To design a geotechnical engineering structure optimally, an iterative decision-making process is required due to the prevailing uncertainty of the ground conditions. At present, these decisions are taken based on simple deterministic rules and models. This paper proposes a risk-based decision-theoretic framework to the optimal planning for geotechnical construction. This framework combines geotechnical probabilistic models, cost analysis using Monte Carlo simulation and the observational method. The framework is illustrated on the design of the surcharge for an embankment on soft soil, whereby the optimal preloading sequence of added surcharge is adapted to the observed settlement. The approach balances the cost of surcharge material against financial penalties related to project delays and insufficient overconsolidation, which causes damage due to residual settlement. The result is a preloading strategy that optimally accounts for information obtained from settlement measurements under uncertain ground conditions. The findings highlight the potential of using risk-based decision planning in geotechnical engineering, in particular when combined with the observational method. For the investigated case study, a reduction in the expected cost in the order of 25% is observed.
INTRODUCTION
Design of geotechnical engineering structures implies decision making under uncertainty. The reason is mainly a lack of knowledge about the prevailing ground conditions, but there are also limitations in understanding and predicting the ground–structure interaction or temporal variations. Managing these uncertainties is essential to achieving a design of satisfactory quality without unnecessary delays and at a reasonable cost. One approach to this challenge is to view the geotechnical design and execution as a sequential decision problem, which has been studied in other areas of engineering and decision making (e.g. Rosenstein & Barto, 2001; Straub & Faber, 2005; Memarzadeh et al., 2014; Papakonstantinou & Shinozuka, 2014; Malings & Pozzi, 2016; Bismut & Straub, 2021; Wang et al., 2022). The engineering challenge lies in finding a cost-effective sequence of design decisions, considering not only the technical requirements at the time of project completion, but also the respective probabilities and costs of potential consequences caused by an unsuccessful design. In the ideal case, the analysis should also consider operational and maintenance costs (Mendoza et al., 2021). At present, these decisions are taken based on simple deterministic rules and simplifying model assumptions.
A typical example of a geotechnical engineer's decision under uncertainty is the design of embankments on soft soil prone to consolidation settlements using a surcharge and prefabricated vertical drains (PVDs) (Fig. 1). The embankment load initiates a consolidation process towards a final long-term settlement, but neither the magnitude of this settlement, nor the time until it is reached, can be well predicted by the engineer; despite geotechnical pre-investigations being performed, there are typically considerable uncertainties regarding the soil's hydraulic conductivity and deformation properties. Unless this uncertainty is carefully managed by a planned sequence of inspection decisions and mitigating actions during design and construction, unwanted costly consequences such as time delays or residual settlements after completion of the superstructure may occur. The engineering challenge therefore essentially lies in finding a cost-effective design solution, considering not only the technical requirements at the time of project completion, but also the respective probabilities and costs of potential consequences caused by an unsuccessful design.
Preloading of an embankment with a surcharge of total height ΔH to accelerate consolidation. Prefabricated vertical drains are omitted for clarity (GW, ground water)
Preloading of an embankment with a surcharge of total height ΔH to accelerate consolidation. Prefabricated vertical drains are omitted for clarity (GW, ground water)
To the authors’ knowledge no geotechnical problem has ever been formalised as a sequential decision problem under uncertainty. A few studies have, however, used other, simpler decision theoretical analyses for other geotechnical applications: Einstein et al. (1978) showed an early application of decision theoretical principles; Zetterlund et al. (2011), Sousa et al. (2017), Klerk et al. (2019) and Hu et al. (2021) performed value of information analyses; and preposterior analyses were performed by Schweckendiek & Vrouwenvelder (2013), Spross & Johansson (2017), van der Krogt et al. (2022), Löfman & Korkiala-Tanttu (2022) and Spross et al. (2022).
Probabilistic settlement analyses have recently been performed by, for example, Bari et al. (2016), Bong & Stuedlein (2018) and Löfman & Korkiala-Tanttu (2022). Addressing the design issue of embankment preloading with PVDs, Spross & Larsson (2021) specifically showed how a probabilistically evaluated initial surcharge height can be used in an observational method to limit the probability of time delay and residual settlement in soft soil. Spross et al. (2019) discussed how settlement monitoring can be evaluated as a basis for a decision to increase the surcharge height. The specific decision-theoretical problem was highlighted, but not solved.
In this paper, the authors propose a risk-based decision-theoretic framework to optimal sequential planning in geotechnical construction. This framework combines a geotechnical probabilistic model with models of the observations and the cost models of actions and unwanted consequences. As a methodology to identify optimal decisions, the authors propose – for the first time in geotechnical engineering – the use of heuristics to describe and optimise the sequence of decisions (Bismut & Straub, 2021).
The proposed framework and methodology are illustrated through an embankment preloading problem. The sequence of decisions on initial surcharge height and later additions to the surcharge are optimised such that a desired settlement is achieved at a minimal expected cost, which reflects whether the settlement is achieved within a fixed timeframe. Construction delays as well as insufficient overconsolidation, which is a cause of residual settlement, are explicitly penalised.
The probabilistic preloading model by Spross & Larsson (2021) is used to describe the settlement evolution. Here, this model is extended to allow simulation of soil settlement curves when the surcharge height is adjusted, thereby enabling modelling of the effect of sequential surcharge height decisions on the settlement evolution.
The outcome of the analysis is a preloading strategy, which prescribes how much surcharge to add conditional on settlement measurements through optimised heuristic parameter values.
EXAMPLE APPLICATION
To illustrate the proposed framework, the current authors take the specific example introduced by Spross & Larsson (2021). A section of an embankment built for the construction of a highway in the south of the county of Stockholm, Sweden is considered. A cross-section of the soil is shown in Fig. 2.
Cross-section of the soil under the planned embankment (from Spross & Larsson (2021) CC-BY-4.0, https://creativecommons.org/licenses/by/4.0/)
Cross-section of the soil under the planned embankment (from Spross & Larsson (2021) CC-BY-4.0, https://creativecommons.org/licenses/by/4.0/)
The authors consider the planning of the surcharge loading on the embankment during an available preloading time, tmax, within which an acceptable soil consolidation is to be reached. The engineering questions can be stated as follows. (a) What initial surcharge height should be used? (b) When is a load increase warranted during the preloading time, and if so, how much more should be added?
GEOTECHNICAL MODEL AND DESIGN REQUIREMENTS
In this section, the main aspects are presented of the probabilistic model adopted to describe the evolution of soil settlement and resulting overconsolidation ratio (OCR), first under constant load and then under multi-stage loading. This geotechnical model, described in detail in Spross & Larsson (2021), considers (a) how primary compression settlement develops with time, due to the weight of the embankment and the surcharge, and (b) the effect of the unloading of the surcharge on the OCR. More detailed and complex models of settlement and consolidation behaviour for staged construction are available in the literature (see, e.g. Walker & Indraratna, 2009; Yin et al., 2022), but the effect of the choice of the geotechnical model on the results is outside the scope of this paper.
Settlement evolution
Under a constant load Δσ and known soil properties, a settlement trajectory with time follows
where
is the spatially averaged degree of consolidation at time t, and S∞ is the predicted long-term primary compression settlement under load Δσ. The vertical consolidation component Uv(t) is obtained from Terzaghi's consolidation theory. For the horizontal consolidation component Uh(t), Hansbo's well-established analytical PVD model is applied (Hansbo, 1979). Owing to the specific consolidation behaviour of soft clays, S∞ is predicted as (Larsson & Sällfors, 1986)
where hcl,i is the thickness of the ith clay layer and Δεi is the strain increase caused by the load Δσ. The strain depends on parameters evaluated from constant-rate-of-strain (CRS) tests, including the preconsolidation pressure and soil moduli (Spross & Larsson, 2021).
In the analyses performed, the embankment and surcharge are assumed to be of the same material; hence the load Δσ is proportional to the material unit weight and to its total height.
If the surcharge is increased by Δσadd after some preloading time, tadd, the adjusted settlement trajectory is modelled as
Under this staged preloading, the first part of the trajectory is equivalent to equation (1). The second part contains, due to the load increase, a recalculated, larger long-term primary consolidation settlement S2,∞ = S∞(Δσ + Δσadd) following equation (3) and a corresponding degree of consolidation U(t − tshift), for which a hypothetical zero degree of consolidation occurs at time tshift = tadd − t0. To determine t0, it is noted that the settlement curve is continuous at tadd, which results in the degree of consolidation
where U(t) is obtained from equation (2). Fig. 3 illustrates tshift and the resulting settlement curve for staged preloading.
Effect of the added surcharge at time tadd on the settlement, where tshift = tadd − t0
Effect of the added surcharge at time tadd on the settlement, where tshift = tadd − t0
Overconsolidation ratio
As achieving overconsolidation by the removal of the surcharge in practice has been found to reduce residual settlement (Alonso et al., 2000; Han, 2015; Indraratna et al., 2019), the model considers this effect through the OCR in the middle of the clay stratum. Under constant surcharge, this quantity can be obtained as in the paper by Spross & Larsson (2021)
where σ′0 is the initial vertical stress in the middle of the clay stratum; Δσsur is the vertical stress caused by the preloaded embankment (i.e. including the surcharge); and Δσemb is the remaining stress increase directly after the unloading of the surcharge (see Fig. 1).
For staged preloading, the effect of the added load on the OCR at unloading depends on the preloading time of both the initial and any added load. To the present authors’ knowledge, there are no validated analytical models for this issue. Therefore, the following reformulation of equation (6) is used to capture the effect on the OCR at the unloading at time t, when it occurs after a previous load increase at time tadd
where ΔU(t) = U(t − tshift) − U(tadd − tshift). Consequently, the effect on the OCR of the added load will depend on the degree of consolidation achieved along the recalculated settlement trajectory after the load has been added. The OCR for staged preloading is depicted in Fig. 4.
Effect of the surcharge added at time tadd on the OCR, using equation (6) with initial surcharge Δσsur corresponding to height ΔH0 for the first part of the curve until t = 36 (weeks) and equation (7) with Δσadd corresponding to additional surcharge height ΔH1. The resulting curve is located below the one for the case where the total surcharge (initial and additional) is applied directly at t = 0, with equation (6)
Effect of the surcharge added at time tadd on the OCR, using equation (6) with initial surcharge Δσsur corresponding to height ΔH0 for the first part of the curve until t = 36 (weeks) and equation (7) with Δσadd corresponding to additional surcharge height ΔH1. The resulting curve is located below the one for the case where the total surcharge (initial and additional) is applied directly at t = 0, with equation (6)
Uncertainties in the soil parameters
The presented soil consolidation model depends on numerous parameters for the soil properties and PVD design. These parameters govern the evolution of the vertical and horizontal consolidation, hence the settlement, as per equations (1)–(7). As explained in the paper by Spross & Larsson (2021), these soil properties are modelled as random variables with an associated probability distribution either evaluated from CRS oedometer tests or assigned based on engineering judgement when data on variability were not available. The parameters in Hansbo's PVD model (Hansbo, 1979) are assumed constant. The complete deterministic and probabilistic assumptions are described in detail in tables 2 and 3 of the paper by Spross & Larsson (2021) and are therefore omitted for brevity. Random settlement trajectories obtained by Monte Carlo (MC) simulation are depicted in Fig. 5.
One hundred sample soil settlement trajectories for an initial surcharge h0 = 0 (m) (no added surcharge). One such trajectory is highlighted in black. For each trajectory, the value of the long-term settlement S∞ is obtained with equation (3). The histogram on the right shows the resulting distribution of S∞. The value starget is obtained from the condition
One hundred sample soil settlement trajectories for an initial surcharge h0 = 0 (m) (no added surcharge). One such trajectory is highlighted in black. For each trajectory, the value of the long-term settlement S∞ is obtained with equation (3). The histogram on the right shows the resulting distribution of S∞. The value starget is obtained from the condition
Settlement and OCR requirements
The proposed risk-based planning framework for optimal preloading requires the definition of performance criteria, such that a preloading decision can be assessed in terms of its success to reach the desired goals. These goals are here expressed in terms of sufficient soil consolidation, through targets on the settlement and OCR, starget and OCRtarget, respectively. These targets are defined in the following paragraphs.
Owing to the uncertainty associated with the ground properties, the long-term settlement S∞ caused by the load of the completed embankment, Δσemb, is also uncertain. To ensure an acceptable residual (post-construction) primary consolidation settlement, Spross & Larsson (2021) proposed a target settlement starget, such that the probability that the long-term settlement under the embankment load attains this target is equal to an acceptable, fixed probability, pFT
In the numerical investigations, pFT is set to 5% to represent a serviceability limit state. By generating sample values of S∞(Δσemb) from the defined probabilistic model and equation (3), starget is obtained as the quantile value corresponding to pFT (Fig. 5). The value of starget is thereafter used to define penalty mechanisms.
In addition, it is required that the OCR exceeds the threshold OCRtarget = 1·10 in the middle of the soft soil stratum after unloading of the surcharge. This is in line with the general technical requirements and guidance for geotechnical works issued by the Swedish Transport Administration (Trafikverket, 2013a, 2013b).
In addition to settlement and OCR requirements, a successful embankment design needs to consider the stability of the embankment. This is typically ensured by the berms (Fig. 1), which add to the construction cost. Ideally, the dimensions of the berms should also be evaluated from the geotechnical model based on the undrained shear strength of the clay. For simplicity, the current authors do not carry out this analysis but do consider the berms in the cost model (see equation (16)).
OPTIMAL PRELOADING STRATEGIES
To find the optimal preloading strategy, the authors rely on the decision analysis framework of Raiffa & Schlaifer (1961), which formalised decision problems under uncertainty with varying information. This enables the optimisation of the surcharge decisions, which can be done in a sequential manner based on measurements of the settlement. Further general information on sequential decision making can be found in Kochenderfer (2015).
Elements of the decision analysis
A decision analysis under uncertainty is based on a probabilistic model of the system, a model of the decision alternatives as well as a utility or cost function. These models are summarised in the following.
Probabilistic model
A complete probabilistic model must account for the effects of actions affecting the system (see ‘Decision alternatives’ below) and reflect the uncertainty in information collection, through a likelihood function (Bismut & Straub, 2022).
In the investigated engineering problem, the soil consolidation model described above is used. Information on the state of the system is obtained as a measurement of the settlement at time t1. The is related to the true value of the settlement by an additive measurement error, ε
For simplicity, the numerical investigation is restricted to error-free measurement – that is, ε = 0. The proposed methodology can easily be adapted to account for noise in the measurement.
Decision alternatives
The decision alternatives describe the available mitigating actions and must account for operational constraints. The description of the available decision alternatives should also include operational constraints that must be accounted for in the planning process.
Utility and cost
The effects of a decision are evaluated in terms of utility, which reflects the preferences of the decision maker. Ultimately, the optimal decision is selected as the one that maximises the expected utility. Assuming a risk-neutral context, the utility can simply translate to costs associated with the actions and the system performance. In this case, utility is expressed in monetary terms.
For the embankment preloading illustration, three cost components are identified, and these are summarised in Table 1. The total cost Ctot incurred at the completion of the preloading operation is obtained as
Components of the cost model for the embankment preloading example
| Cost component | Description |
|---|---|
| Csur,i | Cost of adding a preloading surcharge of height ΔHi. Includes material costs, mobilisation costs, material availability at the time of the decision, and additional berms for slope stability |
| Cdelay | Cost penalty for project delay – that is, sufficient settlement (starget) has not been reached within a dedicated time period |
| COCR | Cost penalty for reduced serviceability of the superstructure, due to residual settlement caused by insufficient overconsolidation at time of unloading |
| Cost component | Description |
|---|---|
| Csur,i | Cost of adding a preloading surcharge of height ΔHi. Includes material costs, mobilisation costs, material availability at the time of the decision, and additional berms for slope stability |
| Cdelay | Cost penalty for project delay – that is, sufficient settlement (starget) has not been reached within a dedicated time period |
| COCR | Cost penalty for reduced serviceability of the superstructure, due to residual settlement caused by insufficient overconsolidation at time of unloading |
If relevant, discounting can be used to reflect the decreasing value of an investment over time; this effect is, however, ignored here.
Decision settings and influence diagrams
With the above elements specified, a decision setting (DS) is defined. A typical compact graphical representation of a DS is the influence diagram (ID) (Jensen et al., 2007). Round nodes represent uncertain outcomes (which are described by the probabilistic model), square nodes are the decisions and lozenge-shaped nodes are the utility. The nodes are connected by directed edges, which represent stochastic, causal and monetary dependence.
The DS is usually determined by operational constraints, as well as the level of complexity of the decision sequence considered. For this study IDs were constructed for three different DSs.
DS #1: surcharge applied at t = 0
In DS #1, the case is considered where the surcharge is applied only at the time of constructing the embankment – that is, at t = 0. The only decision variable is the height ΔH0 of the surcharge. The settlement at time t, St, and the achieved OCR if unloaded at time t, OCRt, are both probabilistic quantities, which depend on the applied surcharge. The overall decision process is summarised by the ID of Fig. 6.
Influence diagram for DS #1. Optimisation of the initial surcharge. The square node ΔH0 indicates that first a value of ΔH0 is chosen, at a cost Csur,0(ΔH0). The now fixed ΔH0 influences the evolution of the settlement St and the overconsolidation ratio at unloading OCRfin as well as the time ttarget when the target settlement is reached, defined by S(ttarget) = starget. Monetary consequences due to project delay and residual settlement result from these quantities. The interaction between ΔH0 and the geotechnical model is represented in a simplified manner
Influence diagram for DS #1. Optimisation of the initial surcharge. The square node ΔH0 indicates that first a value of ΔH0 is chosen, at a cost Csur,0(ΔH0). The now fixed ΔH0 influences the evolution of the settlement St and the overconsolidation ratio at unloading OCRfin as well as the time ttarget when the target settlement is reached, defined by S(ttarget) = starget. Monetary consequences due to project delay and residual settlement result from these quantities. The interaction between ΔH0 and the geotechnical model is represented in a simplified manner
DS #2 and DS #3: surcharge applied at t = 0 and adjusted at time t1
DS #2 and DS #3 consider that there is an opportunity to add a surcharge of height ΔH1 at a fixed time t1, on top of the initial surcharge height ΔH0. The decision on how much to add is based on a measurement of the settlement at time t1 (equation (9)). The overall decision process is summarised by the ID depicted in Fig. 7. In DS #2, the time t1 is fixed and cannot be influenced by the decision maker, whereas in DS #3, this time can be chosen and optimised.
Influence diagram for DS #2 and DS #3. The interactions between the decisions on the initial and added surcharge heights, ΔH0, ΔH1, and the geotechnical model are represented in a simplified manner
Influence diagram for DS #2 and DS #3. The interactions between the decisions on the initial and added surcharge heights, ΔH0, ΔH1, and the geotechnical model are represented in a simplified manner
Optimal decision making
The most desirable outcome of the decision process is the one with the lowest cost. Owing to the uncertain nature of the soil parameters, the outcomes of a sequence of decisions are uncertain, hence so is the total cost. The optimal sequence of decisions is therefore that which results in the minimum expected total cost (Raiffa & Schlaifer, 1961). For DS #1, the optimal decision for ΔH0 is therefore defined as
where E[Ctot(ΔH0)] is the expected value of the total cost evaluated with equation (10), when an initial preloading surcharge of height ΔH0 is applied. This expected total cost thus accounts for the associated risk E[Cdelay(ΔH0)] + E[COCR(ΔH0)] of not achieving the desired settlement or OCR within the available preloading time.
The formulation of the optimisation problem is not as straightforward for DSs that involve one or more opportunities to adjust the surcharge after the initial surcharge is applied – that is, DS #2 and DS #3. In these sequential decision problems, the optimal actions depend on the past observations. Therefore, one must find the optimal function that maps past observations to actions. In general, this type of problem is hard to solve and an exact solution becomes intractable with increasing number of decision or observation steps (Papadimitriou & Tsitsiklis, 1987). Approximate solutions are possible – for example, by way of partially observable Markovian decision processes (POMDPs) or reinforcement learning (Porta et al., 2005; Roy et al., 2005; Silver & Veness, 2010; Mnih et al., 2013; Memarzadeh & Pozzi, 2016; Papakonstantinou et al., 2018; Andriotis & Papakonstantinou, 2019).
To solve the general sequential decision problem, it is convenient to define preloading strategies , which compactly prescribe the sequence of decisions. A strategy consists of a set of rules that prescribes how much surcharge to add at any time as allowed by the DS. For example, for DS #1, a strategy simply prescribes the surcharge height at time t = 0; for DS #2, it prescribes the surcharge height at time t = 0 and gives a rule at time t1, which can be based on settlement measurements, to adjust the surcharge. In DS #3, the strategy additionally prescribes the time t = ti at which to collect the settlement measurement and adjust the surcharge.
Generalising the notation to any preloading strategy , the expected total cost associated with a preloading strategy is thus evaluated as
The optimal preloading problem is equivalent to finding the preloading strategy that minimises the expected total cost
In general, cannot be evaluated analytically. An MC approximation can instead be obtained using the assumed probabilistic geotechnical model. The latter enables the generation of nMC random settlement trajectories, S(k)t, and OCR at unloading OCR(k)fin, obtained from surcharge sequences and so on, with 1 ≤ k ≤ nMC. A total cost can be computed for each of these trajectories as per equations (10), (16), (18) and (19). The MC approximation of the expected total cost of a preloading strategy is therefore
The estimate improves with the number of samples nMC.
HEURISTICS FOR OPTIMAL PRELOADING STRATEGIES
The problem of finding the best strategy is equivalent to finding the best sequence of decisions and an exact solution to equation (13) is still intractable in general. To address this challenge, the space of possible strategies that are considered in the optimisation is reduced, following Bismut & Straub (2022). The proposed methodology considers only strategies that can be described by a specific set of rules, so-called heuristics. A heuristic is typically formulated with simple statements (the rules), in which a number of parameters w = [w1;w2;…;wn] intervene. For example, the following heuristic is defined for DS #2:
- •
the initial surcharge ΔH0 is h0
- •
the additional surcharge ΔH1 at time t1 = 36 weeks is h1 if the measured settlement at this time is lower than a threshold sth.
The parameters w for this heuristic are h0, h1 and sth. In this DS, t1 is fixed to 36 weeks. An arbitrarily chosen preloading strategy following this heuristic format with parameters h0 = 0·94 m, h1 = 1·04 m and sth = 0·77 m will react to different trajectories, as shown in Fig. 8. The total cost incurred will depend on (a) the strategy and (b) the settlement occurring. The expected cost of a strategy with fixed parameters can be estimated with equation (14).
Three sample trajectories for a strategy parameterised with heuristic 2A (DS #2), with h0 = 0·95 m, h1 = 1·04 m and sth = 0·77 m. The time at which the curves intersect with the level starget corresponds to ttarget. For tmax = 72 (weeks), it can be seen that only one of these trajectories satisfies ttarget < tmax and does not lead to project delay
Three sample trajectories for a strategy parameterised with heuristic 2A (DS #2), with h0 = 0·95 m, h1 = 1·04 m and sth = 0·77 m. The time at which the curves intersect with the level starget corresponds to ttarget. For tmax = 72 (weeks), it can be seen that only one of these trajectories satisfies ttarget < tmax and does not lead to project delay
For a given heuristic, there is a set of parameter values that optimises the expected cost. The associated strategy is called the optimal heuristic strategy. Thus, for a given heuristic and associated parameters w = [w1;w2;…;wn], the preloading problem is reduced to finding
As the heuristic formulation of the optimisation problem operates in a restricted strategy space, it yields a sub-optimal preloading strategy. However, the heuristic parametrisation enables the inclusion of operational constraints (e.g. surcharge can only be added at certain prescribed times) and provides easily interpretable strategies. Furthermore, the definition of preloading strategies with heuristics makes sense from the point of view of geotechnical engineering practice, as most preloading strategies would indeed be defined with such simple rules. In addition, several heuristics can be compared and the better-performing strategy selected. In the numerical investigations, the impact of different heuristic choices is discussed, in particular the impact of increasing the number of heuristic parameters.
The optimal parameter values w* are the solution of a noisy optimisation problem where the objective function is expressed as an expected value (Rubinstein & Kroese, 2004), for which no analytical expression exists. An efficient approach is a sampling-based optimisation, which was previously developed for this purpose in Bismut & Straub (2021) and is based on the cross-entropy (CE) method (Rubinstein & Kroese, 2004). The basic steps are summarised in the Appendix and the convergence to the optimal parameter values is illustrated in Fig. 9. The current authors have previously demonstrated this method on other sequential decision planning problems and discussed details of its implementation and performance in Bismut & Straub (2021) and Bismut et al. (2022). The method stands out for the simplicity of its implementation and robustness. However, it can be replaced by any other method suitable for noisy optimisation.
Convergence of heuristic parameters in the CE optimisation for heuristic 2A defined in DS #2
Convergence of heuristic parameters in the CE optimisation for heuristic 2A defined in DS #2
NUMERICAL INVESTIGATIONS
Probabilistic model set-up
As stated above, the probabilistic geotechnical model is described in detail in Spross & Larsson (2021). The settlement target is computed for pFT = 0·05, and is obtained as starget = 1·27 (m) (Fig. 5).
Cost model
Refer to the cost components in Table 1. Csur,i corresponds to the cost of adding surcharge of height ΔHi. It increases with the total surcharge height, and accounts for the cost of berms needed to ensure slope stability (see Fig. 1). It is evaluated from the cost of total surcharge height Htot
where 1·25 is a cost factor addressing the cost increase related to the construction of berms for embankments higher than 1 m. The cost attributed to each increase ΔHi of surcharge on top of existing surcharge Htot is computed as
where the factor fadd,i ≥ 1 accounts for additional costs incurred by increasing the surcharge at a later time ti > 0. Note that the cost of the remaining embankment material after unloading is not included here, as it is the same for all scenarios.
In the model, project delay occurs when the settlement trajectory either does not meet starget within the preloading time allowed by the construction contract, tmax, (ttarget > tmax) or is unable to meet starget at all (ttarget > tlim) (see Fig. 8). The associated penalty is
where cdelay represents the penalty per week of delay.
Finally, the penalty associated with residual settlement due to insufficient OCR is evaluated with the logistic function
where OCRfin is the OCR at unloading at time ttarget or tlim if the settlement target has not been achieved in time. This smoothed step function approaches the maximum penalty cOCR when OCRfin < 1·05, and 0 when OCRfin > OCRtarget = 1·1 – that is, when the OCR requirement is satisfied.
The cost factors csur, cdelay and cOCR and the available preloading time tmax for the initial numerical investigation are given in Table 2.
Heuristic parametrisations
The following heuristics are investigated for the different DSs. The heuristic parameters for each defined heuristic are indicated in bold.
DS #1
As explained above, the optimisation for this setting only consists in optimising the initial surcharge height ΔH0. Thus the corresponding heuristic, with single heuristic parameter h0, is simply as follows.
Heuristic 1: h0 ≥ 0
- (1)
ΔH0 = h0.
DS #2
For DS #2, the performance of two different heuristics in approximating the optimal preloading strategy is investigated. A preloading strategy described with heuristic 2A specifies the initial surcharge height and adjusts it by adding a surcharge height if the measured settlement is lower than a threshold.
Heuristic 2A: h0 ≥ 0, h1 ≥ 0, sth ≥ 0
- (1)
At time t = 0, add surcharge of height ΔH0 = h0.
- (2)
Obtain measurement at time t1 = 36 (weeks).
- (3)
If , add surcharge ΔH1 = h1. Otherwise ΔH1 = 0.
With heuristic 2B, the strategy adjusts the height of the added surcharge based on the difference d between the measured settlement and the threshold. This height adjustment is defined by a sigmoid function varying between 0 and maximum added height h1, characterised by a curve steepness a. When a = 0, this sigmoid function is a step function.
Heuristic 2B: h0 ≥ 0, h1 ≥ 0, sth ≥ 0, a ≤ 0
- (1)
At time t = 0, add surcharge of height ΔH0 = h0.
- (2)
Obtain measurement at time t1 = 36 weeks.
- (3)
Compute .
- (4)
Add surcharge
DS #3
Heuristic 3 is the same as heuristic 2B, with the additional freedom to choose the time t1 at which the settlement is measured and the surcharge height is adjusted. The t1 is thus an additional heuristic parameter.
Heuristic 3: h0 ≥ 0, h1 ≥ 0, sth ≥ 0, a ≤ 0, t1 ∈ {1, 2, 3, …, tmax}
- (1)
At time t = 0, add surcharge of height ΔH0 = h0.
- (2)
Obtain measurement at time t1.
- (3)
Compute .
- (4)
Add surcharge
Computational set-up
For the CE method, the values nCE = 100, nE = 30 and nMC = 10 are fixed. On an eight-core CPU 3·2 GHz machine, optimising the heuristic parameters for a given heuristic takes around 4 min. The expected cost of the resulting optimised strategy is evaluated with nMC = 104 samples.
RESULTS
The CE method is applied to obtain the optimal parameter values and associated expected costs for the different DSs and heuristics defined above, assuming the cost model of Table 2. Fig. 10 illustrates the optimisation of the heuristic parameters for DS #1. The results for all DSs are summarised in Table 3.
Optimal heuristic parameters and associated expected costs
| Parameter | Unit | DS #1 | DS #2 | DS #3 | |
|---|---|---|---|---|---|
| Heuristic 1 | Heuristic 2A | Heuristic 2B | Heuristic 3 | ||
| h0 | m | 1·05 | 0·98 | 0·96 | 0·95 |
| h1 | m | — | 1·06 | 1·08 | 1·81 |
| sth | m | — | 0·71 | 0·73 | 0·37 |
| a | m | — | — | − 0·15 | − 0·28 |
| t1 | weeks | — | 36* | 36* | 20 |
| Expected cost | 106 SEK | 8·11 | 6·54 | 6·29 | 6·06 |
| Std dev. cost | 106 SEK | 7·4 | 6·3 | 6·0 | 5·6 |
| Parameter | Unit | DS #1 | DS #2 | DS #3 | |
|---|---|---|---|---|---|
| Heuristic 1 | Heuristic 2A | Heuristic 2B | Heuristic 3 | ||
| h0 | m | 1·05 | 0·98 | 0·96 | 0·95 |
| h1 | m | — | 1·06 | 1·08 | 1·81 |
| sth | m | — | 0·71 | 0·73 | 0·37 |
| a | m | — | — | − 0·15 | − 0·28 |
| t1 | weeks | — | 36 | 36 | 20 |
| Expected cost | 106 SEK | 8·11 | 6·54 | 6·29 | 6·06 |
| Std dev. cost | 106 SEK | 7·4 | 6·3 | 6·0 | 5·6 |
Value is not optimised but fixed.
The expected costs of the optimal heuristic strategies obtained for each of the DSs decrease from DS #1 to DS #3. This is in agreement with the fact that DS #1 is more restrictive in terms of available actions than DS #2, and in turn DS #2 is more restrictive (because the adjustment time is fixed) than DS #3. Table 3 also reports the estimated standard deviation of the total cost. For the investigated heuristics, the coefficient of variation of the total cost for the optimal strategy varies around 95%. The standard error of the MC estimates of the expected costs is therefore 1%, which ensures a sufficient accuracy to rank the heuristics according to the estimated expected cost of their optimal strategies.
The optimal initial surcharge prescribed by heuristic 1 in DS #1 is higher than the initial surcharge prescribed in DS #2 and DS #3. This shows that the heuristics chosen for DS #2 and DS #3 exploit the fact that measurement information enables an optimised adjustment of surcharge.
For DS #2, it is noted that heuristic 2B performs better than heuristic 2A in terms of expected cost; hence the smoothed step function for the selection of the adjusted load is a better heuristic than the simple step function.
Figure 11 depicts the breakdown of the costs for each optimal heuristic strategy. It is observed that heuristic 3 yields a lower risk of delay than heuristics 2A and 2B and a lower expected total cost, even though it applies on average a higher total surcharge. Therefore, the choice of time t1 to adjust the surcharge plays a significant role in efficiently controlling the settlement. The expected penalty associated with insufficient OCR is here negligible in comparison with the other cost components, for all heuristics.
Breakdown of the expected cost of the optimal strategies for the different DSs and heuristics
Breakdown of the expected cost of the optimal strategies for the different DSs and heuristics
Figure 12 illustrates the effect of adjusting the surcharge at time t1 = 36 on the settlement trajectory, following the optimal strategy for heuristic 2A. The distribution of the settlement at time tmax is obtained from 104 sample trajectories for both the case where only the initial surcharge is applied and not adjusted at t = 36 weeks and the case where the surcharge is adjusted according to the optimal strategy. With the load adjustment action, the settlement trajectories that already reach the target at tmax with the sole initial load are unaffected, while a portion of trajectories which would not have achieved starget at tmax are now compliant – that is, the probability decreases by enabling the adjustment of the surcharge. Most of the corrected trajectories will nevertheless incur a delay penalty, which is optimal under the assumed cost model of Table 2.
Distribution of settlement at tmax for the optimal strategy for DS #2, heuristic 2A, obtained from 104 sample settlement trajectories. The grey histogram represents the distribution of the settlement if only the initial surcharge of height h0 = 0·95 m is applied. The bimodal histogram shows the distribution of the settlement obtained by adjusting the surcharge at t = 36 weeks, as prescribed by the strategy (see Table 3). A full-colour version of this figure can be found on the ICE Virtual Library (www.icevirtuallibrary.com)
Distribution of settlement at tmax for the optimal strategy for DS #2, heuristic 2A, obtained from 104 sample settlement trajectories. The grey histogram represents the distribution of the settlement if only the initial surcharge of height h0 = 0·95 m is applied. The bimodal histogram shows the distribution of the settlement obtained by adjusting the surcharge at t = 36 weeks, as prescribed by the strategy (see Table 3). A full-colour version of this figure can be found on the ICE Virtual Library (www.icevirtuallibrary.com)
The effect of the different heuristics on the final settlement at time tmax and on the OCR at unloading is depicted in Figs 13(a) and 13(b). Heuristics 2A, 2B and 3 can be distinguished from heuristic 1, where the preloading is only added at t = 0. The uncertainty in the settlement reduces when the surcharge is adjusted based on the measured settlement, and the probability that is larger than starget increases from heuristic 1 to heuristic 3. Notably, the optimal strategies for heuristics 2A, 2B and 3 result in a larger probability that the OCR at unloading is smaller than the critical value 1·1, compared to heuristic 1. Hence these heuristics can balance both penalties associated with insufficient settlement and OCR against the applied surcharge in a more efficient manner.
Distribution of (a) settlement achieved at tmax and (b) of the OCR at unloading for the optimal heuristic strategies (see Table 3). The area of the histograms to the left of the dotted line represents for each optimal heuristic strategy, in (a) the probability , and in (b) the probability . A full-colour version of this figure can be found on the ICE Virtual Library (www.icevirtuallibrary.com)
Distribution of (a) settlement achieved at tmax and (b) of the OCR at unloading for the optimal heuristic strategies (see Table 3). The area of the histograms to the left of the dotted line represents for each optimal heuristic strategy, in (a) the probability , and in (b) the probability . A full-colour version of this figure can be found on the ICE Virtual Library (www.icevirtuallibrary.com)
DISCUSSION
To demonstrate the potential of quantitatively analysing and optimising geotechnical design under sequential information, the design of preloading for an embankment on soft soil is considered. The preloading problem is formulated as a sequential decision problem in different DSs. Preloading strategies are described through heuristics with associated parameters, which are optimised to minimise the total expected cost. Different heuristics are considered and it is observed that – as expected – the more flexibility in decision the heuristic provides, the more cost efficient the resulting optimal heuristic strategy is. For the case study investigated, the authors observe a reduction in the expected cost in the order of 25% between heuristics 1 and 3.
It is noted that – with all investigated heuristics – the coefficient of variation of the total cost is large, around 100%. While this variability depends on the assumed cost model, if the decision maker wanted to prioritise strategies that reduce this variability, a risk-averse behaviour could be included in the objective function of equation (13) by considering a utility function that is non-linear with costs (Straub & Welpe, 2014).
Other heuristics than those proposed can be investigated and might result in lower expected costs. For example, one might replace the sigmoid function of heuristic 2B by another function. As settlement measurements are typically available at weekly intervals, a heuristic could be formulated such that the adjusted surcharge at time t1 depends on an observed trend. In this case, the processing of the measurements for the purpose of decision making, hence the trend prediction model, is part of the definition of the heuristic. Ultimately, one could define a heuristic to address the setting in which continuous settlement measurements are available, with near-real-time decision support.
The advantage of the heuristic methodology for the planning of preloading decisions is that the resulting strategies are interpretable, because the decision rules are explicitly defined through the chosen heuristic. This also entails that the heuristic can encode geotechnical expertise. The flexibility in the formulation of the DS through the IDs and the cost functions also enables the analyst to integrate additional constraints. For instance, the uncertainty in the availability of preloading material could be explicitly modelled, such that there is a certain probability of obtaining the requested material at a given point in time.
The decision-theoretical framework described in this paper is suitable to apply in combination with the observational method, which was first defined as a design approach by Peck (1969) and today is accepted into design codes such as Eurocode 7, EN 1997-1:2004 (CEN, 2004). The observational method implies that the geotechnical engineer establishes a monitoring plan with thresholds that trigger prepared design changes specified in an action plan, thereby adjusting the initial design to fit better to the actual ground conditions.
In the context of a sequential decision problem, such thresholds and design changes can be formulated as heuristics, allowing the geotechnical engineer not only to compare conceptually different options of monitoring and action plans, but also to optimise their included threshold values and specified actions. The evaluated DSs in this paper illustrate this clearly: the heuristics 2A, 2B and 3 can be seen as three different options of monitoring and action plans, while Table 3 specifies the optimised heuristics for the plans and also shows their respective expected costs. Such risk-based optimisation of monitoring and action plans is a considerable leap forward from the current practice, where monitoring and action plans usually are defined based on deterministic analyses, although probabilistic approaches are emerging (e.g. Spross & Gasch, 2019).
CONCLUSION
The authors have formalised a geotechnical problem as a sequential decision problem and proposed a methodology based on heuristics to finding optimal strategies. This framework was applied to an embankment preloading problem and highlighted how the DS, chosen heuristics and cost model affect the optimal preloading strategies. This enables a quantitative optimisation of preloading decisions under uncertainty. It was shown that the potential for cost savings is significant. This framework is not limited to embankment design and construction, but is designed as a decision support tool to be extended to a vast range of geotechnical engineering applications, especially those to which the observational method is applied.
ACKNOWLEDGEMENTS
Johan Spross' work was supported equally by the Swedish Transport Administration (grant no. TRV 2020/48425) and Formas (grant no. 2018-01017). The research was conducted without involvement of the funding sources.
APPENDIX. CROSS-ENTROPY OPTIMISATION ALGORITHM
Algorithm 1 describes the steps of the CE method used for the optimisation of the heuristic parameters. The algorithm also applies a smoothing operation, which is not described here, to prevent convergence to local minima (refer to Kroese et al. (2006) for more details). The optimal cost is obtained with equation (14) evaluated in .
The sampling density is here chosen as a truncated normal for positive (or negative) parameters. For integer parameters, the sampled value is rounded to the nearest integer. The updated distribution parameters λ* of the multivariate truncated normal distribution are the mean and covariance of the elite samples.
Cross-entropy method applied to noisy optimisation
| Input: cross-entropy sampling density P(·|λ*); initial sampling distribution parameter λ*; number of CE samples per iteration nCE; number of elite samples nE; number of sample settlement trajectories nMC; maximum number of iterations nmax. | |||
| 1 | ; | ||
| 2 | while l < nmax do | ||
| 3 | for m ← 1 to nCE do | ||
| 4 | generate random heuristic parameter values w(m) from sampling density P(·|λ*); | ||
| 5 | generate nMC settlement trajectories and measurement following strategy ; | ||
| 6 | evaluate the expected total life-cycle cost qm with nMC samples (equation (14)); | ||
| 7 | end | ||
| 8 | sort (w(1), …, w(nCE)) in increasing order of qm; | ||
| 9 | fit the distribution parameter λ* to the nE elite samples; | ||
| 10 | l← l+1; | ||
| 11 | end | ||
| 12 | w*← mean of P(·|λ*); | ||
| 13 | return w* | ||
| Input: cross-entropy sampling density P(·|λ*); initial sampling distribution parameter λ*; number of CE samples per iteration nCE; number of elite samples nE; number of sample settlement trajectories nMC; maximum number of iterations nmax. | |||
| 1 | |||
| 2 | while l < nmax do | ||
| 3 | for m ← 1 to nCE do | ||
| 4 | generate random heuristic parameter values w(m) from sampling density P(·|λ*); | ||
| 5 | generate nMC settlement trajectories and measurement following strategy | ||
| 6 | evaluate the expected total life-cycle cost qm with nMC samples ( | ||
| 7 | end | ||
| 8 | sort (w(1), …, w(nCE)) in increasing order of qm; | ||
| 9 | fit the distribution parameter λ* to the nE elite samples; | ||
| 10 | l← l+1; | ||
| 11 | end | ||
| 12 | w*← mean of P(·|λ*); | ||
| 13 | return w* | ||
NOTATION
- a
heuristic parameter
- Cdelay
cost penalty for project delay
- COCR
cost penalty for reduced serviceability of the superstructure
- Csur,i
cost of adding a preloading surcharge of height ΔHi
- Ctot
total cost
- cdelay
cost factor for Cdelay
- cOCR
cost factor for COCR
- csur
cost factor for Csur
- E
expectation operator
- fadd,i
penalty factor for adding surcharge at later time ti
- Htot
total added surcharge height
- h0
heuristic parameter for surcharge height
- h1
heuristic parameter for surcharge height
- hcl,i
thickness of ith clay layer
- l
number of layers of clay stratum
- Mt
measured settlement at time t
- nCE
number of cross-entropy samples per iteration
- nE
number of elite samples
- nmax
maximum number of cross-entropy iterations
- nMC
number of sample settlement trajectories
- OCRfin
overconsolidation ratio at unloading
- OCRt
overconsolidation ratio at time t
- OCRtarget
target overconsolidation ratio
- P(·)
cross-entropy sampling density
- pFT
acceptable target failure probability
- S
settlement
preloading strategy
- St
settlement at time t
settlement at time tmax
- S∞
long-term primary consolidation settlement
- starget
target settlement
- sth
heuristic parameter for settlement threshold
- t
time
- t1
heuristic parameter for time of added surcharge
- tadd
time of addition of surcharge
- tlim
maximum possible preloading time
- tmax
allowed preloading time in contract
- tshift
time at which a hypothetical zero degree of consolidation occurs
- ttarget
time at which the settlement reaches starget
- U
average degree of consolidation
- Uh
average degree of horizontal consolidation
- Uv
average degree of vertical consolidation
- w
vector of heuristic parameters wj
- w*
optimal heuristic parameters
- ΔH
height of added surcharge
- ΔHi
height of surcharge added at time ti
- ΔU
difference in degree of consolidation with additional surcharge
- Δεi
strain increase
- Δσ
load – that is, stress increase in soil
- Δσadd
stress increase in soil caused by surcharge added at tadd
- Δσemb
remaining stress increase in soil after unloading
- Δσsur
vertical stress increase caused by preloading, including the surcharge
- ε
measurement error
- λ
initial cross-entropy sampling distribution parameter
- σ0′
initial vertical stress
REFERENCES
Discussion on this paper closes 01 April 2025; for further details see p. ii.













