change. Similarly, Backmann et al. (2024) question many of the assumed benefits in the German context, while the UK's Confederation of British Industry acknowledged that a 4-day week is not a “one-size-fits-all” solution and would be economically unviable in many industries and potentially lead to exploitation by unscrupulous employers who may see it as a way to reduce staff numbers, pay, pensions and other workplace entitlements which support worker health and wellbeing. In construction, Tijani et al.’s (2022) review of related research argued that the pros and cons of shorter working weeks remain contentious and that there is a need for more large-scale empirical research. Our research is a response to the above concerns and the gap in existing evidence and the following section describes the methodology and method employed to explore the research questions posed at the start of this paper.

To capture the multiple perspectives of people from a range of demographics, roles and firms across the Australian construction industry we employed an interpretive mixed methods approach to data collection and analysis, which triangulated both qualitative (semi-structured interviews) and quantitative data (industry-wide survey). This approach was adopted to address the numerous methodological challenges in conducting research in this area which have been too often neglected in previous studies:

  1. The need to consider the full diversity of lived experiences and views from across the whole industry (age, gender, ethnicity, role, onsite/offsite etc.);

  2. The need to consider the interests of the wide variety of firms which operate across the industry (small, medium and large contracting firms and trade subcontractors operating in different geographical regions and industry sub-sectors);

  3. The highly personalised and dynamic nature of work life balance which means different things to different people at different times in their lives;

  4. The potential for researcher and respondent bias linked to the inherent commercial and ethical considerations around work life balance which may encourage participants to give a certain response which they perceive to be the right thing to say;

  5. The need to consider impacts across the whole industry rather than only on individual and often unique projects where trials are being conducted.

Data collection and analysis occurred in three stages as explained in more detail below:

  • Stage one: Semi-structured interviews with cost and time experts.

Using a key-informant approach (Tremblay, 1957), semi-structured interviews were undertaken with a representative sample of 47 project planning, cost, project management, human resource management and safety experts from 28 contracting and development firms across the construction industry in the state of New South Wales (NSW) Australia. The NSW construction industry employs 401,564 people which is just under 40% of the total construction industry workforce in Australia (ABS, 2023). It is therefore considered a representative sampling frame.

Following ethical approval from the Human Research Ethics Committee of the University of Technology Sydney and in collaboration with a major industry association, firms were invited to nominate experts, who then independently contacted the research team to ensure anonymity. A random, representative sample was then selected from this initial sampling frame for interview. Each interview lasted about one hour and explored the cost, time, safety and productivity implications of transitioning to various shorter working week scenarios. Many participants also provided documentary evidence (e.g., cost and time estimates) to support their responses. Applying the concept of theoretical saturation and an abductive approach of concurrent data collection and analysis, interviews continued until no new insights emerged. The stage 1 sample is outlined in Table 1.

Table 1

Sample summary – stage 1

DemographicSub-groupsFrequencyPercent
RoleExecutive director48.5
Senior planner612.8
Senior estimator1021.3
Pre-construction manager12.1
National operations manager12.1
Project manager714.9
Construction director12.1
Chief operations officer24.3
Construction manager12.1
Head of conversations and strategy12.1
Managing director714.9
Contracts administrator24.3
Contracts manager24.3
Project engineer12.1
WHS manager12.1
Total47100.0
Firm sizeLarge (250+ employees)1346.4
Medium (50–249 employees)932.1
Small (1–49 employees)621.4
Total28100.0
LocationUrban/city2438.7
Regional1625.8
National1422.6
International812.9
Total62100.0
MarketCommercial2421.4
Industrial108.9
Residential2017.9
Aged care76.3
Health1513.4
Education1614.3
Infrastructure civil76.3
Retail87.1
Hospitality54.5
Total112100.0
Project value range$0–50 million924.3
$50–300 million1232.4
$300 + million1643.2
Total37100.0
  • Stage two: Semi-structured interviews with a cross section of the construction industry

Semi-structured interviews were undertaken with a cross section of people from across the NSW construction industry to understand the work life balance and other personal and health and wellbeing implications of moving to various shorter working week scenarios. We defined work-life balance as “The individual perception that work and non-work activities are compatible and promote growth in accordance with an individual's current life priorities” (Kalliath and Brough, 2008: 324). Using a purposive, stratified sampling approach and with support from the partner industry association, 50 randomly selected firms were invited to nominate five potential participants each. From this sampling frame of approximately 250, a second random sampling ensured anonymity with interviews continuing until theoretical saturation was reached. This resulted in a sample of 64 respondents (see Table 2).

Table 2

Sample summary-stage 2

DemographicSub-groupsFrequencyPercent
Age16–291625.0
30–392640.6
40–491218.8
50–59914.1
60–6911.6
SexMale4976.6
Female1523.4
Non-binary00.0
Marital statusSingle with children34.7
Single no children1625.0
De factor partner34.7
Married with children3554.7
Married no children710.9
RoleSenior director/executive management46.3
Head office-based management, administration1625.0
Site-based project management, site management, supervision, administration2031.3
Construction worker/tradesperson and labourer2437.5
Area and marketUrban/city3453.1
Regional3250.0
National3046.9
International57.8
Total  
SectorCommercial5382.8
Industrial1015.6
Residential3046.9
Aged care914.1
Health1929.7
Education2031.3
Infrastructure civil57.8
Earthworks and remediation57.8
Retail2132.8
Hospitality710.9
House building46.3
Firm sizeLarge (250+ employees)1320.3
Medium (50–249 employees)4164.1
Small (1–49 employees)1015.6

Each interview in stages 1 and 2 was audio-recorded, transcribed verbatim and analysed using thematic analysis in four stages following Guest et al. (2012) and Gioia et al. (2013). In stage one, researchers immersed themselves in the transcripts to gain data familiarity. In stage two, guided by the research questions, each researcher independently conducted open (inductive) coding, organising and generating an initial list of items/codes (first-order coding) from the data set that had a reoccurring pattern. In stage three, recurring patterns and categories were identified and grouped into overarching themes. In stage four the emergent themes were further refined by revisiting the data, allowing further expansion and connections between overlapping themes. Following an abductive approach, analysis ran concurrently with data collection and continued until theoretical saturation was achieved.

  • Stage three: Online survey

An online survey was conducted to complement the stage 1 and 2 interview data. Sampling involved the partner industry association asking its member organizations to distribute an invitation letter and survey link (with consent form) to their staff. We kept the online survey open until we met the required sample size of 383 for all questions, calculated using Newbold et al.’s (2013) formulae based on a population size of 401,564 which is the NSW construction industry labour force (ABS statistics 2023). This resulted in the sample in Table 3.

Table 3

Sample summary-stage 3

DemographicSub-groupsFrequencyPercent
GenderMale1,18080
Female28619.4
Non-binary90.6
Total1,475100
Age15–2416017.4
25–3523125.1
36–4519921.6
46–5516417.8
56–6511812.8
Over 65505.4
Total922100
Marital statusSingle10828.4
Married or long-term de-facto partner27271.6
Total380100
Dependent childrenNo21056.9
Yes15943.1
Total369100
RoleSenior director/executive management22418.5
Head office-based management, administration20617
Site-based project management, site management, supervision, administration52843.7
Construction worker/tradesperson and labourer25120.8
Total1,209100
Employment contractPermanent34392.5
Fixed term184.9
Casual102.7
Total371100
PayFixed salary (no paid overtime)27173.4
Fixed salary (paid overtime)226
Hourly wage (paid overtime)7620.6
Total369100
Employer sizeMicro business (fewer than 10 employees)8021.3
Small business (10–49 employees)6918.4
Medium-sized business (50–249 employees)9124.2
Large business (250 or more people employees)13636.2
Total376100
Employer sectorCommercial building19250.9
Residential building (apartments)4913
House building7419.6
Civil and infrastructure6216.4
Total377100
Employer regionCity areas27572.2
Regional areas10226.8
Remote areas41
Total381100

The survey was split into six sections and employed a combination of open, categorical, interval and Likert-scaled questions. Section 1 asked for general demographic information about the respondents (age, gender, occupation, etc). Section 2 asked about the participant's current working week (worked hours, days, overtime, etc.). Sections 3 and 4 asked about the participant's current work life balance using a range of standard validated work life balance instruments (Amatea et al., 1986; Carlson et al., 2000; Greenhaus et al., 2003; Kodz et al., 2002). Section 5 asked about the potential impact of several 5-day week scenarios on their work life balance and general health and wellbeing, productivity and safety etc. Section 6 included an open question about what an ideal working week would look like.

Based on a Kolmogorov–Smirnov (KS) test which confirmed the non-normal distribution of the data, survey data was analysed using a variety of descriptive and non-parametric tests. A Relative Importance Indexing (RII) method was used to provide relative comparisons of survey items (Holt, 2014). Qualitative data from the open questions which included 450 detailed comments were analysed using the same thematic analysis approach as described for the interviews.

RQ1.

What are the pros and cons of a shorter working week for employees in the Australian construction industry and what is the preferred model?

On average across our survey sample, 39.8% worked more than five days per week, 26.1% worked over 55 h per week and 36.7% more than 10 h per day. Table 4 shows that hours worked varied greatly with the highest being worked by on-site salaried workers, young people in relatively junior roles and some waged workers – especially those working on large projects in inner and infrastructure locations who were especially vulnerable to long hours due to the high value of weekend working on those projects.

Table 4

Days worked a week, hours worked per week and hours worked per day across the sample (N = 581)

DemographicPercentages (%) working days a weekPercentages (%) of working hours a dayPercentages (%) working hours a week
1234567Less than 88910More than 10Less than 3536–4041–4546–5051–55Over 55
All respondents0.71.12.64.950.937.52.34.415.117.426.436.72.51517.618.720.226.1
Male0.90.91.5447.542.62.63.713.116.128.838.31.91216.119.320.630.2
Female01.87.18.865.516.807.524.523.61727.45.128.625.516.318.46.1
Single02.62.67.764.120.52.62.633.315.417.930.89.814.624.412.217.122
Married or long-term de-facto partner0.802.52.552.5401.76.516.320.72531.517.120.424.518.428.6
Job role Group 1 (off-site salaried workers in administrative and managerial roles)0.60.63.93.262.624.54.54.8218.717.525.933.13.214.721.821.81622.4
Job role Group 2 (on-site salaried workers in supervisory roles)00.91.86.450.739.30.92.77.213.128.548.4211.813.216.726.529.9
Job role Group 3 (on-site waged workers in trade and operative roles)01.11.12.13458.53.24.626.425.32320.72.921.423.320.415.516.5
(15–24)03.36.7203533.31.75.213.813.827.639.73.423.716.916.927.111.9
(25–35)002.13.253.7401.13.217.218.325.835.5113.516.717.719.831.3
(36–45)02.71.305242.71.33.614.515.727.738.61.58.829.417.619.123.5
(46–55)1.6004.743.85004.99.814.834.436.11.78.613.822.422.431
(56–65)002.2060.932.64.38.512.812.83431.94.814.316.728.614.321.4
(Over 65)04.208.362.516.78.35.638.922.216.716.79.122.718.29.118.222.7
Fixed salary (no paid overtime)101.96.855.3322.94.312.811.132.539.3114.715.714.725.528.4
Fixed salary (paid overtime)012.5012.537.537.50020203030033.311.111.133.311.1
Hourly wage (paid overtime)003.29.72958.1011.530.819.211.526.93.410.324.120.720.720.7
Principal contractor00.82.48.154.831.52.44.613.814.728.438.51.814.217.714.223.928.3
Sub-contractor004.8042.952.408.316.72525252026.91229.69.413.5
Consultant000072.727.307.738.57.715.430.816.72516.72516.70
Micro business (fewer than 10 employees)07.43.7048.1373.77.726.915.411.538.52.724.332.410.813.516.2
Small business (10–49 employees)0011.13.748.133.33.7021.224.227.327.33.714.822.222.214.822.2
Medium business (50–249 employees)02.905.961.823.55.906.522.632.338.7023.816.79.516.733.3
Large business (250 or more people employees)01.91.913.241.541.501.810.716.121.45008.65.220.73134.5
Commercial buildings02.24.33.246.2431.12.56.317.526.347.54.89.515.920.617.531.7
Residential buildings (apartments)0005.357.931.65.35.321.115.831.626.3030.87.77.7053.8
House building6.9006.955.23105.920.617.629.426.5014.825.918.522.218.5
Civil and infrastructure003.83.853.834.63.80029.417.652.9020.816.712.520.829.2

On average, 61% of people surveyed across our sample had an acceptable, good or very good “self-perceived” work-life balance. When asked about the best ways to improve work-life balance, respondents emphasized the need for greater flexibility and control over when, where and how they worked. However, there was a high level of inequality of access to flexible working across our sample which was a key factor in driving support for a mandated 5-day week for everyone.

Many people aspired to work significantly fewer hours and days than they were currently working (within the range of 35–45 h a week, for 4/5 days a week) (See Table 5). However, not everyone wanted to work shorter working weeks. For example, young people in wage earning roles who were paid hourly and who most valued overtime pay by working weekends.

Table 5

Aspiration for working (hours, days, weekend) in construction industry (N = 220)

I would like my weekends freeI would like to work less days a weekI would like to work less hours a weekWork commitments prevent me from participating fully in life outside workI need to work overtime to get my job doneI would like my weekends free and could safely increase my productivity during the week to compensateThe culture at work can negatively affect relationships outside workI would like my weekends free and could safely work longer hours during the week to compensateI would like to work a rotating schedule where I get alternate weekdays and Saturdays freeI would like my weekends free and could take a pay cut for itLife commitments prevent me from performing fully at workI would like to work more hours a weekI would like to work more days a week
All respondentsRII0.890.780.780.740.730.720.670.660.600.540.530.400.36
Rank1223456789101112
MaleRII0.890.770.770.740.750.710.670.660.620.540.540.430.38
Rank12354678910101112
FemaleRII0.910.840.830.730.650.750.660.630.530.530.500.320.30
Rank1235746899101112
SingleRII0.890.800.790.810.720.750.720.610.700.560.550.420.37
Rank1342656879101112
Married or long term defacto partnerRII0.830.790.760.720.730.710.640.630.590.510.530.430.39
Rank12354678911101213
Age group (15–24)RII0.920.790.790.820.690.750.690.610.680.590.570.410.39
Rank133254576891011
Age group (25–35)RII0.900.820.810.770.720.760.700.680.610.410.560.400.36
Rank12346578911101213
Age group (36–45)RII0.880.790.790.700.770.750.700.720.590.500.490.410.35
Rank122634657891011
Age group (46–55)RII0.870.750.780.790.860.620.690.670.580.610.600.420.35
Rank12345678910111213
Age group (56–65)RII0.860.760.780.640.680.630.620.610.590.510.480.500.43
Rank13254678910121113
Age group (over 65)RII0.840.800.800.560.720.640.640.600.480.600.520.400.44
Rank123745569681110
Job role Group 1RII0.870.750.760.680.770.650.660.620.550.540.520.400.36
Rank14352768910111213
Job role Group 2RII0.940.830.840.790.710.760.710.650.610.520.550.340.32
Rank1324656781091112
Job role Group 3RII0.840.710.670.720.660.740.650.740.670.510.540.570.49
Rank145362725109811
Fixed salary (no paid overtime)RII0.920.790.800.760.720.750.590.660.600.550.520.350.31
Rank13246597810111213
Fixed salary (paid overtime)RII0.900.750.700.700.750.800.800.700.600.700.400.450.35
Rank1344322454768
Hourly wage (paid overtime)RII0.890.780.730.800.670.800.530.730.640.670.600.490.36
Rank13425284657910
Principal contractorRII0.910.820.820.770.750.770.660.700.570.560.530.360.34
Rank122343657891011
Sub-contractorRII0.880.770.730.670.750.750.630.670.550.430.550.470.42
Rank12453365797810
ConsultantRII0.880.720.680.560.680.720.680.760.520.560.520.520.52
Rank1345434276777
Micro businessRII0.830.730.720.670.670.680.570.670.520.580.530.470.45
Rank123554759681011
Small businessRII0.890.770.860.670.740.670.670.600.710.560.510.400.37
Rank132646675891011
Medium businessRII0.870.790.790.770.740.740.700.640.590.370.510.410.39
Rank122344567118910
Large businessRII0.890.750.720.750.700.760.760.710.660.540.550.430.37
Rank134362257981011
Commercial buildingsRII0.900.780.780.770.780.760.700.730.680.460.540.400.38
Rank122324657981011
Resqidential buildings (appartments)RII0.900.720.760.780.900.740.680.740.640.660.580.380.34
Rank153214648791011
House buildingRII0.770.700.700.670.700.590.570.460.560.430.500.470.47
Rank12232459610788
Civil and infrastructureRII0.840.760.710.710.760.840.710.780.530.690.530.490.38
Rank1355415276789
City areasRII0.920.800.790.720.790.770.670.680.640.520.470.370.34
Rank1235347689101112
Regional areasRII0.910.800.800.640.670.740.570.660.540.560.560.360.41
Rank122643759881110

When asked about their preferred model for a shorter working week, Table 6 shows that support for a 5-day week varied across our sample. Qualitative data indicated that this support depended on a range of factors such as: payment method (waged or salaried); existing hours of work; working conditions; current work-life balance provisions such as flexible working; the shorter working week model employed; the level of physical and mental fatigue involved in a job; the value of weekend working (overtime pay); general economic conditions which influence factors such as cost of living; and individual demographics such as sex, age, job, ethnicity, personal preferences and circumstances. However, most respondents (81.5%) favoured a hard 5-day week working five days with every weekend off, compared to just 18.5% who preferred working a soft 5-day week of five days with alternative weekdays and Saturdays off.

Table 6

Support for 5-day working week (N = 584)

DemographicWorking 5 days and having every weekend off (percentage)Working 5 days and getting alternative weekdays and Saturdays free (percentage)
Male80.119.9
Female87.912.1
Single73.926.1
Married or long-term de-facto partner74.525.5
Job role Group 1 (off-site salaried workers in administrative and managerial roles)82.817.2
Job role Group 2 (on-site salaried workers in supervisory roles)86.713.3
Job role Group 3 (on-site waged workers in trade and operative roles)61.538.5
(15–24)75.824.2
(25–35)82.217.8
(36–45)78.421.6
(46–55)86.213.8
(56–65)85.514.5
(Over 65)70.629.4
Fixed salary (no paid overtime)92.97.1
Fixed salary (paid overtime)57.142.9
Hourly wage (paid overtime)59.140.9
Principal contractor83.316.7
Sub-contractor94.75.3
Consultant8020
Micro business6436
Small business76.223.8
Medium business82.917.1
Large business90.29.8
Commercial buildings86.113.9
Residential buildings (apartments)70.829.2
House building67.732.3
Civil and infrastructure66.733.3
City areas86.613.4
Regional areas85.414.6

Working a shorter working week has consequences for employees in the construction industry if clients are not prepared to alter project program parameters and to further explore the most preferred 5-day week model, respondents were presented with three possible scenarios:

  1. Working 5 days and being more productive each day to avoid a pay cut;

  2. Working 5 days and extending daily hours to avoid a pay cut (compressed working week);

  3. Working 5 days and accepting a pay cut to avoid weekend work.

As shown in Table 7 working more productively each day to avoid pay cut was the most preferred scenario, followed by working extra hours and then taking a pay cut for not working weekends. Once again this varied across our sample, with relatively stronger support for increasing productivity from women, onsite professional salaried workers in supervisory roles, younger workers and those working in larger businesses. Waged workers saw no benefits from working more productively since they were generally paid by hours worked not output.

Table 7

Effects on work life balance for different 5-day week scenarios across sample demographics (N = 570)

DemographicWorking 5 days and taking a pay cut for not working the weekendWorking 5 days and extra hours every day to avoid a pay cutWorking 5 days and more productively every day to avoid a pay cut
Significantly improveSlightly improveNot affectedSlightly worsenSignificantly worsenSignificantly improveSlightly improveNot affectedSlightly worsenSignificantly worsenSignificantly improveSlightly improveNot affectedSlightly worsenSignificantly worsen
Male20.113.928.821.615.616.520.136.817.78.930.526.434.65.43
Female15.48.743.321.211.59.614.441.319.215.435.62533.71.93.8
Single20.515.420.528.215.412.87.728.243.67.728.235.920.512.82.6
Married or long-term de-facto partner15.311.231.620.421.413.324.537.814.310.230.628.633.74.13.1
Job role Group 1 (off-site salaried workers in administrative and managerial roles)11.410.246.719.212.610.217.448.513.210.818.626.948.533
Job role Group 2 (on-site salaried workers in supervisory roles)1817.524.92415.714.317.533.224.910.138.725.827.24.63.7
Job role Group 3 (on-site waged workers in trade and operative roles)378.720.716.317.430.417.426.115.210.932.622.827.210.96.5
(15–24)29.718.818.820.312.517.212.526.626.617.242.229.717.23.17.8
(25–35)18.813.5262417.718.816.734.417.712.538.522.928.14.26.3
(36–45)32.415.528.215.58.523.921.140.85.68.532.421.13871.4
(46–55)11.113.937.519.418.116.713.944.416.78.322.216.754.25.61.4
(56–65)13.98.344.416.716.78.330.641.716.72.827.819.447.22.82.8
(Over 65)10045351051065101020560105
Fixed salary (no paid overtime)19.61432.718.71512.123.439.317.87.531.82835.51.92.8
Fixed salary (paid overtime)2010203020302020300503010100
Hourly wage (paid overtime)39.412.121.212.115.239.49.124.218.29.145.521.221.26.16.1
Principal contractor1410.834.431.29.710.821.539.821.56.535.52933.32.20
Sub-contractor26.911.523.126.911.523.123.123.123.17.719.238.519.219.23.8
Consultant16.78.32525258.333.341.7016.733.32541.700
Micro business6.93.444.837.96.913.820.748.36.910.313.813.862.13.46.9
Small business3124.127.63.413.810.327.641.410.310.320.73144.803.4
Medium business19.412.945.216.16.56.519.445.219.49.722.632.335.59.70
Large business24.615.42023.116.921.515.435.418.59.243.123.127.71.54.6
Commercial buildings27.55.830.420.315.924.614.5427.211.637.726.127.52.95.8
Residential buildings (apartments)17.48.743.54.326.121.71339.18.717.439.121.734.84.30
House building7.723.142.319.27.73.811.557.719.27.711.526.95011.50
Civil and infrastructure36.8021.136.85.326.310.521.131.610.547.421.131.600
City areas23.518.627.518.611.816.719.634.312.716.732.422.536.33.94.9
Regional areas12.512.542.517.5152.517.54527.57.522.522.547.552.5

While increasing productively was the most favoured option, there were considerable concerns about the feasibility of doing so. Safety implications were raised for workers performing mentally and physically demanding jobs and concerns were also raised about how to measure productivity accurately due to the intangible nature of management roles or complex interdependencies between different jobs/trades. Concerningly, 24.7% of participants also said they would look for a second job to earn income on their free weekends and 15.3% predicted that their employers would require them to work weekends from home anyway or on an alternative 6-day week project (if a 5-day week was not mandated) (Table 8). Many expressed concern that many second jobs would be in the unregulated grey economy where worker exploitation and safety risks were higher and that this would increase existing levels of fatigue and associated physical and mental health risks even further on existing projects.

Table 8

Employer would require working a sixth day on another project if were required to work a 5-day week on one project (N = 581)

FrequencyPercent
Yes8915.3
No29751.1
Possibly19533.6
Total581100

While participants preferred to work more productively to keep their weekends free, the most common model employed in the Australian construction industry is a “compressed 5-day week” where people work longer hours during weekdays to compensate for not working weekends. However, support for this model was not universal and depended on factors such as pay method (salaried or waged); age; family and caring responsibilities and gender. For example, many people felt that a compressed hard 5-day week was especially bad for people with caring and family responsibilities and women who took the bulk of these responsibilities. Other negative implications associated with a compressed hard 5-day week included:

  1. Increased fatigue and poorer safety (especially for those in physically or cognitively demanding roles or who commute long distance to work).

  2. Increased fatigue and poorer safety from many people (around 8%) looking for a second jobs on weekends or in the unregulated grey economy. Increased fatigue due to uncontrolled weekend working because administrative work normally done in the week would need to be shifted to the weekend to be done in people's own time;

  3. Potential loss of overtime pay for many waged construction workers who rely on weekend working.

RQ2.

What are the pros and cons of a shorter working week for employers in the Australian construction industry and what is the preferred model?

Many participants argued that a shorter working week could have many business benefits for employers. These included improved: staff work life balance; health and wellbeing; staff recruitment, engagement and retention; workplace behaviour; and reduced illness and absenteeism. Many also argued that the business viability of a shorter working week has increased in recent years due to increased costs of overtime rates on weekends and reducing worker productivity and attendance. However, most participants also expressed significant concerns about the potential negative impact of a shorter working week on employer's business competitiveness and viability and on their client's projects. While many acknowledged these risks depended on the shorter working week model employed, there were especially strong concerns about the potentially significant business risks associated with a compressed hard 5-day week (where sites are shut on weekends except in exceptional circumstances and people worked longer days during the week to compensate). This is the most common model employed in the Australian construction industry and many respondents had undertaken detailed analysis and modelling of the risks involved which included:

  1. Potentially significant cost and program impacts which varied between +5% and +25% for time and +0.40% to +4% for costs, depending on a range of assumptions such as: project type; value of weekend working; client willingness to share risks; liquidated damages imposed for delays; costs of overtime for weekend working etc. While some argued that there could be a reduction in overtime costs due to people not working weekends, this financial benefit was far outweighed by, increased preliminary costs (due to longer programs) and increased risks of liquidated damages from delays (since most clients would not change their programs). Subcontractors are also currently under-pricing the risks of a shorter working week because they can spread them across 6-day week projects. But if a shorter working week was mandated across the whole industry (as advocated by some industry groups and researchers), these costs would increase by as much as 20%.

  2. Exacerbation of critical skills shortages sue to potential loss of labour to other industries where operatives can earn overtime by working a 6-day week or a migration of labour from 5-day week projects to 6-day week projects (assuming a 5-day week was not mandated across the whole industry).

  3. Reduced productivity – While many acknowledged that the productivity of Saturday work had reduced in recent years due to increasing overtime costs and reduced weekend attendance, Saturdays were widely considered to still be valuable for some key trades and on many projects (especially on inner city CBD projects with large workforces and significant logistical challenges and where planning conditions allowed it).

  4. Reduced safety due to the risk of greater fatigue from working longer hours during the week (especially for those in cognitively or physically demanding roles).

  5. Increased bankruptcies given stresses already on the industry arising from increasing labour and materials costs and growing market uncertainty.

  6. Reduced competitiveness for firms employing a shorter working week model when tendering against firms using a 6-day week model (if a shorter working week was not mandated across the whole industry);

  7. Increased costs and programs for clients resulting in potentially cancelled projects.

Given the above risks of a hard 5-day week, most respondents agreed that it was only viable:

  1. On selective projects where the value of weekend working is low and reduced productivity from not working weekends is minimal;

  2. One selective projects which have been assessed, planned and designed from the very start to fit a hard 5-day week program (rather than retrospectively imposing a shorter week at tender stage which is most often the case);

  3. If clients were willing to share the significant cost and program risks by adjusting their budgets and programs to suit;

  4. If clients reduce uncertainty for tenderers by mandating a hard 5-day week, do not accept competing 6-day week tenders and enforcing it in practice;

  5. If clients remove pressures for firms to work a 6-day week such as excessive liquidated damages and contractual risks distributions which shift uncontrollable delays onto contractors;

  6. If a range of other complementary interventions are also used to avoid the potential risks listed above such as: fatigue management, discouraging people from taking second jobs on weekends, carers support, improved safety management systems etc.

Unfortunately, respondents widely agreed that the above conditions were unlikely to be met. Therefore, a hard 5-day week would produce significant work-life balance and business challenges and unintended consequences for the industry (especially small firms which are likely to get passed the risk by principal contractors).

For the above reasons, the majority respondents felt that a soft 5-day week where firms kept sites open on weekends was a viable compromise between business and individual worker interests. In this 5-day week model, employers, clients and individuals can negotiate a 5-day week schedule in a flexible way which responds to employees’ unique needs and project constraints. This can be done using standard workplace flexibility arrangements and rotating schedules to give people an alternative Saturday and weekday free while keeping the site open on Saturdays. Many respondents had been voluntarily operating a soft 5-day week for some time for both off-project and on-project staff with minimal impact on project programs, costs and business competitiveness. Although respondents acknowledged organizational challenges that had to be managed (such as ensuring continuity of site management/supervision between weekdays and weekends and ensuring projects do regress to a 6-day week when projects run behind), this model provided employees with the flexibility to accommodate their varying work and life demands and allowed employers to remain competitive by keeping projects operating 6 days a week.

In relation to research question one, our results provide further empirical evidence that many people working in the construction industry work long hours which are potentially detrimental to their work life balance and health and wellbeing and that they support a shorter working week as a way to improve this (Townsend et al., 2011; Lingard et al., 2021). However, we found that this is not as universal as many previous studies suggest and that because of the potential individual and business risks involved, flexible working (rather than a shorter working week) is the preferred way to improve work life balance and health and wellbeing for most people. While the importance of flexible working has also been acknowledged in construction work-life balance research (Francis et al., 2006; Holden and Sunindijo, 2018; Sui Pheng et al., 2019), our findings provide further insights into the variability of access to flexibility across the construction workforce and how this drives support for a mandatory hard 5-day week where the whole industry would be forced to shut down on weekends. However, given the potential individual and organizational risks linked to this model, our findings indicate that if flexibility provisions were improved and made more equal across the entire construction workforce, that support for a hard 5-day week would fall away.

Our findings also add further nuance to previous shorter working week research which tends to treat the construction workforce as a homogenous whole. While numerous studies acknowledge that there is a divide between salaried and waged workers in their support for a shorter working week (Townsend et al., 2006a, c; Lingard and Turner, 2022; Lingard et al., 2024) our findings show that support for a 5-day week varies significantly across the workforce depending on a range of additional factors such as: existing work life balance provisions; the 5-day model employed; the level of risk and physical and mental fatigue involved in one's job, the location of one's job (onsite or offsite) and various demographic factors such as age etc. We also found that support for a 5-day week was driven by potential personal, relational and organizational impacts such as the risk of reduced income, the limitations of working harder and longer hours during the week; potentially negative impacts on other team members' work life balance; and potentially negative impacts on project outcomes and organizational viability and competitiveness. These interdependencies are rarely acknowledged in existing research. Our findings therefore support Lingard et al. (2021) who argues that the specific costs and benefits of different 5-day week models must be considered from different stakeholder perspectives. However, overall, our findings are much more critical of a compressed 5-day week (the most common model in Australia) than many previous construction studies (see for example Lingard and Francis, 2009; Brown et al., 2010, Galea et al., 2020). In particular, we find that there are certain groups of people who are especially exposed to these risks (young people working in relatively junior supervisory onsite roles in large commercial, infrastructure and residential projects). Furthermore, given that many women still take the main caring role in families (Standing Committee on Economy and Gender and Economic Equality, 2021), our results qualify many previous studies which argue that a shorter working week is always good for increasing gender equity and diversity in the industry (see for example Lingard et al., 2021, Galea et al., 2020).

We also found that the most popular 5-day week option was one which involved working more productively during the week (a 4-day week type 100:80:100 model – Lewis et al., 2023) rather than longer working days (a compressed model). However, we raise new questions about how this may be viable within the context of construction where it is notoriously difficult to measure productivity (Crawford and Vogl, 2006).

Overall, our findings in relation to research question one reflect wider concerns by researchers outside the field of construction about the overwhelming positivity of the shorter working week debate (Stronge and Harper, 2019; Harlington, 2022) and need for further exploration via larger scale studies (most previous studies are based on limited case studies and small sample sizes).

In relation to research question two, in addition to raising similar concerns to those expressed by previous researchers about the risks of a compressed 5-day week model (see Townsend et al., 2006a, c, 2011, 2012; Lingard et al., 2008; 2024; Bradley et al., 2010; Galea et al., 2020), our findings contribute a much larger array of potential business risks (such as reduced productivity, safety and increased costs) which contradict many previous research studies. These risks are especially pronounced in a hard compressed 5-day working week model and we find that these business interests cannot be separated from employee interests in considering the viability of a shorter working week. Yet this interdependence has been largely neglected in previous research which tends to look at the shorter working week from an individual employee perspective. Importantly, we also find that the unpredictability of many of these risks, the unwillingness of many clients to share them and the general lack of provisions within the industry to manage them, makes a hard 5-day week a highly risky option at both an organizational and individual level. Ultimately this will translate into risks for employees, employers and clients of the industry who will have to bear these consequences.

Overall, our results are much more cautionary about the merits of a hard 5-day week than previous construction studies which we argue are often methodologically flawed and tend to uncritically echo wider assumptions about the automatic and often universal benefits of shorter working weeks (see for example Joyeaux, 2025 who comes to similar conclusions). In contrast, our results favour a “soft 5-day week” where sites are kept open on weekends and people negotiate a 5-day week to fit in with individual project requirements and co-worker needs. The value of this soft 5-day week model is that there is considerable experience and organizational data available about the potential risks. Furthermore, these risks are minimal to individuals, businesses and clients in the industry making a soft 5-day week the best compromise between business and individual worker interests of all the models we explored. It is therefore surprising that a soft 5-day weekmodel has not previously been explored in the field of construction, although we note that one of the case studies (yet to be reported) in the Lingard et al. (2024) study is similar.

Addressing the lack of large-scale studies into the pros and cons of a shorter working week in construction, our findings make several important contributions to advancing research in this area.

First, our results provide evidence that a culture of long working hours and working weeks, which is damaging to people's work life balance and general health and wellbeing is common in some parts of the Australian construction industry. However, the potential benefits of a shorter working week are not as clear, universal and guaranteed that most previous studies suggest and that the workforce cannot be treated as a homogeneous whole. We find that many people's lives could be detrimentally impacted if a 5-day week was imposed universally across the whole construction industry with risks being especially significant for young professional site-based salaried employees with large mortgages and those not able to work longer days during the week due to family and other weekday commitments or due to the physically and cognitively demanding nature of their work. This means that a mandatory hard 5-day week could introduce new inequities across the workforce, potentially worsen gender inequalities and exacerbate the current labour shortage crisis in the Australian construction industry.

Second, we find that there are many unexplored business and project-related risks associated with a shorter working week and that one cannot separate employee and employer interests when considering the pros and cons of a shorter working week, as most previous studies do. While these risks depend on the wide range of factors which need to be further explored, they appear to be especially concerning for projects where the value of weekend working is high (such as large complex inner city sites subject to very tight time and cost constraints where clients do share the risks and impose large liquidated damages). Our findings raise especially significant concerns about the impact of a compressed hard 5-day week which is the most common model currently employed in the Australian construction industry.

Third, our research raises new questions about who will pay for these potential risks. While there are always exceptions to the rule, few employees are willing or able to take a pay cut, to work longer hours during the week or increase their productivity to suit. Furthermore, few businesses are willing or able to accept the risks involved and few clients are prepared to adjust their programs and budgets to suit. This raises the worrying prospect that these risks will be passed down the supply chain by clients and contractors to smaller subcontractors which are least able to bear and manage them, causing potentially significant damage to them, their employees, the wider construction industry and ultimately the clients it serves.

Fourth, if a 5-day model is employed in the construction industry then our results indicate that a soft-5-day week where sites are kept open on the weekend would have the greatest level of support because it represents the best compromise between employee, employer and client interests. Furthermore, many firms have been operating this model for some time without any significant impact on their business viability.

Finally, we find that by far the least risky model would be to simply provide people with greater and more equal access to flexibility and control over when, where and how they work regardless of role, age, gender and project circumstances. If this were to happen then a mandated shorter working week and its associated risks would not be needed.

In conclusion, our findings indicate that the impact of a shorter working week at an individual and organisational level is dependent on a wide range of factors which are currently poorly understood. Therefore, reflecting recent concerns raised about the merits of a 4-day week outside construction (Joyeaux, 2025) we conclude that generalised statements about the individual benefits of a 5-day week should be treated with great caution. The jury is still out on the pros and cons of a shorter working week and that answers to our research questions are complex and will only become evident over time as more research is undertaken across a variety of contexts and shorter week scenarios.

The implications of our findings for managers and policy makers seeking to improve work life balance in construction are significant since they call into question the widespread assumption, promulgated by past research and recent media that a shorter working week will be universally beneficial for society. Rather, our findings show that improving work life balance is more than simply about reducing hours worked and days worked and that it should be only treated as one potential strategy alongside a host of other complementary strategies. For example, these might include physical and mental health support, improved leave and flexibility provisions, improved organisational cultures and management practices and improved site conditions and facilities etc. Our findings also reveal that managers and policy makers can also not assume widespread support for a shorter working week, as is often suggested. Instead, our findings indicate that the construction workforce is not as homogenous as many well-intentioned managers and policy makers assume and that support for a working week varies significantly across the workforce depending on factors such as profession, trade, pay structures, age, gender and marital and family status. Furthermore, because people's lives change, support for a shorter working week may also change over the course of a person's working life. We also find that a shorter working week is not risk free. There are potential upsides and downsides for individuals and firms and we find that these risks and opportunities are much more interdependent than is often suggested. For businesses and clients in construction, we found potential risks to productivity, cost, safety and quality on many types of projects, especially on large complex inner city projects where clients are not prepared to adjust their project parameters to accommodate such a change. So the top-down imposition of a hard 5-day week, as is being proposed in the Australian construction industry by some groups should be avoided since there is a risk that the unintended consequences could inadvertently exacerbate the very problems managers and policy-makers are seeking to resolve. These potential risks are magnified even further for a compressed 5-day week which is the most common model being proposed in Australia. Our findings indicate that a far better solution would be to focus on improving equal access to workplace flexibility for everyone since this would allow individuals to tailor their working arrangements to suit their specific circumstances as they change over time. However, if managers and policy makers were determined to introduce a shorter working week, then our results indicate that a soft (uncompressed) 5-day week is the best option because this minimises potential risks to productivity, cost, safety and quality. Furthermore, we recommend that the imposition of any requirements needs to be better monitored and enforced to ensure that employers do what they promise, especially when projects falls behind and pressures to revert to a 6/7 days week are most intense. While our results sound a note of caution for managers and policy makers about the widely claimed benefits of a 5-day week, we end this paper by acknowledging that the shorter working week debate has been valuable in starting a much needed conversation in the construction industry about the impact of the industry's culture and work practices on worker wellbeing, what companies can reasonably expect of their employees in the pursuit of profit which is required to provide people with secure employment and what role clients play in setting healthy parameters for the projects they procure.

We acknowledge the following limitations to the above findings. First, the above research was conducted within the specific context of the Australian industry and the 5-day week models which are being trailed there. Different 5-day week models may emerge in different geographical contexts and variations in regulatory environments, economic conditions and cultures (national and industry) and this may influence the answers to our research questions. Second, while our sample was large and we used a mixed methods approach, further insights may be gained by employing more case study based and ethnographic type research which provides more in-depth individual insights into the impacts of different models on different types of employees across the industry.

This research was approved by the Human Research Ethics Committee of the University of Technology Sydney, Australia. Reference: ETH22-7710.

During the generation of this paper the authors did not use generative AI and AI-assisted technologies.

The authors would like to acknowledge the support of the NSW Master Builders Association in this research and especially the late Brain Seidler AM, Elenor Worsfold and Cameron Spence.

4 Day Week Global
(
2023
),
Experimenting with a 4 Day Week in Australasia
,
4 Day Week Global
,
Auckland
.
ABS
(
2023
),
Labour Force, Australia, Detailed
,
Australian Bureau of Statistics
,
Canberra
,
available at:
 https://www.abs.gov.au/statistics/labour/employment-and-unemployment/labour-force-australia-detailed/dec-2023 (
accessed
 8 April 2025).
Adah
,
C.A.
,
Aghimien
,
D.O.
and
Oshodi
,
O.
(
2023
), “
Work–life balance in the construction industry: a bibliometric and narrative review
”,
Engineering, Construction and Architectural Management
, Vol. 
32
No. 
1
, pp. 
38
-
58
, doi: .
Amatea
,
E.S.
,
Cross
,
E.G.
,
Clark
,
J.E.
and
Bobby
,
C.L.
(
1986
), “
Assessing the work and family role expectations of career-oriented men and women: the life role salience scales
”,
Journal of Marriage and the Family
, Vol. 
48
No. 
4
, pp. 
831
-
844
, doi: .
Backmann
,
J.
,
Hoch
,
F.
,
Hüby
,
J.
,
Platz
,
M.
and
Sinnemann
,
M.F.
(
2024
),
The 4-Day-Week in Germany: First Results of Germany's Trial on Work Time Reduction
,
Intraprenör
,
Berlin
.
Berman
,
D.
(
2009
), “
Cost-benefit analysis of a four 10-hour day work week in construction
”,
Unpublished thesis, University of Florida, Florida, USA
.
Bowen
,
P.
and
Zhang
,
R.P.
(
2020
), “
Cross-boundary contact, work-family conflict, antecedents, and consequences: testing an integrated model for construction professionals
”,
Journal of Construction Engineering and Management
, Vol. 
146
No. 
3
, 04020005, doi: .
Bowen
,
P.
,
Govender
,
R.
,
Edwards
,
P.
and
Cattell
,
K.
(
2018
), “
Work-related contact, work-family conflict, psychological distress and sleep problems experienced by construction professionals: an integrated explanatory model
”,
Construction Management and Economics
, Vol. 
36
No. 
3
, pp. 
153
-
174
, doi: .
Bradley
,
L.
,
Brown
,
K.
,
Lingard
,
H.
,
Townsend
,
K.
and
Bailey
,
C.
(
2010
), “
Talking the talk and walking the walk How managers can influence the quality of work-life balance in a construction project
”,
International Journal of Managing Projects in Business
, Vol. 
3
No. 
4
, pp. 
589
-
603
, doi: .
Briem
,
K.
and
Ólafsson
,
P.
(
2015
), “
Is less work better work? A shorter working week from a managerial viewpoint
”,
Masters Thesis. Lund University, School of Economics and Management, The Netherlands
.
Brouwer
,
T.
(
1957
), “
The limitation of the work week: an analysis of its rationale, enforcement, and economic effects
”,
Doctor of Philosophy Thesis, University of Michigan, USA
.
Brown
,
K.
,
Bradley
,
L.
,
Lingard
,
H.
,
Townsend
,
K.
and
Ling
,
S.
(
2010
), “
Working time arrangements and recreation: making time for weekends when working long hours
”,
Australian Bulletin of Labour
, Vol. 
36
No
2
, pp. 
194
-
213
, ISSN
[PubMed]
.
Carlson
,
D.S.
,
Kacmar
,
K.
and
Williams
,
L.
(
2000
), “
Construction and initial validation of a multidimensional measure of work/family conflict
”,
Journal of Vocational Behavior
, Vol. 
56
No. 
2
, pp. 
249
-
276
, doi: .
Carver
,
T.N.
(
1936
), “
The theory of the shortened working week
”,
The American Economic Review
, Vol. 
26
No. 
3
, pp. 
451
-
462
,
available at:
 https://www.jstor.org/stable/1802725
Commonwealth of Australia
(
2023
),
The Senate Select Committee on Work and Care Final Report
,
Commonwealth of Australia
,
Canberra
.
Crawford
,
P.
and
Vogl
,
B.
(
2006
), “
Measuring productivity in the construction industry
”,
Building Research and Information
, Vol. 
34
No. 
3
, pp.
208
-
219
.
Crook
,
D.
and
Tessler
,
A.
(
2021
), “
The cost of doing nothing report
”,
Oxford Economics and the Culture in Construction Taskforce
,
available at:
 https://cultureinconstruction.com.au/wp-content/uploads/2021/09/The-Cost-of-Doing-Nothing-Report.pdf (
accessed
 8 April 2025).
Ditzell
,
R.
,
Dalton
,
B.
,
Johns
,
R.
and
Stephens
,
A.
(
2024
), “
Can the four-day work week achieve sustainable human resource management goals? An examination of a four-day work week trial
”,
2024 European Academy of Management (EURAM) Annual Conference
,
University of Bath
,
Bath
,
June 2024
.
Downey
,
L.
and
Stough
,
C.
(
2018
),
Measuring the Psychological Impact of Work Related Stress and Related Occupational Factors in the Australian Infrastructure Construction Industry
,
Swinburne University
,
Melbourne
.
Francis
,
V.
,
Lingard
,
H.
and
Gibson
,
A.
(
2006
),
A Qualitative Study of Work-Life Experiences in the Public and Private Sectors of the Australian Construction Industry
,
Construction Industry Institute, Queensland University of Technology
,
Australia
.
Galea
,
N.
,
Powell
,
A.
,
Chappell
,
L.
and
Loosemore
,
M.
(
2020
), “
The gendered dimensions of informal institutions in the Australian construction industry
”,
Gender, Work and Organization
, Vol. 
27
No. 
3
, pp. 
1214
-
1231
, doi: .
Gioia
,
D.A.
,
Corley
,
K.G.
and
Hamilton
,
A.L.
(
2013
), “
Seeking qualitative rigor in inductive research: notes on the Gioia methodology
”,
Organizational Research Methods
, Vol. 
16
No. 
1
, pp. 
15
-
31
, doi: .
Golden
,
L.
(
2010
), “
A purpose for every time? The timing and length of the work week and implications for worker well-being
”,
Connecticut Law Review
, Vol. 
42
No. 
4
, pp. 
53
-
74
, doi: .
Greenhaus
,
J.
,
Collins
,
K.
and
Shaw
,
D.
(
2003
), “
The relation between work-family balance and quality of life
”,
Journal of Vocational Behaviour
, Vol. 
63
No. 
3
, pp. 
510
-
531
, doi: .
Guest, G., MacQueen, K.M. and Namey, E.E.
(
2012
),
Applied Thematic Analysis
,
SAGE Publications, Thousand Oaks, CA
, doi: .
Hanna
,
E.S.
and
Markam
,
S.
(
2019
), “
Constructing better health and wellbeing? Understanding structural constraints on promoting health and wellbeing in the UK construction industry
”,
International Journal of Workplace Health Management
, Vol. 
12
No. 
3
, pp. 
146
-
159
, doi: .
Harlington
,
C.
(
2022
), “
The 4-day week is flawed. Works still want it, wired, Feb 3, 2022
”,
WIRED, available at:
 https://www.wired.com/story/four-day-week-burnout/ (
accessed
 12 December 2025).
Hertzog-Young
,
C.
(
2021
),
Building a Shorter Working Week: Investigating the Potential for a Four Day Week in the UK Construction Industry
,
4 Day Week Campaign
,
United Kingdom
,
available at:
 https://policycommons.net/artifacts/3450614/6a142f_1d27dbad6db34288b66acf689a131da2//4250871/ 
(6 August 2023) CID: 20.500.12592/6bz5tm
(
accessed
 10 December 2025).
Holden
,
S.
and
Sunindijo
,
R.Y.
(
2018
), “
Technology, long work hours, and stress worsen work-life balance in the construction industry
”,
International Journal of Integrated Engineering
, Vol. 
10
No. 
2
, pp. 
13
-
18
, doi: .
Holdsworth
,
S.
,
Turner
,
M.
,
Scott-Young
,
C.M.
and
Sandri
,
K.
(
2020
),
Women in Construction: Exploring the Barriers and Supportive Enablers of Wellbeing in the Workplace
,
RMIT University
,
Melbourne
.
Holt
,
G.D.
(
2014
), “
Asking questions, analysing answers: relative importance revisited
”,
Construction Innovation
, Vol. 
14
No. 
1
, pp. 
2
-
16
, doi: .
International Labour Organization
(
2022
),
Working Time and Work-Life Balance Around the World
,
International Labour Office
,
available at:
 https://www.ilo.org/sites/default/files/wcmsp5/groups/public/@ed_protect/@protrav/@travail/documents/publication/wcms_864222.pdf (
accessed
 8 April 2025).
Joyeaux
,
M.C.
(
2025
), “
Work less, live more? The impact of an introduction of the four-day working week on happiness in the context of the Icelandic four-day working week experiment
”,
Junior Management Science
, Vol. 
10
No. 
4
, pp. 
831
-
857
, ISSN
[PubMed]
.
Kalliath
,
T.
and
Brough
,
P.
(
2008
), “
Work-life balance: a review of the meaning of the balance construct
”,
Journal of Management and Organization
, Vol. 
14
No. 
3
, pp. 
323
-
327
, doi: .
Kamerāde
,
D.
,
Balderson
,
U.
,
Burchell
,
B.
,
Wang
,
S.
and
Coutts
,
A.
(
2020
),
Shorter Working Week and Workers' Well-Being and Mental Health
,
Centre for Business Research, University of Cambridge
,
Working Paper No. 522, University of Cambridge, Cambridge, UK
, ISSN
[PubMed]
.
Kodz
,
J.
,
Harper
,
H.
and
Dench
,
S.
(
2002
),
Work-Life Balance: Beyond the Rhetoric
,
The Institute for Employment Studies
,
Brighton
, ISSN
[PubMed]
.
Kotera
,
Y.
,
Green
,
P.
and
Sheffield
,
D.
(
2019
), “
Work-life balance of UK construction workers: relationship with mental health
”,
Construction Management and Economics
, Vol. 
38
No. 
3
, pp. 
291
-
303
, doi: .
Kotłowska
,
A.
(
2024
), “
The shortened working week and its impact on workplace sustainability
”,
Education of Economists and Managers
, Vol. 
71
No. 
1
, pp. 
69
-
97
, doi: .
Lefrançois
,
M.
and
Trottier
,
M.
(
2022
), “
Work–family balance in the construction industry: why gender analysis matters to develop sustainable interventions
”,
Ergonomics
, Vol. 
65
No. 
11
, pp. 
1525
-
1536
, doi: .
Lewis
,
K.
,
Stronge
,
W.
,
Kellam
,
J.
,
Kikuchi
,
L.
,
Schor
,
J.
,
Fan
,
W.
,
Kelly
,
O.
,
Gu
,
G.
,
Frayne
,
D.
,
Burchel
,
B.
,
Hubbard
,
N.B.
,
White
,
J.
,
Kamarāde
,
D.
and
Mullens
,
F.
(
2023
),
The Results are in: The UK's Four-Day Week Pilot
,
Autonomy Research
,
Crookham Village, Hampshire
.
Lingard
,
H.
and
Francis
,
V.
(
2004
), “
The work‐life experiences of office and site‐based employees in the Australian construction industry
”,
Construction Management and Economics
, Vol. 
22
No. 
9
, pp. 
991
-
1002
, doi: .
Lingard
,
H.
and
Francis
,
V.
(
2009
),
Managing Work-Life Balance in Construction
,
Spon Press
,
London
, ISSN
[PubMed]
.
Lingard
,
H.
and
Turner
,
M.
(
2022
), “
Making time for life: a whole-of-industry initiative to reducing work hours and promoting health and gender inclusion in project-based construction work
”,
Project Leadership and Society
, Vol. 
3
, 100065, doi: .
Lingard
,
H.C.
,
Yip
,
B.
,
Rowlinson
,
S.
and
Kvan
,
T.
(
2007
), “
The experience of burnout among future construction professionals: a cross-national study
”,
Construction Management and Economics
, Vol. 
25
No. 
4
, pp. 
345
-
357
, doi: .
Lingard
,
H.
,
Townsend
,
K.
,
Bradley
,
L.
and
Brown
,
K.
(
2008
), “
Alternative work schedule interventions in the Australian construction industry: a comparative case study analysis
”,
Construction Management and Economics
, Vol. 
26
No. 
10
, pp. 
1101
-
1112
, doi: .
Lingard
,
H.
,
Nette
,
A.
,
Harley
,
J.
,
Pirzadeh
,
P.
,
Clarke
,
J.
,
Yazidjoglou
,
A.
,
Strazdins
,
L.
and
Sargent
,
G.M.
(
2021
),
Triple Wins: Work Hour Cultures for Health, Safety and Gender Equality in Construction Literature Review
,
Construction Work Health and Safety Research @ RMIT, RMIT University
,
Australia
.
Lingard
,
H.
,
Turner
,
M.
and
Pirzadeh
,
P.
(
2024
), “
Culture in construction pilot projects: summary interim report
”,
March 2024, RMIT, Melbourne, Victoria, Australia
.
McKinsey & Company
(
2020
),
The Next Normal in Construction How Disruption is Reshaping the World's Largest Ecosystem
,
June 2020
,
McKinsey & Company
,
London
.
Morgan
,
K.
(
2023
), “
The great resignation is ‘over’. What does that mean? BBC Worklife, 3rd August 2023, The great resignation is ‘over’. What does that mean?
”,
BBC Worklife
,
available at:
 https://www.bbc.com/worklife/article/20230731-the-great-resignation-is-over-what-does-that-mean (
accessed
 6 August 2023).
Mullens
,
F.
and
Glorieux
,
I.
(
2024
), “
Reducing working hours: shorter days or fewer days per week? Insights from a 30-hour workweek experiment
”,
Cambridge Journal of Economics
, Vol. 
48
No. 
1
, pp. 
41
-
68
, doi: .
Newbold
,
P.
,
Carlson
,
W.L.
and
Thorne
,
B.
(
2013
),
Statistics for Business and Economics
,
Pearson Education
,
UK
.
Olsaretti
,
S.
and
Kalender
,
C.N.
(
2016
),
MA Thesis: The Autonomy based Argument for a Shorter Working Week
,
Universitat Pompeu Fabra MA Degree in Political Philosophy
,
Barcelona
.
O'Halloran
,
J.
and
Thomas
,
C.
(
2024
),
Healthy Industry, Prosperous Economy
,
Institute of Public Policy Research
,
London
.
Pang
,
A.S.
(
2022
),
Shorter: How Working Less Will Revolutionise the Way Your Company Gets Things Done
,
Penguin Business
,
London
.
Productivity Commission
(
2021
),
Working from Home Research Paper, Productivity Commission
,
Australian Government
,
Canberra
.
Roos
,
C.F.
(
1935
), “
Economic theory of the shorter work week
”,
Econometrica: Journal of the Econometric Society
, Vol. 
3
No. 
1
,
January
, pp. 
21
-
39
, doi: .
Schor
,
J.B.
,
Fan
,
W.
,
Kelly
,
O.
,
Gu
,
G.
,
Bazdenezhnykh
,
T.
and
Bridson-Hubbard
,
N.
(
2022
), “
The four day week: assessing global trials of reduced work time with No reduction in pay
”,
Four Day Week Global, Auckland, NZ
.
Society for Human Resource Management
(
2021
),
2017 Employee Benefits: Remaining Competitive in a Challenging Talent Marketplace
,
Society for Human Resource Management
,
Alexandria, VA
.
Soga
,
L.R.
,
Bolade-Ogunfodun
,
Y.
,
Mariani
,
M.
,
Nasr
,
R.
and
Laker
,
B.
(
2022
), “
Unmasking the other face of flexible working practices: a systematic literature review
”,
Journal of Business Research
, Vol. 
142
,
March
, pp. 
648
-
662
, doi: .
Spencer
,
D.
(
2024
), “
Encouraging a four-day working week could make inequality worse
”,
The Conversation
,
September 7th, available at:
 https://theconversation.com/encouraging-a-four-day-working-week-could-make-inequality-worse-238270 (
accessed
 4 February 2025).
Standing Committee on Economy and Gender and Economic Equality
(
2021
), “
Future of the working week
”,
Discussion paper, Canberra City, Australian Capital Territory : ACT Government, Australia
.
Stronge
,
W.
and
Harper
,
A.
(
2019
),
The Shorter Working Week
,
January
,
Autonomy, Autonomy Research
,
Cranbourne
.
Stronge, W. and Lewis, K.
(
2021
),
Overtime: Why We Need a Shorter Working Week
,
Verso Books, London
, ISBN:
[PubMed]
, doi: .
Sui Pheng, L., Benjamin K.Q. and Chua, B.K.Q.
(
2019
),
Work–Life Balance in Construction Millennials in Singapore and South Korea
,
Springer Engineering ebooks, Singapore
, ISBN:
[PubMed]
.
Swinney
,
P.
,
Graham
,
D.J.
,
Vera
,
O.
,
Anupriya
,
Hörcher
,
D.
and
Ojha
,
S.
(
2023
),
Office Politics: London and the Rise of Home Working
,
Centre for Cities
,
London
.
Tijani
,
B.
,
Osei-Kyei
,
R.
and
Feng
,
Y.
(
2022
), “
A review of work-life balance in the construction industry
”,
International Journal of Construction Management
, Vol. 
22
No. 
14
, pp. 
2671
-
2686
, doi: .
Townsend
,
K.
,
Bailey
,
C.
,
Brown
,
K.
,
Bradley
,
L.M.
,
Lingard
,
H.
and
Helen
,
C.
(
2006a
), “
How would employees' construct’ a balance between work and non-work life? Work-life balance in the construction industry
”,
Paper Presented at the 14th International Employment Relations Association Conference
,
Hong Kong
.
Townsend
,
K.
,
Bailey
,
C.
,
Brown
,
K.
,
Bradley
,
L.
and
Lingard
,
H.
(
2006b
), “
When the balance isn't easy: a case study exploring the complications with work/life balance initiative in the Australian construction industry
”, in
De Cieri
,
H.
,
Bardoel
,
A.
,
Barrett
,
R.
,
Buttigeig
,
D.
,
Rainnie
,
A.
and
McLean
,
K.
(Eds),
Proceedings Socially Responsive, Socially Responsible Approaches to Employment and Work, Proceedings of the ACREW conference
,
Prato
.
Townsend
,
K.
,
Bailey
,
C.
,
Brown
,
K.
,
Bradley
,
L.M.
,
Lingard
,
H.
and
Helen
,
C.
(
2006c
), “
How would employees' construct’ a balance between work and non-work life? Work-life balance in the construction industry
”,
Proceedings 14th International Employment Relations Association Conference
,
Hong Kong
.
Townsend
,
K.
,
Lingard
,
H.
,
Bradley
,
L.
and
Brown
,
K.
(
2011
), “
Working time alterations within the Australian construction industry
”,
Personnel Review
, Vol. 
40
No. 
1
, pp. 
70
-
86
, doi: .
Townsend
,
K.
,
Lingard
,
H.
,
Bradley
,
L.
and
Brown
,
K.
(
2012
), “
Complicated working time arrangements: construction industry case study
”,
Journal of Construction Engineering and Management
, Vol. 
138
No. 
3
, pp. 
443
-
448
, doi: .
Tremblay
,
M.A.
(
1957
), “
The key informant technique: a nonethnographic application
”,
American Anthropologist
, Vol. 
59
No. 
4
, pp.
688
-
701
.
Veal
,
A.
(
2023
), “
4-day work week trials have been labelled a ‘resounding success’. But 4 big questions need answers
”,
March 24, 2023, available at:
 https://theconversation.com/4-day-work-week-trials-have-been-labelled-a-resounding-success-but-4-big-questions-need-answers-201476 (
accessed
 4 February 2025).
Wong
,
K.
,
Chan
,
A.H.S.
and
Ngan
,
S.C.
(
2019
), “
The effect of long working hours and overtime on occupational health: a meta-analysis of evidence from 1998 to 2018
”,
International Journal of Environmental Research and Public Health
, Vol. 
16
No
12
, pp. 
2102
-
2114
doi: . PMID:
[PubMed]
; PMCID:
[PubMed]
.
World Economic Forum
(
2020
),
The Future of Jobs Report 2020
,
World Economic Forum
,
Geneva
.
World Health Organization and International Labour Organization
(
2021
), “
Long working hours increasing deaths from heart disease and stroke
”,
Joint news release, 17 May 2021, available at:
 www.who.int/news/item/17-05-2021-long-working-hours-increasing-deaths-from-heart-disease-and-stroke-who-ilo (
accessed
 18 January 2023).
Ainsley
,
T.
(
2022
),
Unilever Expands Four-Day Work Week Pilot to Australia after NZ Pilot
,
Bloomberg
,
available at:
 https://www.bloomberg.com/news/articles/2022-11-01/unilever-expands-four-day-work-week-to-australia-after-nz-pilot (
accessed
 16 April 2025).
Autonomy
(
2021
), “
Going public: Iceland's journey to a shorter working week
”,
available at:
 https://autonomy.work/wp-content/uploads/2021/06/ICELAND_4DW.pdf (
accessed
 6 August 2023).
CEDA
(
2023
),
Occupational Gender Segregation
,
Committee for Economic Development of Australia, Melbourne Committee for Economic Development of Australia
,
Australia
.
Joly
,
J.
,
Hurst
,
J.
,
Walsh
,
D.
and
Carbonaro
,
G.
(
2023
), “
Four-day week: which countries have embraced it and how's it going so far?
”,
Euronews
,
available at:
 https://www.euronews.com/next/2024/02/02/the-four-day-week-which-countries-have-embraced-it-and-how-s-it-going-so-far (
accessed
 8 April 2025).
Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at Link to the terms of the CC BY 4.0 licence.

or Create an Account

Close Modal
Close Modal