Purpose

This research aims to examine the complex interrelationships of human-related barriers that significantly affect lean construction scheduling in the New Zealand construction industry and rank them to support targeted intervention.

Design/methodology/approach

A qualitative design was used, combining a systematic literature review (SLR) of 77 peer-reviewed studies with semi-structured interviews involving five industry experts. The analysis applied thematic coding and network-based measures, including frequency, degree of centrality and eigenvector centrality, to identify and rank influential factors.

Findings

The SLR produced 615 human-related factors, which were consolidated into 54 unique categories. Analysis revealed six factors as most critical: lower motivation and engagement, inadequate collaboration among stakeholders, weak top management support, cultural resistance to change, a conservative, negative attitude and limited conceptual knowledge. These factors were frequently cited in the literature and held a strong systemic influence in network analysis. Interviews confirmed their practical relevance while also pointing to additional issues such as psychological safety and leadership style. Addressing these human-centred barriers is therefore essential to achieving the intended benefits of lean scheduling.

Research limitations/implications

Generalising findings from the SLR may overlook local details or project-specific outcomes. The primary data were limited to a small expert sample, restricting the breadth of perspectives. In addition, external influences such as financial constraints, supply chain issues and regulatory factors were excluded, which may also affect lean scheduling outcomes.

Practical implications

The results provide clear priorities for practice, including stronger leadership commitment, structured training, enhanced collaboration and strategies to overcome cultural barriers. Implementing these interventions can strengthen lean adoption and improve project outcomes in New Zealand.

Social implications

This research carries important social implications by emphasising the human dimension of productivity in the construction sector. It highlights how motivation, collaboration, leadership and learning culture directly influence not only project outcomes but also workplace well-being and professional development. By addressing these human factors, the study encourages more inclusive, communicative and supportive work environments that value participation and continuous learning. Ultimately, improving these social dynamics can strengthen teamwork, job satisfaction and long-term workforce sustainability within the construction industry.

Originality/value

Previous studies have examined individual factors affecting lean construction scheduling but often in isolation. This research highlights how human-related barriers interact and how their interrelationships influence outcomes. Using network-based methods, including causal loop diagrams and centrality measures, the study identifies not only the most frequent factors but also the most structurally influential ones. Its originality lies in consolidating diverse human factors into distinct categories and ranking them through frequency and centrality, offering a systems perspective beyond traditional analyses.

The construction sector is a cornerstone of global economic growth, contributing about 13% to global GDP and generating annual spending of nearly USD 10 trillion, projected to reach USD 14 trillion by 2025 (Mc Kinsey Global Institute, 2017). Despite its large scale, the industry continues to lag behind other sectors in productivity, with annual growth averaging only 1% compared to 3% in manufacturing (McKinsey Global Institute, 2024). As global demand for infrastructure, housing, and sustainable development intensifies, these inefficiencies create pressure to adopt innovative and waste-reducing practices (Weerapura et al., 2023). In New Zealand, the construction industry mirrors these global trends but faces additional local constraints. It contributes 6.3% to GDP and employs over 10% of the national workforce (MBIE, 2024). Yet productivity remains low due to factors such as housing markets and reliance on imported materials (Kirby et al., 2024). Further challenges include an ageing workforce and a persistent shortage of skilled labour (Kirby et al., 2025). These systemic pressures underscore the need for lean construction methods, which have shown significant benefits internationally but remain slow to be adopted and inconsistent in New Zealand, largely due to persistent human-related barriers.

Lean construction emerged in response to inefficiencies and cost overruns in project delivery (González et al., 2022). Its principles focus on maximising value for the client by eliminating non-value-adding activities, improving workflow reliability, and fostering collaboration among project stakeholders (Katō and Smalley, 2011). Internationally, lean methodologies such as the Last Planner System (LPS) and takt time planning have reported improvements of up to 25% in cost efficiency compared to traditional project management practices (Hasan et al., 2018). These approaches rely not only on technical scheduling tools but also on teams' collective commitment to honouring work promises, communicating effectively, and continuously improving performance (Warid and Hamani, 2023). In practice, however, lean construction often faces obstacles when applied outside of manufacturing because construction projects are temporary, involve multiple stakeholders with competing interests, and operate under uncertain site conditions. Tezel et al. (2018) note that lean is sometimes adopted superficially under client pressure, leading to inefficiencies and disillusionment. Similarly, Vecchio et al. (2023) emphasise that early collaboration and stakeholder engagement are crucial to project success, yet fragmented supply chains frequently undermine these practices.

A critical dimension of lean construction is the influence of human factors on scheduling practices. While many studies have focused on the technical application of lean tools, less attention has been given to how behavioural, organisational, and cultural variables shape implementation outcomes. Hughes and Thorpe (2014) argue that workforce resistance to change and insufficient training frequently derail lean initiatives, while Likita et al. (2024) highlight that poor teamwork and communication exacerbate waste and inefficiency. Kirby et al. (2025) further stress that weak leadership commitment and conservative attitudes towards innovation continue to hinder lean adoption in New Zealand. These findings reveal a significant gap in the literature: existing research often treats lean scheduling inefficiencies as technical issues, rather than recognising the systemic role of human barriers (Hasan et al., 2018; Kirby et al., 2024; Likita et al., 2024; Magnani et al., 2023). The consequence is that lean construction efforts frequently fail to realise their full potential, as individuals' behaviours, skills, and attitudes remain misaligned with the collaborative norms required for success.

This study directly addresses that gap by focusing on the human-related variables that affect lean construction scheduling in New Zealand. By analysing these human-centric challenges, the research aims to provide practical insights into how lean scheduling can be better adapted to local realities. The guiding research question is: What are the human factors affecting the efficiency of lean scheduling in the New Zealand construction industry, and what actions can be recommended to reduce their impact? Addressing this question not only contributes to the academic understanding of lean construction but also offers actionable strategies for industry stakeholders seeking to enhance productivity, reduce waste, and strengthen project performance.

The construction sector is vital to New Zealand's economy, accounting for 6.3% of GDP and employing more than 10% of the national workforce in 2023 (MBIE, 2024). Despite its importance, productivity remains low, with growth rates consistently lagging behind the OECD average (Curtis, 2018; New Zealand Productivity Commission, 2023). These challenges have intensified calls for innovative approaches to improve performance, with lean construction increasingly recognised as a viable solution (Kirby et al., 2024). Derived from the Toyota Production System, lean construction provides a structured framework to minimise waste, enhance workflow reliability, and strengthen collaboration (González et al., 2022; Likita et al., 2024). Techniques such as the Last Planner System and takt time planning have demonstrated substantial gains, including a 54% productivity improvement and early project completion in case studies (Johansen et al., 2021). Beyond efficiency, lean promotes safety, trust, and continuous improvement across project teams (Power et al., 2024; Sarhan et al., 2019). However, in New Zealand, adoption remains fragmented due to skill shortages, limited workforce capability, and cultural resistance to change, leading to partial implementation and reduced benefits (Tezel et al., 2018).

Several studies point to the persistent inefficiency of lean implementation in practice. Despite its theoretical promise, lean construction has not delivered consistent productivity gains across the sector, particularly in regions like New Zealand, where output has fluctuated, with construction's GDP contribution falling from 6.3% to 4.4% in 2023 (MBIE, 2024). Globally, construction productivity has remained stagnant since the mid-twentieth century, even as manufacturing and agriculture achieved transformative gains (Mc Kinsey Global Institute, 2017). Scholars emphasise that many of these shortcomings are linked not to the lean framework itself, but to barriers to its application, including weak leadership commitment, ineffective integration across supply chains, and insufficient workforce capability (Kirby et al., 2025; Likita et al., 2024). These observations suggest that while lean scheduling tools have proven technical value, their success depends on addressing the human and organisational conditions in which they are embedded. As such, research attention has increasingly shifted toward understanding the specific factors that hinder or enable lean scheduling performance.

Among the most critical influences are human-related factors. Studies identify multiple dimensions, including knowledge and skill, behaviour and attitude, communication and collaboration, and decision-making. Skill shortages, an ageing workforce, and insufficient training limit the industry's ability to adapt to new technologies and processes (Chen et al., 2023; Uhrin et al., 2017). Without adequate training, resistance to lean tools is common, as observed in Brazil, Lebanon, and other contexts (De Silva et al., 2025; Hamzeh and Albanna, 2019). Behavioural and cultural factors further complicate implementation, with low motivation, adversarial team cultures, and resistance to change frequently undermining collaboration (Evans and Farrell, 2021; Sarhan et al., 2019; Ugurlu et al., 2021). Poor communication and weak collaboration are repeatedly cited as global barriers that contribute to rework, safety issues, and significant productivity losses (Bayhan et al., 2019; Demirkesen and Bayhan, 2020; Yang et al., 2020). Finally, decision-making processes, which are often constrained by cognitive biases, limited information, or time pressures, can generate waste and heighten risks on site (Purushothaman and Seadon, 2024). While these variables are widely acknowledged in international studies, their interplay within the New Zealand context remains underexplored.

In summary, the literature demonstrates that lean construction has the potential to transform project delivery by reducing waste, enhancing workflow, and fostering collaboration. However, evidence also reveals persistent inefficiencies linked to human factors, such as ineffective training, workforce ageing, a conservative attitude, and poor communication. Although these challenges have been investigated in global studies (Chen et al., 2023; Enshassi et al., 2021; Magnani et al., 2023), there remains limited research examining their specific influence on lean scheduling within the New Zealand construction industry. This gap is significant given New Zealand's unique demographic profile, small and fragmented market, and reliance on imported labour and materials. Addressing this research gap is crucial to understanding how behavioural dynamics shape the implementation of lean scheduling locally, and to developing targeted strategies that can support contractors, consultants, and subcontractors in overcoming these barriers and improving project efficiency.

This study employed a qualitative research design that integrated a systematic literature review (SLR) with expert validation to examine people-centred factors affecting lean construction scheduling. The SLR, conducted in accordance with PRISMA guidelines (Page et al., 2021), ensured methodological transparency and rigour. Seventy-seven peer-reviewed studies published after 2020 were reviewed and thematically coded into eight categories: awareness, behaviour, collaboration, communication, decision making, organisation, skills, and training. The selected studies were sourced internationally and were not limited to the New Zealand context, ensuring that the identified human factors reflect globally reported lean construction challenges. Network analysis further enhanced the process by analysing frequency through an author–factor matrix, identifying key influences using eigenvector and degree of centrality measures, and visualising systemic relationships through causal loop diagrams. To validate and contextualise these findings, semi-structured interviews were held with five experienced professionals from New Zealand's construction industry. Their insights confirmed the relevance of key factors and provided context-specific understanding of how these human elements influence lean scheduling efficiency. Table 1 summarises the data sources, collection methods, and analytical approaches adopted in this study.

Table 1

Summary of data collection and analysis methods

S/NResearch dataCollection methodResearch analysis methods
1Secondary Data Peer-reviewed journal articles, conference papers, and academic publicationsSystematic Literature Review (SLR)Biblometric Analysis (mapping research trends and influential publications)
Thematic Analysis (identifying recurring themes and research gaps)
2Primary Data Industrial experiences and perspectives of construction professionals in New ZealandSemi-Structured Interviews Narrative enquiry and open ended questionNarrative Analysis (interpreting participants' lived experiences)
Thematic Analysis (extracting common patterns and key issues across narratives)
Source(s): Authors’ own work

A systematic literature review (SLR) was undertaken as the primary strategy for collecting secondary data on human factors affecting lean construction scheduling. The review process began with the development of a keyword framework based on four pillars: lean construction, human involvement, influencing factors, and the construction context. Synonyms and Boolean operators were used to create search strings executed across Scopus, ScienceDirect, and EBSCOhost, following defined inclusion and exclusion criteria. Table 2 summarises the search strategy and results. A total of 604 publications were retrieved, of which 77 met the selection criteria and were analysed in detail. These studies provided the foundation for identifying and consolidating human-related factors, which were later examined through thematic and network analysis.

Table 2

Database search strategy and results

DatabaseSearch stringInclusionExclusion
Scopus(“Lean Construction” OR “Lean Management” OR “Lean Enterprise” OR “Lean Thinking”) AND (Factor* OR Barrier* OR Challenge* OR Influence*) AND (Construction OR Building Or Engineering)2020–2025, English, journal and conference papers, engineering and management subject areasNon-English, before 2020, reviews, irrelevant subject categories
ScienceDirect(“Lean Construction” OR “Lean Management” OR “Lean Thinking”) AND (“Human factor” OR Barriers OR Challenges OR “Human impact”) AND (Construction)2020–2025, English, engineering, peer-reviewed research articlesNon-English, before 2020, reviews, conference papers
EBSCO(“Lean Construction” OR “Lean Management” OR “Lean Thinking”) AND (“Human factor” OR Barriers OR Challenges OR “Human impact”) AND (Construction)Past 5 years, English, peer-reviewed, full text, lean construction and project-focused publicationsNon-English, older than 5 years, reviews, conference papers
Source(s): Authors’ own work

3.2.1 Prisma flow Chart and data extraction

The combined database searches yielded 604 records, of which 116 duplicates were removed, leaving 488 unique studies for screening. Titles and abstracts were reviewed against the inclusion criteria, leading to the exclusion of 341 records that were not directly related to lean construction or human barriers. The remaining 147 articles were retrieved in full text and assessed for eligibility. Seventy of these were excluded because they either lacked methodological rigour, addressed technical scheduling models without human-related analysis, or were outside the construction sector. This process resulted in a final set of 77 studies that were included in the systematic review. The selection pathway is illustrated in the PRISMA flow diagram (Figure 1), which shows the progressive refinement of records across the identification, screening, and inclusion stages.

Figure 1
A flowchart illustrating the identification and screening process of studies via databases and registers.The flowchart illustrates the identification and screening process of studies via databases and registers. The process begins with the identification of 604 records from Scopus, Science Direct, and Ebsco. 37 duplicate records are removed before screening. 567 records are screened, and 466 are excluded for not being relevant after abstract and title screening. 101 reports are sought for retrieval, but 4 reports are not retrieved. 97 reports are assessed for eligibility, and 20 reports are excluded for various reasons such as being systematic literature reviews, methodology only, essay type, or lacking relevant detail. Finally, 77 reports of included studies are identified.

Prisma flow diagram. This work is licensed under CC BY 4.0. To view a copy of this license, visit Link to the website. Page et al. (2021) 

Figure 1
A flowchart illustrating the identification and screening process of studies via databases and registers.The flowchart illustrates the identification and screening process of studies via databases and registers. The process begins with the identification of 604 records from Scopus, Science Direct, and Ebsco. 37 duplicate records are removed before screening. 567 records are screened, and 466 are excluded for not being relevant after abstract and title screening. 101 reports are sought for retrieval, but 4 reports are not retrieved. 97 reports are assessed for eligibility, and 20 reports are excluded for various reasons such as being systematic literature reviews, methodology only, essay type, or lacking relevant detail. Finally, 77 reports of included studies are identified.

Prisma flow diagram. This work is licensed under CC BY 4.0. To view a copy of this license, visit Link to the website. Page et al. (2021) 

Close modal

3.2.2 Data extraction and recording

After screening, data from 77 selected studies were systematically extracted to identify human factors influencing lean construction scheduling. Bibliographic details such as author, year, and country were recorded in Microsoft Excel for reference management. Each article was reviewed in full, and relevant text relating to human or behavioural factors was highlighted using EndNote 21, as shown in Figure 2. The extracted data were organised into five columns, recording the factor, description, author's stance, page number, and article ID. This process produced 615-factor entries, forming a structured foundation for subsequent thematic and network analysis.

Figure 2
A computer screen displaying a data screening process using EndNote software.A computer screen showing a data screening process using EndNote 21 software. The screen is divided into multiple sections with various columns such as Author, Year, Title, and Contains. Each row represents a different reference with details filled in the respective columns. The left sidebar includes groups and tags for organizing references. The top menu bar contains options for different actions and searches. The main section of the screen lists references with their respective details, and the right side shows a preview of a selected document titled 'Barriers to the application of lean construction.pdf'.

Data screening using endnote. Authors’ own work using EndNote 21 software

Figure 2
A computer screen displaying a data screening process using EndNote software.A computer screen showing a data screening process using EndNote 21 software. The screen is divided into multiple sections with various columns such as Author, Year, Title, and Contains. Each row represents a different reference with details filled in the respective columns. The left sidebar includes groups and tags for organizing references. The top menu bar contains options for different actions and searches. The main section of the screen lists references with their respective details, and the right side shows a preview of a selected document titled 'Barriers to the application of lean construction.pdf'.

Data screening using endnote. Authors’ own work using EndNote 21 software

Close modal

A “factor” was defined as any explicitly stated human-related barrier, enabler, or behavioural condition influencing lean construction or scheduling performance. During extraction, semantically similar expressions (e.g. “lack of training” and “insufficient lean education”) were recorded separately to preserve the original author's intent. Consolidation into 54 categories was conducted through iterative thematic comparison, in which conceptually overlapping items were merged based on their shared underlying meaning rather than on wording similarity. To enhance coding reliability, extracted items were re-reviewed and cross-checked against original sources to ensure conceptual consistency prior to aggregation.

3.2.3 Thematic analysis, coding, and pattern identification

The recorded data from 615 entries were organised and categorised through thematic analysis to identify recurring patterns among human aspects affecting lean construction scheduling. Each factor was coded and grouped into one of eight themes, with overlapping or duplicated terms standardised for consistency. This process refined the dataset to 54 unique factors, each assigned a thematic code for analysis. Relationships between factors were then examined to determine influence and polarity, defined as positive, negative, or neutral, as shown in Figure 3. These structured relationships served as the foundation for subsequent network and causal loop analyses.

Figure 3
A table comparing barriers of implementation across different articles.The table presents a comparison of barriers to implementation across various articles. It includes columns for article number, title, author, year, factor A, factors, factor B, polarity, page number, and paragraph number. The table lists multiple barriers such as inadequate skilled workforce, lack of respect and trust, lack of continuous lean training, and inadequate technical skill. Each barrier is associated with specific factors and polarities, indicating whether the factor is positive or negative. The data spans articles from 2020 to 2023 and includes authors like Ahmed, Aka, and Aziz.

Interrelationships and polarity among factors. Authors’ own work

Figure 3
A table comparing barriers of implementation across different articles.The table presents a comparison of barriers to implementation across various articles. It includes columns for article number, title, author, year, factor A, factors, factor B, polarity, page number, and paragraph number. The table lists multiple barriers such as inadequate skilled workforce, lack of respect and trust, lack of continuous lean training, and inadequate technical skill. Each barrier is associated with specific factors and polarities, indicating whether the factor is positive or negative. The data spans articles from 2020 to 2023 and includes authors like Ahmed, Aka, and Aziz.

Interrelationships and polarity among factors. Authors’ own work

Close modal

3.2.4 Data analysis tools and process

The previously coded data, together with the developed author–factor matrix and interrelationship matrix, were used for network and system analysis. Vensim software was used to generate the causal loop diagram and calculate centrality, enabling visualisation of the dynamic relationships among factors. Gephi software was then used to compute eigenvector centrality, identifying the most influential nodes within the network. Together, these analytical tools provided a comprehensive understanding of how human factors interact and shape lean construction scheduling efficiency.

Expert interviews were conducted to complement the systematic literature review and provide contextual support for the findings within the New Zealand construction context. The aim was to confirm whether the most influential behavioural factors identified through the SLR align with industry practice. Five experts were purposively selected, each with over five years of experience and direct involvement in lean construction. Participants were recruited through academic and professional networks and provided with information on confidentiality. Interviews were conducted online via Microsoft Teams using a semi-structured format, lasting 20–40 minutes. All sessions were recorded with consent, transcribed, anonymised, and securely stored in AUT OneDrive. As presented in Table 3, the participants represented a balanced mix of academia and industry, including lecturers, researchers, engineers, and senior managers. Although the sample size was limited to five participants, purposive selection prioritised depth of lean construction experience over numerical breadth. The interviews provided contextual alignment with the literature-derived findings and helped assess their practical resonance within the New Zealand setting.

Table 3

Demographic profile of participants

CodeCurrent roleOrganisation typeYears of experienceInterview date
P1Assistant LecturerAcademia714 Aug 2025
P2Project ManagerPrivate Contractor1022 Aug 2025
P3Planning EngineerMain Contractor529 Aug 2025
P4General ManagerPrivate Contractor214 Sept 2025
P5Lean Research ExpertAcademia916 Sept 2025
Source(s): Authors’ own work

This section presents the analytical results from the systematic literature review and thematic coding of 54 unique human variables influencing lean construction scheduling. The analysis interprets structured data to examine interrelationships, frequencies, and influence pathways among factors. Using narrative interpretation, matrix mapping, and systems-thinking tools, it provides a comprehensive understanding of how human variables shape lean scheduling performance. The author–factor and interrelationship matrices, provided in the appendix 1 and 2, formed the analytical foundation. Frequency analysis identified dominant themes, while causal loop and centrality measures highlighted key influential factors. Eigenvector centrality further revealed systemic importance. Expert validation complements these findings with practical industry perspectives.

Figure 4 illustrates the annual distribution of publications between 2020 and 2025. In terms of overall contributions, the United States leads with 7 articles, followed by the United Kingdom and India with 6 each. Other regular contributors include Australia, China, Malaysia, and New Zealand. Countries with 1–2 publications were grouped under “Others,” which includes Brazil, Colombia, Egypt, Finland, Jordan, Qatar, Singapore, and Turkey, with 2 each, alongside 15 nations with 1 each, such as Canada, Chile, Ethiopia, Ghana, and Vietnam. This distribution highlights both the growing interest in lean construction research and its global diversity, though it is concentrated in a smaller number of leading countries.

Figure 4
A bar graph showing the annual distribution of articles by country from 2020 to 2025.A stacked bar graph compares the number of articles published by different countries from 2020 to 2025. The horizontal axis represents the years 2020 to 2025, and the vertical axis represents the number of articles, ranging from 0 to 20. Each bar is divided into segments representing different countries, with each color corresponding to a specific country. The countries included are USA, UK, UAE, Qatar, Peru, Norway, New Zealand, Malaysia, Ireland, India, China, Australia, and others. The graph shows the following data for each year: 2020: USA 3, UK 1, UAE 1, Norway 3, China 2, total 11. 2021: USA 1, UK 1, UAE 1, Qatar 1, Peru 1, Norway 6, total 13. 2022: USA 2, UK 1, Qatar 1, Peru 1, Norway 5, total 11. 2023: USA 1, UK 1, UAE 1, Qatar 1, Peru 1, Norway 7, total 19. 2024: USA 1, UK 3, UAE 1, Norway 8, India 4, total 19. 2025: UK 1, Norway 2, New Zealand 1, total 4.

Annual distribution of articles by country. Authors’ own work

Figure 4
A bar graph showing the annual distribution of articles by country from 2020 to 2025.A stacked bar graph compares the number of articles published by different countries from 2020 to 2025. The horizontal axis represents the years 2020 to 2025, and the vertical axis represents the number of articles, ranging from 0 to 20. Each bar is divided into segments representing different countries, with each color corresponding to a specific country. The countries included are USA, UK, UAE, Qatar, Peru, Norway, New Zealand, Malaysia, Ireland, India, China, Australia, and others. The graph shows the following data for each year: 2020: USA 3, UK 1, UAE 1, Norway 3, China 2, total 11. 2021: USA 1, UK 1, UAE 1, Qatar 1, Peru 1, Norway 6, total 13. 2022: USA 2, UK 1, Qatar 1, Peru 1, Norway 5, total 11. 2023: USA 1, UK 1, UAE 1, Qatar 1, Peru 1, Norway 7, total 19. 2024: USA 1, UK 3, UAE 1, Norway 8, India 4, total 19. 2025: UK 1, Norway 2, New Zealand 1, total 4.

Annual distribution of articles by country. Authors’ own work

Close modal

This analysis examined how often each human factor appeared across the reviewed literature to highlight those most commonly recognised in lean construction research. Using the Author–Factor Matrix, 54 unique factors were evaluated across 77 studies and ranked by frequency. The most cited factor was Inadequate Conceptual Knowledge (A01), appearing in 42 studies, followed by Cultural Resistance to Change (O04, 31 mentions), Lower Motivation and Engagement (B05, 28 mentions), and Lack of Continuous Lean Training (T03, 28 mentions). These reflect recurring organisational, cultural, and skill-related barriers. At the lower end, factors such as CM05 and D03 were mentioned only once, though they may still hold contextual relevance as shown in Table 4 below.

Table 4

Frequency of factors identified in the SLR

S/NCodeFactorsFrequencyRank
1A01Inadequate Conceptual Knowledge42#1
2O04Cultural Resistance to Change31#2
3B05Lower Motivation and Engagement28#3
4T03Lack of Continuous Lean Training28#3
5C03Inadequate Collaboration Between Stakeholders27#4
6O03Inadequate Commitment and Support from Top Management27#4
7B04Individual's Resistance to Change26#5
8B03Conservative and Negative Attitude23#6
9O05Inadequate Engagement from Stakeholders20#7
10A02Inadequate Technical Knowledge18#8
11CM01Inadequate Information Exchange Among Stakeholders17#9
12B08Poor Leadership16#10
13S03Inadequate Skilled Workforce16#10
14C01Lack of Respect and Trust15#11
15CM03Ineffective Communication Among Team Members15#11
16S02Inadequate Technical Skill15#11
17D05Poor Decision-Making Due to Inadequate Knowledge14#12
18B09Lack of Commitment13#13
19S01Lack of Lean Expert13#13
20O02Absence of Lean Culture12#14
21O01Inadequate Motivation or Incentives11#15
22T02Lack of Conceptual Awareness Programs11#15
Source(s): Authors’ own work

A causal loop diagram (CLD) was developed using Vensim software to examine the systemic interactions among behavioural factors. As shown in Figure 5, the diagram illustrates how 54 generalised factors interact through 294 directional linkages, forming a dense network of reinforcing relationships. Based on these mapped relationships, the degree of centrality was calculated to determine the most structurally influential factors. Centrality measures the importance of each factor by assessing its number of incoming and outgoing links, revealing leverage points where interventions can create broader system-wide improvements (Bamakan et al., 2019). The results (Table 5) show “Lower Motivation and Engagement” (B05) and “Inadequate Top Management Support” (O03) as the most central, followed by “Cultural Resistance to Change” (O04) and related collaboration factors.

Figure 5
A causal loop diagram with interconnected nodes and arrows.A causal loop diagram featuring numerous labeled nodes connected by arrows, indicating relationships and feedback loops. The central node is labeled 'Lean Inefficiency', surrounded by various other nodes such as 'A01', 'B05', 'C04', 'D08', and more. Arrows between nodes show directional influences, with some arrows marked by plus or minus signs to indicate the nature of the relationship.

Causal loop diagram. Authors’ own work using Vensim Software

Figure 5
A causal loop diagram with interconnected nodes and arrows.A causal loop diagram featuring numerous labeled nodes connected by arrows, indicating relationships and feedback loops. The central node is labeled 'Lean Inefficiency', surrounded by various other nodes such as 'A01', 'B05', 'C04', 'D08', and more. Arrows between nodes show directional influences, with some arrows marked by plus or minus signs to indicate the nature of the relationship.

Causal loop diagram. Authors’ own work using Vensim Software

Close modal
Table 5

Degree of centrality ranking table

CodeFactorsOut-degreeIn-degreeTotal degreeDegree of centralityRank
B05Lower Motivation and Engagement616221.00#1
O03Inadequate Commitment and Support from Top Management157221.00#1
O04Cultural Resistance to Change317200.91#2
C06Lack of Effective Teamwork212140.64#3
C07Inadequate Internal Collaboration212140.64#3
B03Conservative and Negative Attitude122140.64#3
A01Inadequate Conceptual Knowledge85130.59#4
C03Inadequate Collaboration Between Stakeholders49130.59#4
B04Individual's Resistance to Change310130.59#4
B09Lack of Commitment58130.59#4
C01Lack of Respect and Trust102120.55#5
B08Poor Leadership111120.55#5
T03Lack of Continuous Lean Training83110.50#6
O02Absence of Lean Culture38110.50#6
O05Inadequate Engagement from Stakeholders64100.45#7
C04Ineffective Planning010100.45#7
CM03Ineffective Communication Among Team Members64100.45#7
A02Inadequate Technical Knowledge3690.41#8
D05Poor Decision-Making Due to Inadequate Knowledge1670.32#9
S01Lack of Lean Expert7070.32#9
D08Lack Of Time4370.32#9
S02Inadequate Technical Skill2460.27#10
S03Inadequate Skilled Workforce5160.27#10
S04Lack of Experience6060.27#10
CM01Inadequate Information Exchange Among Stakeholders2460.27#10
A08Lack of Standerdised Knowledge5160.27#10
Source(s): Authors’ own work

Network edges represent co-occurrence relationships identified within the reviewed studies, indicating conceptual association rather than causal dependency. Centrality measures were employed to assess structural prominence within this conceptual network, identifying factors occupying influential positions within the interconnected structure. While frequency reflects regularity in literature, centrality captures the quality of relationships, thereby reducing the risk of equating popularity with systemic influence.

Eigenvector centrality is a robust metric in network analysis that identifies the most influential nodes in a system by considering not just the number of connections or degree of a node, but also the importance of the nodes it is connected to (Bienenstock and. Unlike degree centrality, which treats all connections equally, eigenvector centrality gives more weight to links connected to already well-connected nodes.

Based on the interrelationship matrix developed in the previous section, eigenvector centrality values were calculated using Gephi 0.10, which is a specialised network visualisation and analysis tool (Link to the website). The output was normalised using the following formula:

The results were used to rank the most influential factors within the system, as shown in Table 6. These findings are visually represented in Figure 6, where the node size reflects the relative centrality score. The larger the node, the more structurally influential the factor is in the network.

Table 6

Eigenvector centrality ranking

CodeFactorsEigenvector centralityNormalised value (centrality/Norm)Rank
B05Lower Motivation and Engagement1.0000.380#1
O04Cultural Resistance to Change0.9240.351#2
O03Inadequate Commitment and Support from Top Management0.8400.319#3
B03Conservative and Negative Attitude0.7790.296#4
C07Inadequate Internal Collaboration0.6960.265#5
B08Poor Leadership0.6550.249#6
B09Lack of Commitment0.6120.233#7
C01Lack of Respect and Trust0.5980.228#8
A01Inadequate Conceptual Knowledge0.5940.226#9
C03Inadequate Collaboration Between Stakeholders0.5770.220#10
O02Absence of Lean Culture0.5710.217#11
C06Lack of Effective Teamwork0.5520.210#12
O05Inadequate Engagement from Stakeholders0.5490.209#13
CM03Ineffective Communication Among Team Members0.4990.190#14
B04Individual's Resistance to Change0.4840.184#15
 Norm (Magnitude)2.6293 
Source(s): Authors’ own work
Figure 6
A network graph displaying connections between various nodes labeled with alphanumeric codes.A network graph displaying connections between various nodes labeled with alphanumeric codes. The nodes are interconnected with lines of varying colors and thicknesses, indicating the strength or type of connections. The graph is densely populated with nodes and lines, suggesting a complex network structure. The nodes are labeled with codes such as B03, B05, O04, and others, and are positioned in a circular layout. The lines connecting the nodes form a web-like pattern, with some nodes appearing more central and connected than others. The graph does not include specific axes or units, focusing instead on the relationships and centrality of the nodes within the network.

Eigenvector centrality network graph. Authors’ own work using Gaphi Software

Figure 6
A network graph displaying connections between various nodes labeled with alphanumeric codes.A network graph displaying connections between various nodes labeled with alphanumeric codes. The nodes are interconnected with lines of varying colors and thicknesses, indicating the strength or type of connections. The graph is densely populated with nodes and lines, suggesting a complex network structure. The nodes are labeled with codes such as B03, B05, O04, and others, and are positioned in a circular layout. The lines connecting the nodes form a web-like pattern, with some nodes appearing more central and connected than others. The graph does not include specific axes or units, focusing instead on the relationships and centrality of the nodes within the network.

Eigenvector centrality network graph. Authors’ own work using Gaphi Software

Close modal

To explore how human barriers interact systemically, a loop cycle analysis was performed using the causal loop diagram results. Unit weight measures the number of unique factors in each loop, while centrality weight reflects how structurally influential the loop is. The results, summarised in Table 7, show that Loops 1 and 2 contain the most factors (21 each), followed by Loops 3 and 4 (20 each). Loop 3 achieved the highest centrality score of 11.27, dominated by critical factors such as lower motivation (B05), weak management support (O03), and inadequate training (T03). High-weight loops demonstrate how inefficiencies reinforce each other, while lower-weight loops reveal localised behavioural issues and potential leverage points for intervention within lean construction systems.

Table 7

Key feedback loops with unit and centrality weight

Loop cycleUnit weightUnit weight rankCentrality weightCentrality weight rank
1C01 → O02 → O04 → C03 → O05 → T03 → A04 → CM05 → B01 → CM03 → D05 → O03 → D08 → B03 → B08 → B04 → B09 → C07 → C06 → CM01 → B05 → C0121#110.91#3
2C01 → O02 → O04 → B09 → C07 → C06 → CM01 → C03 → O05 → T03 → A04 → CM05 → B01 → CM03 → D05 → O03 → D08 → B03 → B08 → B04 → B05 → C0121#110.91#3
3C01 → CM03 → D05 → O03 → D08 → B03 → B08 → C07 → C06 → CM01→ C03 → O05 → T03 → A01 → A06 → O02 → O04 → B09 → B04 → B05 → C0120#211.27#1
4T03 → A04 → CM05 → B01 → CM03 → D05 → O03 → T01 → S02 → A02 → O02 → O04 → B09 → B04 → B05 → C07 → C06 → CM01 → C03 → O05 → T0320#29.77#4
5C01 → CM03 → D05 → O03 → D08 → B03 → B08 → C07 → C06 → CM01 → C03 → O05 → T03 → A01 → O02 → O04 → B09 → B04 → B05 → C0119#311.09#2
6CM03 → D05 → O03 → D08 → B03 → B08 → B04 → B05 → C07 → O04 → B09 → C06 → CM01 → C03 → O05 → CM03158.95
7A01 → A06 → O02 → B05 → B04 → B09 → C06 → C07 → O04 → C03 → O05 → CM03 → D05 → O03 → T01 → A01158.68
8S02 → A02 → O02 → B05 → B04 → B09 → C06 → C07 → O04 → C03 → O05 → CM03 → D05 → O03 → T01 → S02158.59
9A02 → O02 → O04 → B09 → B04 → B05 → C07 → C06 → CM01 → C03 → O05 → CM03 → D05 → O03 → T01 → A02158.59
10T03 → A01 → D05 → O03 → T01 → S02 → A02 → B05 → C03 → C06 → C07 → O04 → O05 → T0313#Mid Value7.55#Mid Value
11B04 → B09 → C06 → CM01 → B05 → B0453.09
12D05 → O03 → D08 → B03 → B08 → D0552.82
13C03 → O05 → C07 → C06 → CM01 → C0352.59
14O04 → B09 → B05 → C07 → O0443.14
15O05 → B05 → C07 → O04 → O0543
16B05 → C07 → C06 → CM01 → B0542.55
17O03 → D08 → B03 → O0331.95
18C03 → C06 → CM01 → C033#Lowest1.5#Lowest
19B03 → B08 → D08 → B033#Lowest1.5#Lowest
Source(s): Authors’ own work

As shown in Table 8, collaboration, leadership support, and motivation were the most frequently emphasised by participants. The other three factors, inadequate conceptual knowledge, conservative attitude, and cultural resistance to change, were also highlighted, though with slightly less frequency, confirming their ongoing significance in practice. These results indicate that the human barriers identified through global research are also visible in the New Zealand context.

Table 8

Summary of expert validation with SLR findings

Theme / FactorMentioned (n = 5)Alignment with SLR findingsParticipant insight
Motivation and Engagement (B05)5Aligned – motivation seen as central to lean adoption“The challenge is not only about the tools themselves but about how motivated people are to use them …” (P2)
Collaboration (C03)4Aligned – collaboration highlighted as essential“Collaboration is the key. It is the core of lean construction …” (P1)
Leadership Support (O03)4Aligned – leadership commitment viewed as critical“Every system implementation … requires the full support and commitment from leadership …” (P3)
Cultural Resistance (O04)5Aligned – resistance to new practices still prevalent“Many experienced people prefer to continue with the methods they already know …” (P3)
Conservative Attitudes (B03)3Aligned – hierarchical attitudes seen as barriers“We are still stuck with the hierarchy of leadership …” (P5)
Conceptual Knowledge (A01)3Aligned – knowledge gaps weaken lean practice“Understanding lean principles is very important …” (P1)
Psychological Safety1Emergent – highlighted as missing from current factors“They may be afraid to be replaced by these new methods and tools …” (P1)
Transformational Leadership1Emergent – raised as an additional human factor“Transformational leadership encourages lean culture …” (P5)
Source(s): Authors’ own work

This section interprets the findings by focusing on the human factors that most strongly influence inefficiencies in lean construction scheduling. Drawing on results from the systematic literature review, degree of centrality, interrelation mapping, and expert validation, the analysis identifies factors with both academic and practical significance in the New Zealand context. A comparative assessment was conducted using three analytical dimensions: SLR frequency, degree of centrality, and eigenvector centrality. This multi-layered approach highlights not only how frequently each factor appears in the literature but also its structural importance within the interconnected network of human barriers. Table 9 summarises the comparative results, showing the top-ranked factors across all three measures.

Table 9

Comparison of top-ranked human factors

A table comparing top-ranked human factors across three metrics.
A table comparing top-ranked human factors across three metrics.

Six factors emerged as the most critical contributors to lean scheduling inefficiencies: lower motivation and engagement (B05), inadequate collaboration between stakeholders (C03), inadequate commitment and support from top management (O03), cultural resistance to change (O04), conservative and negative attitude (B03), and inadequate conceptual knowledge (A01). Their consistent appearance across multiple analyses indicates that inefficiencies in lean scheduling arise from complex human interactions rather than isolated issues. Together, these six factors provide the foundation for developing targeted strategies to enhance the application of lean in New Zealand.

The core network structure was derived from a global systematic literature review, indicating that the identified patterns reflect internationally recognised lean construction challenges. The New Zealand interviews provided contextual validation, suggesting that the findings are transferable to similar project-based construction markets.

Lower Motivation and Engagement (B05): Motivation is central to lean practices such as the Last Planner System (LPS), which depend on active participation. However, perceived complexity and meeting fatigue often lead to disengagement, weakening collaboration (Hua and Schwartz, 2021). Motivation drives proactive behaviours like risk anticipation and constraint management (Power et al., 2024). Strategies such as linking promotions or recognition to lean achievements can enhance engagement (Likita et al., 2025). As one expert noted, “The challenge is not only about the tools but about how motivated people are to use them” (P2). Therefore, sustaining motivation is crucial for transforming lean practices into a shared mindset that drives continuous improvement.

Inadequate Collaboration Between Stakeholders (C03): Effective collaboration among contractors, consultants, and suppliers underpins lean success. Poor collaboration disrupts workflows and reduces trust. Studies show that LPS enhances coordination (Bajjou and Chafi, 2022) and that interdepartmental cooperation improves project efficiency (Berawi et al., 2023). Conversely, fragmentation and misaligned goals increase inefficiencies (Hyarat et al., 2024). Experts reinforced that collaboration forms “the people side of lean pillars” (P1). In short, it acts as a systemic barrier that weakens trust, disrupts coordination, and prevents lean construction from achieving its full efficiency potential.

Inadequate Commitment and Support from Top Management (O03): Leadership commitment determines whether lean initiatives are sustained or superficial. Without consistent management support, motivation and accountability weaken (Hughes and Thorpe, 2014). Visible leadership engagement through resources, follow-ups, and cultural endorsement enhances adoption (Likita et al., 2024). Expert feedback confirmed that strong managerial backing is essential for maintaining site-level enthusiasm and embedding lean culture. Hence, it weakens the cultural and motivational foundations of lean, highlighting that sustained leadership commitment is crucial. These findings are also consistent with broader organisational and leadership research, which emphasises the central role of culture and managerial commitment in shaping behavioural change within complex project environments.

Cultural Resistance to Change (O04): Cultural inertia and adversarial traditions remain major barriers to lean transformation. Research across China, Turkey, and the Middle East links hierarchical and conservative work cultures to limited lean adoption (Bayhan et al., 2023; Ugurlu et al., 2021). Similar patterns exist in New Zealand, where ingrained habits and scepticism toward new methods continue to impede change. Therefore, cultural resistance reinforces traditional practices and obstructs innovation, and thereby acts as a major barrier to cultural transformation.

Conservative and Negative Attitude (B03): At the individual level, conservative mindsets restrict innovation and openness to new tools (Kirby et al., 2025). Negative perceptions of lean can lead to disengagement, preventing systems such as LPS from achieving their full benefits (Sarhan et al., 2019). Experts emphasised that entrenched attitudes among senior staff often slow progress. In short, this factor creates behavioural rigidity that limits adaptability, open-mindedness, and continuous learning within lean teams.

Inadequate Conceptual Knowledge (A01): A limited understanding of lean concepts reduces the effectiveness of implementation. Insufficient training creates confusion and resistance (De Silva et al., 2025; Hamzeh and Albanna, 2019). Knowledge-sharing across teams enhances collective capability (Chen et al., 2023; Malvik et al., 2024). Expert interviews confirmed ongoing conceptual gaps in New Zealand's workforce, underscoring the need for structured lean education. Therefore, this factor prevents teams from translating lean theory into effective practice, making targeted education and knowledge exchange essential.

Causal loop analysis reveals how behavioural dynamics interact systemically to influence lean construction scheduling. Reinforcing loops illustrate how behavioural barriers such as low motivation, poor communication, and resistance to change compound over time. Loops with the highest unit and centrality weights, particularly Loops 1 to 5, represent the most influential feedback cycles, involving interlinked factors that perpetuate inefficiencies. Six key factors recur across these loops: lower motivation (B05), limited management support (O03), cultural resistance (O04), poor collaboration (C03), conservative attitude (B03), and insufficient conceptual knowledge (A01).

Among them, Loops 1 and 3 are the most significant. Loop 1, with the highest unit weight, demonstrates how a lack of respect and trust (C01) triggers weak culture, poor collaboration, and limited training, leading to low motivation and poor decision-making. Loop 3, with the highest centrality weight, highlights how poor leadership, negative attitude, and weak communication reinforce each other. Both loops show that improving trust, leadership, and collaboration is crucial to breaking self-reinforcing behavioural patterns that sustain inefficiencies. Expert interviews confirmed this, noting that leadership commitment and cultural support are essential to overcoming resistance and promoting collaborative lean practices.

Loop 1:

C01 → O02 → O04 → C03 → O05 → T03 → A04 → CM05 → B01 → CM03 → D05 → O03 → D08 → B03 → B08 → B04 → B09 → C07 → C06 → CM01 → B05 → C01

Loop 3:

C01 → CM03 → D05 → O03 → D08 → B03 → B08 → C07 → C06 → CM01 → C03 → O05 → T03 → A01 → A06 → O02 → O04 → B09 → B04 → B05 → C01

The efficiency of lean construction scheduling is shaped by a wide range of human factors that extend beyond technical processes. This study found recurring challenges such as skill shortages, an ageing workforce, training issues, low motivation, cultural resistance, and weak collaboration. These issues disrupt workflow reliability, delay project delivery, and limit the expected benefits of lean practices. Their influence is systemic rather than isolated, affecting project performance at multiple stages.

A qualitative design was adopted, using a systematic literature review (SLR) and expert interviews to capture both global evidence and local perspectives. The SLR analysed 77 studies, identifying 615 factors that were refined into 54 categories. Network analysis revealed six factors as most critical: lower motivation and engagement (B05), inadequate collaboration between stakeholders (C03), inadequate commitment and support from top management (O03), cultural resistance to change (O04), conservative and negative attitude (B03), and inadequate conceptual knowledge (A01). Expert interviews confirmed their relevance and highlighted additional themes, including psychological safety and transformational leadership.

These results address the research objectives by identifying the most influential people-centric factors and proposing strategies to mitigate their impact. The study indicates that interventions should target structurally influential factors rather than isolated variables. Centrality analysis suggests that leadership commitment, motivation, collaboration, and lean literacy function as leverage points within the broader relational system. Addressing these high-centrality factors first may generate wider systemic improvement and reduce the risk of fragmented or superficial lean adoption.

This research uniquely combines a systematic literature review with systems thinking and network analysis to explore how human factors collectively influence lean construction scheduling. Unlike previous studies that treat these factors separately, it examines their systemic interconnections using causal loop diagrams and centrality measures. A key innovation is the use of eigenvector centrality to identify the most structurally influential factors within the network. By integrating frequency and relational influence, this study provides a holistic framework for understanding and improving lean practices in New Zealand's construction industry. The study is primarily a systems-oriented synthesis of global literature, supported by contextual expert perspectives.

The contribution of this study lies not in identifying new human factors, but in structuring established factors as an interconnected system and distinguishing between prevalence and structural influence. By applying network centrality analysis, the research advances lean construction knowledge beyond descriptive barrier lists and provides actionable prioritisation for managerial intervention.

The centrality analysis identifies six structurally influential factors that function as leverage points within the relational network. This suggests that leadership commitment, motivation, collaboration, and lean literacy should be prioritised as foundational conditions before tool-based optimisation. Such sequencing shifts lean implementation from a procedural focus to a behavioural systems perspective, reducing the risk of superficial adoption.

This study is grounded in socio-technical systems theory and systems thinking, which conceptualise project performance as emerging from interconnected social and technical elements. By applying network and causal loop analysis, it extends behavioural project management research through empirically mapping systemic human interdependencies in lean construction scheduling.

This study contributes to theory and practice by showing that inefficiencies in lean construction scheduling stem not only from operational issues but also from systemic behavioural interactions. Through thematic, causal loop, and network analyses, it demonstrates how factors such as resistance, disengagement, and fragmentation reinforce inefficiencies. The research links qualitative insights with network theory, offering a framework for analysing human factors within interconnected systems. Practically, six key factors, including low motivation, weak collaboration, poor leadership support, cultural resistance, conservative attitude, and limited knowledge, highlight where targeted interventions should focus to enhance collaboration, leadership, and learning, fostering sustainable lean practices in New Zealand construction.

This study offers valuable insights into the human factors affecting lean construction scheduling in New Zealand, but it has several limitations. The systematic literature review used only peer-reviewed sources, excluding grey literature that could add practical context. Synthesising global findings may have diluted local nuances, and the five expert interviews, though rich in insight, limited the diversity of industry perspectives. While the sample size was limited, future research may expand participant representation to strengthen empirical robustness and broader industry applicability. The study also focused mainly on human-related variables, omitting external influences such as financial pressures or supply chain issues. Future research should expand participation, explore themes such as psychological safety and leadership style, and apply mixed-methods approaches to enhance generalisability and practical relevance.

Future research may examine causal relationships among the identified factors to understand better how these dynamics evolve over time. Further studies could also test the framework's transferability to other project-based industries.

The authors acknowledge the valuable contributions of the five construction professionals who participated in the expert validation interviews. This study involved voluntary participation, and all interviewees provided informed consent before data collection. No personal or identifying information was obtained or included in the analysis. According to the AUT ethical review policy (exemption policy 6.7), this type of research was exempt from requiring formal ethics approval. The author also wishes to thank the academic supervisors and colleagues for their guidance and constructive feedback throughout this research.

The supplementary material for this article can be found online

Bajjou
,
M.S.
and
Chafi
,
A.
(
2022
), “
Exploring the critical waste factors affecting construction projects
”,
Engineering, Construction and Architectural Management
, Vol. 
29
No. 
6
, pp. 
2268
-
2299
, doi: .
Bamakan
,
S.M.H.
,
Nurgaliev
,
I.
and
Qu
,
Q.
(
2019
), “
Opinion leader detection: a methodological review
”,
Expert Systems with Applications
, Vol. 
115
, pp. 
200
-
222
, doi: .
Bayhan
,
H.G.
,
Demirkesen
,
S.
and
Jayamanne
,
E.
(
2019
), “
Enablers and barriers of lean implementation in construction projects [Conference paper]
”,
IOP Conference Series: Materials Science and Engineering
, Vol. 
471
, 022002, doi: .
Bayhan
,
H.G.
,
Demirkesen
,
S.
,
Zhang
,
C.
and
Tezel
,
A.
(
2023
), “
A lean construction and BIM interaction model for the construction industry
”,
Production Planning and Control
, Vol. 
34
No. 
15
, pp. 
1447
-
1474
, doi: .
Berawi
,
M.A.
,
Sari
,
M.
,
Miraj
,
P.
,
Saroji
,
G.
and
Susantono
,
B.
(
2023
), “
Lean construction practice on toll road project improvement: a case study in developing country
”,
Civil Engineering Journal (Iran)
, Vol. 
9
No. 
12
, pp. 
3186
-
3201
, doi: .
Chen
,
W.
,
Yang
,
Z.
,
Yan
,
H.
and
Zhao
,
Y.
(
2023
), “
Promoting construction labor professionalization: an evolutionary game perspective
”,
Sustainability
, Vol. 
15
No. 
12
, p.
9688
, doi: .
Curtis
,
M.
(
2018
), “Productivity in New Zealand's construction Industry 2017”, in
(SR388 Productivity in the Construction Industry 2017 (January 2020)
,
Issue, available at:
 Link to the website
De Silva
,
S.H.
,
Ranadewa
,
K.A.T.O.
and
Rathnasinghe
,
A.P.
(
2025
), “
Barriers and strategies for implementing lean six sigma in small- and medium sized enterprises (SMEs) in construction industry: a fuzzy TOPSIS analysis
”,
Construction Innovation
, Vol. 
25
No. 
2
, pp. 
510
-
551
, doi: .
Demirkesen
,
S.
and
Bayhan
,
H.G.
(
2020
), “
A lean implementation success model for the construction industry
”,
EMJ - Engineering Management Journal
, Vol. 
32
No. 
3
, pp. 
219
-
239
, doi: .
Enshassi
,
A.
,
Saleh
,
N.
and
Mohamed
,
S.
(
2021
), “
Barriers to the application of lean construction techniques concerning safety improvement in construction projects
”,
International Journal of Construction Management
, Vol. 
21
No. 
10
, pp. 
1044
-
1060
, doi: .
Evans
,
M.
and
Farrell
,
P.
(
2021
), “
Barriers to integrating building information modelling (BIM) and lean construction practices on construction mega-projects: a Delphi study
”,
Benchmarking
, Vol. 
28
No. 
2
, pp. 
652
-
669
, doi: .
González
,
V.A.
,
Hamzeh
,
F.
and
Alarcón
,
L.F.
(
2022
),
Lean Construction 4.0 : Driving a Digital Revolution of Production Management in the AEC Industry
,
Routledge
, doi: .
Hamzeh
,
F.
and
Albanna
,
R.
(
2019
), “
Developing a tool to assess workers' understanding of lean concepts in construction
”,
Annual Conference of the International Group for Lean Construction
, pp. 
179
-
190
, doi: .
Hasan
,
A.
,
Baroudi
,
B.
,
Elmualim
,
A.
and
Rameezdeen
,
R.
(
2018
), “
Factors affecting construction productivity: a 30 year systematic review
”,
Engineering, Construction and Architectural Management
, Vol. 
25
No. 
7
, pp. 
916
-
937
, doi: .
Hua
,
D.
and
Schwartz
,
T.
(
2021
), “
Lps implementation using physical and digital visual management-based tools: a case study in Luxembourg
”,
IGLC 2021-29th Annual Conference of the International Group for Lean Construction - Lean Construction in Crisis Times: Responding to the Post-Pandemic AEC Industry Challenges
, pp. 
65
-
74
, doi: .
Hughes
,
R.
and
Thorpe
,
D.
(
2014
), “
A review of enabling factors in construction industry productivity in an Australian environment
”,
Construction Innovation
, Vol. 
14
No. 
2
, pp. 
210
-
228
, 17107547, doi:
Hyarat
,
E.
,
Montalbán-Domingo
,
L.
and
Pellicer
,
E.
(
2024
), “
Lean constructions barriers in Jordan's building sub-sector: a comprehensive knowledge framework
”,
Ain Shams Engineering Journal
, Vol. 
15
No. 
5
, 102703, doi: .
Johansen
,
P.
,
Christensen
,
S.
,
Neve
,
H.H.
and
Wandahl
,
S.
(
2021
), “
Lean renovation – a case study of productivity, flow, and time improvements
”,
Proc. 29th Annual Conference of the International Group for Lean Construction (IGLC)
, pp. 
839
-
848
, doi: .
Katō
,
I.
and
Smalley
,
A.
(
2011
),
Toyota Kaizen Methods : The Core of Toyota's Lean Skill Set
,
CRC Press
, doi: .
Kirby
,
M.
,
Rotimi
,
F.E.
and
Naismith
,
N.
(
2024
), “
Factors for improving productivity in the New Zealand residential construction sector
”,
Journal of Engineering, Design and Technology
, Vol. 
23
No. 
5
, pp. 
1712
-
1728
, doi: .
Kirby
,
M.
,
Rotimi
,
F.E.
and
Naismith
,
N.
(
2025
), “
A multidimensional analysis of strategies for improving New Zealand residential construction productivity
”,
Ain Shams Engineering Journal
, Vol. 
16
No. 
3
, 103274, doi: .
Likita
,
A.J.
,
Jelodar
,
M.B.
,
Vishnupriya
,
V.
and
Rotimi
,
J.O.B.
(
2024
), “
Lean and BIM integration benefits construction management practices in New Zealand
”,
Construction Innovation
, Vol. 
24
No. 
1
, pp. 
106
-
133
, doi: .
Likita
,
A.J.
,
Jelodar
,
M.B.
,
Vishnupriya
,
V.
and
Rotimi
,
J.O.B.
(
2025
), “
A guideline for BIM and lean integrated construction practice
”,
Smart and Sustainable Built Environment
, Vol. 
14
No. 
4
, pp. 
1264
-
1291
, doi: .
Magnani
,
F.
,
Siadat
,
A.
,
Caillaud
,
E.
and
Gaudichau
,
O.
(
2023
), “
Defining lean experts' roles and behavioral competencies during lean adoption: a case study of groupe PSA
”,
The TQM Journal
, Vol. 
36
No. 
4
, pp. 
1054
-
1073
, doi: .
Malvik
,
T.O.
,
Torp
,
O.
and
Johansen
,
A.
(
2024
), “
Awareness, understanding, and use of lean construction in the Norwegian construction industry
”,
Lean Construction Journal
, pp. 
29
-
58
, doi:
MBIE
(
2024
),
Key New Zealand Economic and Industry Trends
,
Ministry of Business, Innovation & Employment
,
available at:
 Link to the website (
accessed
 2 April).
McKinsey Global Institute
(
2017
),
Reinventing Construction: a Route to Higher Productivity
,
M. Company
,
available at:
 Link to the website
McKinsey Global Institute
(
2024
),
Delivering on Construction Productivity is no Longer Optional
,
M. Company
,
available at:
 Link to the website
New Zealand Productivity Commission
(
2023
),
Productivity by the Numbers
,
New Zealand Productivity Commission
,
available at:
 Link to the website
Page
,
M.J.
,
Moher
,
D.
,
Bossuyt
,
P.M.
,
Boutron
,
I.
,
Hoffmann
,
T.C.
,
Mulrow
,
C.D.
,
Shamseer
,
L.
,
Tetzlaff
,
J.M.
,
Akl
,
E.A.
,
Brennan
,
S.E.
,
Chou
,
R.
,
Glanville
,
J.
,
Grimshaw
,
J.M.
,
Hróbjartsson
,
A.
,
Lalu
,
M.M.
,
Li
,
T.
,
Loder
,
E.W.
,
Mayo-Wilson
,
E.
,
McDonald
,
S.
,
McGuinness
,
L.A.
,
Stewart
,
L.A.
,
Thomas
,
J.
,
Tricco
,
A.C.
,
Welch
,
V.A.
,
Whiting
,
P.
and
McKenzie
,
J.E.
(
2021
), “
PRISMA 2020 explanation and elaboration: updated guidance and exemplars for reporting systematic reviews
”,
BMJ
, Vol. 
372
, n160, doi: .
Power
,
W.
,
Sinnott
,
D.
and
Lynch
,
P.
(
2024
), “
Takt complementing last planner® system on residential construction projects
”,
Construction Economics and Building
, Vol. 
24
Nos
4-5
, pp. 
58
-
80
, doi: .
Purushothaman
,
M.B.
and
Seadon
,
J.
(
2024
), “
System-wide construction waste and their connectivity to construction phases, impacting 5M factors and effects: a systematic review
”,
Smart and Sustainable Built Environment
, Vol. 
13
No. 
2
, pp. 
354
-
369
, doi: .
Sarhan
,
J.G.I.
,
Xia
,
B.
,
Fawzia
,
S.
,
Karim
,
A.
,
Olanipekun
,
A.O.
and
Coffey
,
V.
(
2019
), “
Framework for the implementation of lean construction strategies using the interpretive structural modelling (ISM) technique
”,
Engineering Construction and Architectural Management
, Vol. 
27
No. 
1
, pp. 
1
-
23
, doi: .
Tezel
,
A.
,
Koskela
,
L.
and
Aziz
,
Z.
(
2018
), “
Lean thinking in the highways construction sector: motivation, implementation and barriers
”,
Production Planning and Control
, Vol. 
29
No. 
3
, pp. 
247
-
269
, doi: .
Ugurlu
,
D.
,
Harris
,
N.
and
Demirkesen
,
S.
and
University of Salford
and
Gebze Technical University
(
2021
), “
A framework for implementing lean in the Turkish construction industry
”,
Journal of Construction Engineering Management and Innovation
, Vol. 
4
No. 
3
, pp. 
117
-
133
, doi: .
Uhrin
,
Á.
,
Bruque-Cámara
,
S.
and
Fuentes
,
J.M.
(
2017
), “
Lean production, workforce development and operational performance
”,
Management Decision
, Vol. 
55
No. 
1
, pp. 
103
-
118
, doi: .
Vecchio
,
V.
,
Abellanosa
,
A.D.
,
Konwat
,
B.
,
Wei
,
Y.
and
Hamzeh
,
F.
(
2023
), “
Collaborative dialogue during the pre-tendering phase to maximise project value generation
”,
Proceedings of the 31st Annual Conference of the International Group for Lean Construction (IGLC31)
, pp. 
333
-
343
, doi: .
Warid
,
O.
and
Hamani
,
K.
(
2023
), “
Lean construction in the UAE: implementation of last planner system®
”,
Lean Construction Journal
, Vol. 
2023
, pp. 
1
-
20
, doi: .
Weerapura
,
V.
,
Sugathadasa
,
P.T.R.S.
,
Silva
,
M.M.D.
,
Nielsen
,
I.
and
Thibbotuwawa
,
A.
(
2023
), “
Feasibility of digital twins to manage the operational risks in the production of a ready-mix concrete plant
”,
Buildings
, Vol. 
13
No. 
2
, p.
447
, doi: .
Yang
,
R.
,
Wakefield
,
R.
,
Lyu
,
S.
,
Jayasuriya
,
S.
,
Han
,
F.
,
Yi
,
X.
,
Yang
,
X.
,
Amarasinghe
,
G.
and
Chen
,
S.
(
2020
), “
Public and private blockchain in construction business process and information integration
”,
Automation in Construction
, Vol. 
118
, 103276, doi: .
Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) license. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at Link to the terms of the CC BY 4.0 licence.

Supplementary data

or Create an Account

Close Modal
Close Modal